Aviation and Seaport Committee: julio de 2026
Miami-Dade County
GENERAL ASPHALT CO. LLC FOR RIM HOT SPOT 3 AT OPF
Resolution approving a construction contract between Miami-Dade County and General Asphalt Co., LLC for the Runway Incursion Mitigation (RIM) Hot Spot 3 project at Miami-Opa Locka Executive Airport (OPF), Project No. AC042A, in an amount not to exceed $10,541,788.93. The project includes demolition of existing airfield pavements and taxiways, construction of new full-strength taxiway pavements, new shoulder pavements, installation of new taxiway lighting, signage, infield grading and drainage modifications, and removal and installation of pavement markings. The contract term is 480 consecutive calendar days. The Aviation and Seaport Committee forwarded the item to the Board of County Commissioners (BCC) with a favorable recommendation on 7/13/2026. The BCC agenda date is 9/1/2026. The project is located within District 1, represented by Commissioner Oliver G. Gilbert III, but the impact is countywide. Funding sources are Future Financing ($10,109,788.93, 96%) and Federal Aviation Administration ($432,000.00, 4%). The base bid is $9,559,545.62, which is 18.22 percent below the base estimate of $11,689,350.00. The contract includes a 10 percent contingency of $955,954.56 and an Inspector's General Fee of $26,288.75. Liquidated damages are specified for delays in opening various taxiways and Runway 12-30. The project is subject to Davis Bacon Wages and the Buy American Iron and Steel Procurement Program. The project manager is Sergio Mejia. The contract was advertised on February 24, 2026, and closed on April 22, 2026, with four bids received. General Asphalt's bid was deemed responsive by the County Attorney's Office on May 6, 2026. The Engineer of Record, AtkinsRéalis USA, Inc., confirmed the low bidder qualifies for award on May 11, 2026. General Asphalt has been in business for 60 years and is located at 4850 NW 72 Ave, Miami, FL 33166. The company principal is Jose A Bolanos. The project has a life expectancy of 20 years. The annualized cost of routine maintenance is $38,574.86. Operations costs are $116,893.50. The total engineer's estimate is $12,890,431.00. The project will enable MDAD to meet FAA standards in the 2024 Airport Design Advisory Circular, AC 150/5300-13B. Hot Spot 3 is bounded by Runways 12/30 and 09R/27L, and the convergence of Taxiways T, Y, D, and connectors T8 and Y7. The project will add no-taxi islands, decommission pavement, modify pavement geometry and fillets, and update runway and taxiway lighting and markings. The project is part of the $12 billion Modernization In Action (M.I.A.) Plan. The County Mayor is Daniella Levine Cava. The Deputy Mayor is Roy Coley. The contract manager is Sylvia Novela, Assistant Aviation Director. The project is subject to sea level rise projections pursuant to Miami-Dade County Resolution No. R-451-14. The project has no DBE measures assigned due to an Interim Final Rule released by the U.S. Department of Transportation on October 3, 2025. General Asphalt has 50 evaluations in the SBD's Capital Improvements Information System with an average rating of 3.5 out of 4.0. General Asphalt has been awarded four contracts in the last three years with a value of $45,745,258.00. The project is funded under Program No. #2000001049, General Aviation Airports Subprogram, FY2025-26 Adopted Budget and Multi-Year Capital Plan, Volume 3, Page 204.
- Board:
- Aviation and Seaport Committee
- Date:
- 2026-07-13
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation by the Aviation and Seaport Committee on 7/13/2026; pending BCC approval on 9/1/2026
- Address:
- Miami-Opa Locka Executive Airport (OPF)
- Applicant:
- Miami-Dade Aviation Department (MDAD)
GENERAL ASPHALT CO. LLC FOR RIM HOT SPOT 3 AT OPF
Miami-Dade County Board of County Commissioners (BCC) is set to approve a contract for the Runway Incursion Mitigation (RIM) Hot Spot 3 project at Miami-Opa Locka Executive Airport (OPF). The project aims to enhance safety by reconfiguring taxiways, improving airfield geometry, signage, and lighting to reduce the risk of runway incursions. The contract is awarded to General Asphalt Co., LLC for an amount not to exceed $10,541,788.93. The project involves demolition of existing pavements, construction of new taxiways and pavements, installation of lighting and signage, infield grading, drainage modifications, and new pavement markings. The contract term is 480 consecutive calendar days. The Aviation and Seaport Committee forwarded this item to the BCC with a favorable recommendation.
