1. 2026-05 May Financials
City Council · 2026-06-15 · agenda_item
Beaches Energy Services is planning to purchase a replacement power transformer for the Ft. Diego Substation. This transformer is needed because the current units, installed in 1982, are nearing the end of their expected 40-year service life. The estimated cost for this transformer is currently $2.4 million, with an anticipated delivery time of three years. This project is currently under review by the City Council. The work will involve the procurement and eventual installation of a large power transformer, which may include site preparation, foundation work, and electrical connections. Contractors specializing in heavy electrical equipment installation, site preparation, and related trades could find opportunities. Reaching out early is advised as plans and specific installation sites are still being determined.
- substation transformer voltage
- 138 kV
- substation transformer voltage
- 26.4 kV
- transformer cost
- 1.7 million
- transformer lead time
- 2 years
- current transformer cost
- 2.4 million
- estimated delivery timeline
- 3 years
- current transformers installation year
- 1982
- average operational lifespan
- 40 years
- fiscal year
- 2025
- federal grant reimbursement
- 75 %
- fiscal year
- 2026
Industries that could win this work
- General Contractor
- Electrical
- Utilities (Sub)
- Building & Industrial Supply
- Engineering & Architecture
Follow this across meetings
Board
City CouncilApplicants and firms
Mira los negocios reales detrás de estos números
Obtén los registros reales, con direcciones y directivos, respaldados por una garantía de reembolso de 14 días.
Crea tu cuenta