3. Oslo WTP Executed agreement
Board of County Commissioners Meeting · 2026-06-02 · agenda_item
Indian River County is planning a sand strainer replacement project at the South Oslo Road Water Treatment Plant (WTP). This project involves the delivery and installation of a new sand strainer system, including associated piping and electrical work. The total estimated cost for this project is $782,000. The project is currently under review, with an executed agreement noted. Work will likely involve site preparation, demolition of the existing strainer, installation of new components, electrical and instrumentation setup, and final testing. Contractors specializing in water treatment facility upgrades, heavy civil work, plumbing, electrical, and material supply could find opportunities. Early engagement is advised as plans and permits are being finalized.
- total estimated cost
- 782,000.00 $
- Mobilization, Demobilization and Planning
- 30,000.00 $
- General Conditions, Bonds and Insurance
- 25,000.00 $
- Sand Strainer Replacement
- 662,000.00 $
- Electrical and Instrumentation
- 65,000.00 $
- Allowances
- 125,000.00 $
- Change Orders
- (125,000.00) $
- Butterfly Valve
- 11,892.00 $
- SST Piping
- 27,350.00 $
- The Reserve West at Grand Harbor PD Phase 2, Plat 33
- 41 lots
- The Reserve West at Grand Harbor PD Phase 2, Plat 33
- 100 units
- The Reserve West at Grand Harbor PD Phase 2, Plat 33
- 30.89 acres
- The Reserve West at Grand Harbor PD Phase 2, Plat 33
- 75.5 acres
- The Reserve West at Grand Harbor PD Phase 2, Plat 33
- 1.30 units per acre
Industries that could win this work
- General Contractor
- Plumbing
- Electrical
- Site Prep, Grading & Hardscape
- Utilities (Sub)
- Building & Industrial Supply
Follow this across meetings
Applicants and firms
Mira los negocios reales detrás de estos números
Obtén los registros reales, con direcciones y directivos, respaldados por una garantía de reembolso de 14 días.
Crea tu cuenta