51. Award Contract to Reconstruct the Fort Myers Beach Fishing Pier
Lee Board of County Commissioners · 2026-05-19 · agenda_item
The Lee Board of County Commissioners has approved a contract for the reconstruction and enhancement of the Fort Myers Beach Fishing Pier. The project, proposed by RJ Gorman Contracting, LLC, will extend the pier to approximately 1,000 feet in length and 12 feet in width. It will include reinforced concrete piles, a concrete deck, aluminum railings, an entry gate, and three shade structures. Construction is expected to begin after receiving final approval from the U.S. Army Corps of Engineers, with an estimated 12-month construction period and one additional month for final completion. This project will involve site clearing and grading, concrete work, structural framing, installation of railings and shade structures, and final landscaping. Local contractors, trades, suppliers, and service providers are encouraged to reach out to RJ Gorman Contracting, LLC early, before final plans and permits are settled, to explore potential subcontracting or supply opportunities.
- contract amount
- 11,737,398.18 $
- pier length
- 1,000 feet
- pier width
- 12 feet
- construction duration
- 12 months
- final completion duration
- 1 month
- bid difference
- 4.2 million
- engineer's estimate of probable cost difference
- 1 %
- concrete pilings diameter
- 24 inch
- concrete pilings depth
- 100 feet
- liquidated damages per day
- 5200 $
- change order threshold
- 100,000 $
Industries that could win this work
- General Contractor
- Concrete & Masonry
- Site Prep, Grading & Hardscape
- Painting & Flooring
- Electrical
- Plumbing
- HVAC & Climate Control
- Building & Industrial Supply
- Real Estate Development
- Engineering & Architecture
- Landscaping & Lawn Service
Follow this across meetings
Applicants and firms
Locations
Mira los negocios reales detrás de estos números
Obtén los registros reales, con direcciones y directivos, respaldados por una garantía de reembolso de 14 días.
Crea tu cuenta