- Board:
- Aviation and Seaport Committee
- Date:
- 2026-07-13
- Type:
- Resolution
- Decision:
- Approved (Resolution)
- Address:
- Miami-Opa Locka Executive Airport (OPF)
- Applicant:
- General Asphalt Co., LLC
GENERAL ASPHALT CO. LLC FOR RIM HOT SPOT 3 AT OPF
Resolution approving a contract between Miami-Dade County and General Asphalt Co., LLC for the Miami-Opa Locka Executive Airport (OPF) Runway Incursion Mitigation (RIM) Hot Spot 3 Project No. AC042A, in an amount not to exceed $10,541,788.93. The project will reconfigure Hot Spot 3, an area bounded by Runways 12/30 and 09R/27L and the convergence of Taxiways T, Y, D, and connectors T8 and Y7, including demolition of existing airfield pavements and taxiways, construction of new full-strength taxiway pavements, new shoulder pavements, installation of new taxiway lighting, signage, infield grading and drainage modifications, and removal and installation of pavement markings. The contract was recommended for approval by the Aviation and Seaport Committee on 7/13/2026 and is scheduled for the Board of County Commissioners on 9/1/2026. The project is located at OPF, within District 1, represented by Commissioner Oliver G. Gilbert III. The total contract term is 480 consecutive calendar days. The base award amount is $9,559,545.62, with a 10 percent contingency of $955,954.56 and an Inspector's General Fee of $26,288.75. Funding sources are Future Financing ($10,109,788.93, 96%) and Federal Aviation Administration ($432,000.00, 4%). The project was advertised on February 24, 2026, and closed on April 22, 2026, with four bids received. The Engineer of Record, AtkinsRéalis USA, Inc., determined General Asphalt is fully qualified for the award. The County Attorney's Office deemed General Asphalt's bid responsive on May 6, 2026. The project manager is Sergio Mejia. The company principal is Jose A Bolanos, and the company location is 4850 NW 72 Ave, Miami, FL 33166. The document does not state a street address for the project site, parcel or folio number, acreage, or number of units or lots. The document does not state any public comment or stakeholder sentiment.
- Board:
- Aviation and Seaport Committee
- Date:
- 2026-07-13
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation by the Aviation and Seaport Committee on 7/13/2026; pending before the Board of County Commissioners as of 9/1/2026
- Applicant:
- General Asphalt Co., LLC
GENERAL ASPHALT CO. LLC FOR RIM HOT SPOT 3 AT OPF
Miami-Dade County Board of County Commissioners is approving a contract for the Runway Incursion Mitigation (RIM) Hot Spot 3 project at Miami-Opa Locka Executive Airport (OPF). The project aims to enhance safety by improving airfield geometry, signage, and lighting to reduce the risk of runway incursions. General Asphalt Co., LLC was awarded the contract for construction services. The project involves demolition, construction of new taxiway pavements and lighting, infield grading, drainage modifications, and new pavement markings. The contract duration is 480 consecutive calendar days. The Aviation and Seaport Committee forwarded the item to the Board with a favorable recommendation.
