C. Utility Underground Update
June 15, 2026, Regular City Council Meeting · 2026-06-15 · agenda_item
The City of Destin is reviewing an update on a utility undergrounding project. Accurate Drilling Systems (ADS) was awarded a contract for this work, which involves undergrounding utilities. The project has experienced delays due to design flaws identified by FPL, material procurement issues, and sizing problems. The city council is considering a motion to impose liquidated damages for the delays while allowing the City Manager to negotiate a mitigation plan. This project would involve significant underground utility work, potentially including trenching, conduit installation, and utility connections. Contractors specializing in underground utility construction, drilling, and related trades could find opportunities as the project moves forward and mitigation plans are finalized. Early engagement with the city and project managers may provide insight into upcoming needs.
- contract duration
- 560 days
- substantial completion date
- May 18, 2026
- requested extension
- 115 days
- liquidated damages
- 1,500 per day
- motion vote
- 7-0
Industries that could win this work
- Utilities (Sub)
- Site Prep, Grading & Hardscape
- Electrical
- Plumbing
- Construction (Other)
- Building & Industrial Supply
- Engineering & Architecture
- Legal Services
- Waste Management
Follow this across meetings
Applicants and firms
Mira los negocios reales detrás de estos números
Obtén los registros reales, con direcciones y directivos, respaldados por una garantía de reembolso de 14 días.
Crea tu cuenta