3. Resolution of the City Commission
City Commission Meeting · 2026-05-26 · agenda_item
The City of Leesburg is planning an engineering evaluation of wastewater treatment facilities formerly owned by Cutrale. This review will assess if these facilities can be repurposed for city use, estimate rehabilitation costs and capacity, and provide a fair market value. The evaluation is currently under review and is expected to take about 90 days. This project will involve engineering consulting services to gather data and provide cost estimates for adapting the existing facility versus building new capacity. The outcome could inform future decisions about significant wastewater infrastructure investments. Local contractors, suppliers, and service providers in engineering, construction, and related fields may find opportunities by engaging early to understand the project's scope and potential future needs before formal plans or bids are established.
- MGD water and wastewater capacity
- 9 MGD
- projected to meet demand until
- 2035–2040
- CUP comes under review by
- 2030
- engineering evaluation cost
- 70,000 $
- potential future expansion costs
- 100 million $
- evaluation duration
- 90 days
Industries that could win this work
- Engineering & Architecture
- Site Prep, Grading & Hardscape
- Utilities (Sub)
- Building & Industrial Supply
Follow this across meetings
Applicants and firms
Locations
Mira los negocios reales detrás de estos números
Obtén los registros reales, con direcciones y directivos, respaldados por una garantía de reembolso de 14 días.
Crea tu cuenta