- Board:
- Aviation and Seaport Committee
- Date:
- 2026-07-13
- Type:
- Resolution
- Decision:
- Approved (Resolution)
- Address:
- Miami-Opa Locka Executive Airport (OPF)
- Applicant:
- General Asphalt Co., LLC
GENERAL ASPHALT CO. LLC FOR RIM HOT SPOT 3 AT OPF
Resolution approving a contract between Miami-Dade County and General Asphalt Co., LLC for the Runway Incursion Mitigation (RIM) Hot Spot 3 project at Miami-Opa Locka Executive Airport (OPF), Project No. AC042A, in an amount not to exceed $10,541,788.93. The project includes demolition of existing airfield pavements and taxiways, construction of new full-strength taxiway pavements, new shoulder pavements, installation of new taxiway lighting, signage, infield grading and drainage modifications, and removal and installation of pavement markings. The contract term is 480 consecutive calendar days. The resolution was adopted on 9/1/2026. The project was forwarded to the Board of County Commissioners with a favorable recommendation by the Aviation and Seaport Committee on 7/13/2026. The base bid was $9,559,545.62, which is 18.22 percent below the base estimate of $11,689,350.00. The total contract award amount includes a 10 percent contingency of $955,954.56 and an Inspector's General Fee of $26,288.75. Funding sources are Future Financing ($10,109,788.93, 96%) and Federal Aviation Administration ($432,000.00, 4%). The project is located at OPF, within District 1, represented by Commissioner Oliver G. Gilbert III. The project will reconfigure Hot Spot 3, an area bounded by Runways 12/30 and 09R/27L, and the convergence of Taxiways T, Y, D, and connectors T8 and Y7, by adding no-taxi islands, decommissioning pavement, modifying pavement geometry and fillets, and updating lighting and markings. Liquidated damages are specified for delays in various phases. The project is subject to Davis Bacon Wages and the Buy American Iron and Steel Procurement Program. The project manager is Sergio Mejia. The contract was advertised on February 24, 2026, and closed on April 22, 2026, with four bids received. General Asphalt's bid was deemed responsive by the County Attorney's Office on May 6, 2026. The Engineer of Record, AtkinsRéalis USA, Inc., confirmed on May 11, 2026, that General Asphalt qualifies for award. General Asphalt has been in business for 60 years and is located at 4850 NW 72 Ave, Miami, FL 33166. The company principal is Jose A Bolanos. No public comment or stakeholder sentiment is stated in the document.
- Board:
- Aviation and Seaport Committee
- Date:
- 2026-07-13
- Type:
- Resolution
- Decision:
- Adopted
- Address:
- Miami-Opa Locka Executive Airport (OPF)
- Applicant:
- Miami-Dade Aviation Department (MDAD)
GENERAL ASPHALT CO. LLC FOR RIM HOT SPOT 3 AT OPF
Resolution approving a contract between Miami-Dade County and General Asphalt Co., LLC for the Miami-Opa Locka Executive Airport (OPF) Runway Incursion Mitigation (RIM) Hot Spot 3 Project No. AC042A, in an amount not to exceed $10,541,788.93. The project includes demolition of existing airfield pavements and taxiways, construction of new full-strength taxiway pavements, new shoulder pavements, installation of new taxiway lighting, signage, infield grading and drainage modifications, and removal and installation of pavement markings. The project is located at OPF, bounded by Runways 12/30 and 09R/27L and the convergence of Taxiways T, Y, D, and connectors T8 and Y7. The total contract term is 480 consecutive calendar days. The Aviation and Seaport Committee forwarded the item to the Board of County Commissioners with a favorable recommendation on 7/13/2026. The agenda date is 9/1/2026. The resolution was introduced on 6/23/2026. The status is 'Before the Board'. The applicant is the Aviation Department. The contractor is General Asphalt Co., LLC. The project number is AC042A. The file number is 261144. The base bid is $9,559,545.62, which is 18.22 percent below the $11,689,350.00 base estimate. The total contract award amount is $10,541,788.93, including a 10 percent contingency of $955,954.56 and an Inspector's General Fee of $26,288.75. The funding sources are Future Financing ($10,109,788.93, 96%) and Federal Aviation Administration ($432,000.00, 4%). The project will enable MDAD to meet FAA standards in the 2024 Airport Design Advisory Circular, AC 150/5300-13B. The project is located within District 1, represented by Commissioner Oliver G. Gilbert III, but the impact is countywide. The project manager is Sergio Mejia. The contract manager is Sylvia Novela. The company principal is Jose A Bolanos. The company location is 4850 NW 72 Ave, Miami, FL 33166. The company has been in business for 60 years. The project was advertised on February 24, 2026, and closed on April 22, 2026, with four bids received. The County Attorney's Office deemed General Asphalt's bid responsive on May 6, 2026. The Engineer of Record, AtkinsRéalis USA, Inc., confirmed the low bidder qualifies for award on May 11, 2026. Liquidated damages are specified for delays in various phases. The project is subject to Davis-Bacon Wages and the Buy American Iron and Steel Procurement Program. The project has a life expectancy of 20 years. The annualized maintenance cost is $38,574.86. Operations costs are $116,893.50. The total engineer's estimate is $12,890,431.00. No public comment or stakeholder sentiment is stated in the document.
