iv. The above insurance shall not include Primary and Non-Contributory Coverage and ITLLC shall not

City Council · 2026-06-02 · agenda_item

This notice concerns a proposed project involving the installation of CIPP (Cured-In-Place Pipe) lining for existing underground pipes. The work is planned for the area around 580 Goddard Avenue. The project scope includes pipe cleaning, television inspection, traffic control, and pipe setup. The total estimated cost for this phase of work is $149,947.00. This item is currently under review by the City Council of West Melbourne. The project will involve site preparation, underground utility work, and potentially specialized pipe repair trades. Local contractors, suppliers, and service providers are encouraged to reach out early to understand the project details before bids and permits are finalized, as this offers an advantage in securing potential work.

LF
1994 LF
Traffic Control
7 Day
Travel and Mobilization
1 EA
Total
149947.00

Industries that could win this work

  • General Contractor
  • Restoration & Waterproofing
  • Utilities (Sub)
  • Building & Industrial Supply

Follow this across meetings

Mira los negocios reales detrás de estos números

Obtén los registros reales, con direcciones y directivos, respaldados por una garantía de reembolso de 14 días.

Crea tu cuenta