CENTRAL CHILLER REPAIRS

Aviation and Seaport Committee · 2026-05-11 · resolution

Miami-Dade County Commissioners ratified an emergency contract (E-10658) for Central Chiller Plant Condenser Water Repairs (Phase 1) to Botas Engineering, Inc. for $305,228.00. This action addresses critical failures in the condenser water system at Miami International Airport (MIA), impacting cooling capacity and posing an operational emergency. Phase 1 involves engineering services to assess and redesign repairs for cooling towers CT-1, CT-2, CT-3, CT-5, CT-6, CT-7, and CT-8. A separate Phase 2 for construction services, with an anticipated budget of $35 million, will be presented later. The contract was ratified on June 2, 2026.