- Board:
- Aviation and Seaport Committee
- Date:
- 2026-07-13
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation
- Applicant:
- Aviation Department
GENERAL ASPHALT CO. LLC FOR RIM HOT SPOT 3 AT OPF
Miami-Dade County Board of County Commissioners (BCC) is set to approve a contract for the Runway Incursion Mitigation (RIM) Hot Spot 3 Project at Miami-Opa Locka Executive Airport (OPF). The project, identified as AC042A, aims to enhance safety by reconfiguring taxiways, improving signage, and updating pavement markings to reduce the risk of runway incursions. General Asphalt Co., LLC has been recommended for the contract, valued at $10,541,788.93, which includes a 10% contingency. The project duration is 480 consecutive calendar days. The Aviation and Seaport Committee forwarded this item to the BCC with a favorable recommendation. No public comment is stated in the document.
- Board:
- Aviation and Seaport Committee
- Date:
- 2026-07-13
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation by Aviation and Seaport Committee; pending BCC Assignment
- Address:
- Miami-Opa Locka Executive Airport (OPF)
- Applicant:
- General Asphalt Co., LLC
GENERAL ASPHALT CO. LLC FOR RIM HOT SPOT 3 AT OPF
Resolution approving a contract between Miami-Dade County and General Asphalt Co., LLC for the Miami-Opa Locka Executive Airport (OPF) Runway Incursion Mitigation (RIM) Hot Spot 3 Project No. AC042A, in an amount not to exceed $10,541,788.93. The project includes demolition of existing airfield pavements and taxiways, construction of new full-strength taxiway pavements, new shoulder pavements, installation of new taxiway lighting, signage, infield grading and drainage modifications, and removal and installation of pavement markings. The project is located at OPF, bounded by Runways 12/30 and 09R/27L and the convergence of Taxiways T, Y, D, and connectors T8 and Y7. The contract term is 480 consecutive calendar days. The item was forwarded to the Board of County Commissioners with a favorable recommendation by the Aviation and Seaport Committee on 7/13/2026, and is scheduled for the Board agenda on 9/1/2026. Public comment sentiment is not stated.
- Board:
- Aviation and Seaport Committee
- Date:
- 2026-07-13
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation
- Applicant:
- General Asphalt Co., LLC
GENERAL ASPHALT CO. LLC FOR RIM HOT SPOT 3 AT OPF
Miami-Dade County Board of County Commissioners is set to approve a contract for the Runway Incursion Mitigation (RIM) Hot Spot 3 project at Miami-Opa Locka Executive Airport (OPF). The project aims to enhance safety by improving airfield geometry, signage, and lighting to reduce the risk of runway incursions. General Asphalt Co., LLC has been recommended for the contract, which includes demolition, construction of new taxiway pavements and lighting, infield grading, drainage modifications, and new pavement markings. The contract duration is 480 consecutive calendar days. The Aviation and Seaport Committee forwarded this item to the Board with a favorable recommendation.
