Skip to main content

Sé el Primero, Construye Relaciones Duraderas

L. Utilities Services

Board of County Commissioners Meeting · 2026-04-21 · agenda_item

The Indian River County Board of County Commissioners is receiving an update on the Integrated Water Master Plan. This plan, developed by HDR Engineering, aims to address challenges like population growth and aging infrastructure over the next 20 years. It includes eight primary goals such as forecasting demand, planning infrastructure capacity, and developing a funding strategy. The project is currently about 75% complete and is being delivered in eight modules, with initial assessments finished. Future work includes continued public engagement, with a second round of outreach planned for late spring or early summer. This ongoing planning process could lead to future construction and utility projects, offering opportunities for contractors, suppliers, and service providers. Early engagement with the Department of Utility Services is advised as the plan progresses toward implementation phases.

IRCDUS Project ID
00.23.547
plan horizon
20 year
plan modules
8
progress percentage
75 %
approved contingency funding
742000 $
authorized contingency funding
272000 $
remaining contingency funding
470000 $

Industries that could win this work

  • Utilities (Sub)
  • Site Prep, Grading & Hardscape
  • General Contractor
  • Electrical
  • Plumbing
  • HVAC & Climate Control
  • Building & Industrial Supply
  • Engineering & Architecture
  • Landscaping & Lawn Service
  • Government Authority

Follow this across meetings

Applicants and firms

Mira los negocios reales detrás de estos números

Obtén los registros reales, con direcciones y directivos, respaldados por una garantía de reembolso de 14 días.

Crea tu cuenta