Skip to main content

Sé el Primero, Construye Relaciones Duraderas

CHANGE ORDER NO. 2 WITH JOHN BELL CONSTRUCTION, INC.

Board of County Commissioners · 2026-06-02 · resolution

Miami-Dade County approved Change Order No. 2 for the Coconut Grove Playhouse Phase 1 project, increasing the contract amount by $1,812,258.98 due to unforeseen structural deterioration and required repairs to the historic gateway building's facade walls and bracing. The total contract amount is now $6,805,189.97. Funding is from Convention Development Tax Bonds (Special Obligation Bond Series 2005). The original contract and Change Order No. 1 were approved under delegated authority, but this increase required Board approval. No public comment was noted in the document.

Follow this across meetings

Applicants and firms

Mira los negocios reales detrás de estos números

Obtén los registros reales, con direcciones y directivos, gratis por 7 días. Sin tarjeta de crédito.

Comienza tu prueba gratis