- Board:
- Aviation and Seaport Committee
- Date:
- 2026-07-13
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation by Aviation and Seaport Committee; pending Board of County Commissioners approval.
- Address:
- Miami-Opa Locka Executive Airport (OPF)
- Applicant:
- General Asphalt Co., LLC
GENERAL ASPHALT CO. LLC FOR RIM HOT SPOT 3 AT OPF
Resolution approving a contract between Miami-Dade County and General Asphalt Co., LLC for the Miami-Opa Locka Executive Airport (OPF) Runway Incursion Mitigation (RIM) Hot Spot 3 Project No. AC042A, in an amount not to exceed $10,541,788.93. The project will reconfigure Hot Spot 3, an area bounded by Runways 12/30 and 09R/27L and the convergence of Taxiways T, Y, D, and connectors T8 and Y7, including demolition of existing airfield pavements and taxiways, construction of new full-strength taxiway pavements, new shoulder pavements, installation of new taxiway lighting, signage, infield grading and drainage modifications, and new pavement markings. The contract was advertised on February 24, 2026, and closed on April 22, 2026, with four bids received. General Asphalt's base bid was $9,559,545.62, which is 18.22 percent below the $11,689,350.00 base estimate. The total contract term is 480 consecutive calendar days. The item was forwarded to the Board of County Commissioners with a favorable recommendation by the Aviation and Seaport Committee on July 13, 2026, and is scheduled for the Board agenda on September 1, 2026. The document does not state any public comment or stakeholder sentiment.
- Board:
- Aviation and Seaport Committee
- Date:
- 2026-07-13
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation
- Applicant:
- General Asphalt Co., LLC
GENERAL ASPHALT CO. LLC FOR RIM HOT SPOT 3 AT OPF
Miami-Dade County Board of County Commissioners (BCC) is set to approve a contract for the Runway Incursion Mitigation (RIM) Hot Spot 3 project at Miami-Opa Locka Executive Airport (OPF). The project aims to enhance safety by reconfiguring taxiway geometry, improving signage, and updating pavement markings to reduce the risk of runway incursions. The contract is awarded to General Asphalt Co., LLC for an amount not to exceed $10,541,788.93. The project involves demolition of existing airfield pavements, construction of new taxiway pavements and lighting, signage, infield grading, drainage modifications, and new pavement markings. The contract duration is 480 consecutive calendar days. The Aviation and Seaport Committee forwarded this item to the BCC with a favorable recommendation.
- Board:
- Aviation and Seaport Committee
- Date:
- 2026-07-13
- Type:
- Resolution
- Decision:
- Approved (Recommended by Aviation and Seaport Committee, pending BCC approval)
- Address:
- Miami-Opa Locka Executive Airport (OPF)
- Applicant:
- General Asphalt Co., LLC
GENERAL ASPHALT CO. LLC FOR RIM HOT SPOT 3 AT OPF
Miami-Dade County is approving a contract for the Runway Incursion Mitigation (RIM) Hot Spot 3 project at Miami-Opa Locka Executive Airport (OPF). The project aims to enhance safety by improving airfield geometry, signage, and lighting to reduce the risk of runway incursions. The contract is awarded to General Asphalt Co., LLC for an amount not to exceed $10,541,788.93. The project involves demolition of existing pavements, construction of new taxiways and pavements, installation of new lighting and signage, infield grading, drainage modifications, and new pavement markings. The contract term is 480 consecutive calendar days. The project is funded by Future Financing (96%) and the Federal Aviation Administration (4%). Public comment is not stated in the document.
- Board:
- Aviation and Seaport Committee
- Date:
- 2026-07-13
- Type:
- Resolution
- Decision:
- Approved (Resolution)
- Address:
- Miami-Opa Locka Executive Airport (OPF)
- Applicant:
- General Asphalt Co., LLC
GENERAL ASPHALT CO. LLC FOR RIM HOT SPOT 3 AT OPF
Resolution approving a construction contract between Miami-Dade County and General Asphalt Co., LLC for the Runway Incursion Mitigation (RIM) Hot Spot 3 project at Miami-Opa Locka Executive Airport (OPF), Project No. AC042A, in an amount not to exceed $10,541,788.93. The project includes demolition of existing airfield pavements and taxiways, construction of new full-strength taxiway pavements and shoulder pavements, installation of new taxiway lighting and signage, infield grading and drainage modifications, and removal and installation of pavement markings. The contract term is 480 consecutive calendar days. The Aviation and Seaport Committee forwarded the item to the Board of County Commissioners with a favorable recommendation on 7/13/2026. The Board agenda date is 9/1/2026. The project is located at OPF, within District 1, represented by Commissioner Oliver G. Gilbert III, but the impact is countywide. The project is funded by Future Financing ($10,109,788.93, 96%) and the Federal Aviation Administration ($432,000.00, 4%). The base award amount is $9,559,545.62, with a 10% contingency of $955,954.56 and an Inspector's General Fee of $26,288.75. The project was advertised on February 24, 2026, and closed on April 22, 2026, with four bids received. The Engineer of Record, AtkinsRéalis USA, Inc., determined General Asphalt is fully qualified for the award. The County Attorney's Office deemed General Asphalt's bid responsive on May 6, 2026. Liquidated damages are specified for delays in various phases. The project is subject to Davis Bacon Wages and the Buy American Iron and Steel Procurement Program. The project manager is Sergio Mejia. The contract manager is Sylvia Novela. The company principal is Jose A Bolanos, and the company location is 4850 NW 72 Ave, Miami, FL 33166. The company has been in business for 60 years. The project has a life expectancy of 20 years. The annualized maintenance cost is $38,574.86. The operations cost is $116,893.50. The total engineer's estimate is $12,890,431.00. The base engineer's estimate is $11,689,350.00. The project will enable MDAD to meet FAA standards in the 2024 Airport Design Advisory Circular, AC 150/5300-13B. Hot Spot 3 is bounded by Runways 12/30 and 09R/27L, and the convergence of Taxiways T, Y, D, and connectors T8 and Y7. The project will add no-taxi islands, decommission pavement, modify pavement geometry and fillets, and update lighting and markings. The project is part of the $12 billion Modernization In Action (M.I.A.) Plan. The project is in the FY2025-26 Adopted Budget and Multi-Year Capital Plan, Volume 3, Page 204, Program No. #2000001049. The project is subject to sea level rise considerations per Miami-Dade County Resolution No. R-451-14. The project has no DBE measures due to an Interim Final Rule from the U.S. Department of Transportation. General Asphalt has 50 evaluations in the CIIS database with an average rating of 3.5 out of 4.0. General Asphalt has been awarded four contracts in the last three years with a value of $45,745,258.00, and nine contracts as a Prime Contractor from March 2012 to October 2022 with a value of $117,019,789.00, for a total value of $162,765,047.00. The project is a critical safety enhancement to reduce the risk of runway incursions. The project will be monitored by MDAD Project Manager Sergio Mejia. The resolution authorizes the County Mayor or designee to execute the contract and exercise its termination provisions. The item was introduced on 6/23/2026. The requester is the Aviation Department. The staff recommendation is to approve the resolution. The legislative history shows the item was assigned to the County Attorney on 9/1/2026. The report notes 'MDAD - No sponsor - pending July cmte - County attorney David Murray - attachments A-H - PGS 71'. The resolution was forwarded to the BCC with a favorable recommendation by the Aviation and Seaport Committee on 7/13/2026. The status is 'Before the Board'. The final action is not stated. The effective date and expiration date are not stated. The sunset provision is 'No'. The registered lobbyist is 'None Listed'. The sponsors are 'NONE'. The indexes are 'NONE'. The cost is not stated. The agenda item number is 8A2. The control is 'Pending BCC Assignment'. The version is 0. The reference is not stated. The printable PDF format is available. The file type is Resolution. The file name is 'GENERAL ASPHALT CO. LLC FOR RIM HOT SPOT 3 AT OPF'. The project location is stated as 'OPF'. The project description is to meet FAA standards. The approval path is the Board of County Commissioners, Section 2-8.1 of the Miami-Dade County Code. The delegation of authority is pursuant to Sections 2-285 and 285.2 of the Miami-Dade County Code. The due diligence was conducted pursuant to Resolution No. R-187-12. The SBD history of violations is 'Yes, all identified underpayment amounts have been recovered.' The procurement history includes the advertisement and closing dates, the four bidders, the compliance review, the responsive irregularities, and the CAO determination. The contract summary, bid bond, and required affidavits are enclosed as Attachment H. The project has a 10 percent contingency allowance. The IG fee is 0.25%. The project is not PTP, GOB, or ARRA funded. Art in Public Places is 'No'. The Sustainable Buildings Ordinance is 'Not applicable'. The project is subject to the Buy American Iron and Steel Procurement Program. One bid package was issued and four were received. The project manager's phone is (305) 876-7922 and email is [email protected]. The contract manager's phone is (305) 876-7048, cell (786) 769-1580, and email is [email protected]. The deputy mayor is Roy Coley. The document does not state any public comment or stakeholder sentiment.
- Board:
- Aviation and Seaport Committee
- Date:
- 2026-07-13
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation by the Aviation and Seaport Committee on 7/13/2026; pending final action by the Board of County Commissioners on 9/1/2026
- Address:
- Miami-Opa Locka Executive Airport (OPF), not stated
- Applicant:
- General Asphalt Co., LLC
GENERAL ASPHALT CO. LLC FOR RIM HOT SPOT 3 AT OPF
Miami-Dade County Board of County Commissioners (BCC) is set to approve a contract for the Runway Incursion Mitigation (RIM) Hot Spot 3 project at Miami-Opa Locka Executive Airport (OPF). The project, identified as AC042A, aims to enhance safety by reconfiguring taxiways, improving pavement markings, and upgrading signage and lighting to reduce the risk of runway incursions. General Asphalt Co., LLC has been recommended for the contract, with a total compensation amount not to exceed $10,541,788.93. The project involves demolition, construction of new taxiway pavements, lighting, signage, grading, drainage, and pavement markings. The contract duration is 480 consecutive calendar days. The Aviation and Seaport Committee forwarded this item to the BCC with a favorable recommendation.
- Board:
- Aviation and Seaport Committee
- Date:
- 2026-07-13
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation by Aviation and Seaport Committee; pending BCC approval
- Address:
- Miami-Opa Locka Executive Airport (OPF)
- Applicant:
- General Asphalt Co., LLC
GENERAL ASPHALT CO. LLC FOR RIM HOT SPOT 3 AT OPF
Miami-Dade County is approving a contract for the Runway Incursion Mitigation (RIM) Hot Spot 3 Project at Miami-Opa Locka Executive Airport (OPF). The project aims to enhance safety by reconfiguring taxiway geometry, updating pavement markings, and improving airfield signage and lighting to reduce the risk of runway incursions. The contract is awarded to General Asphalt Co., LLC for an amount not to exceed $10,541,788.93, with a contract term of 480 consecutive calendar days. The project is in committee and has not yet received final action.
- Board:
- Aviation and Seaport Committee
- Date:
- 2026-07-13
- Type:
- Resolution
- Decision:
- In Committee
- Address:
- Miami-Opa Locka Executive Airport (OPF)
- Applicant:
- General Asphalt Co., LLC
GENERAL ASPHALT CO. LLC FOR RIM HOT SPOT 3 AT OPF
Resolution approving a contract between Miami-Dade County and General Asphalt Co., LLC for the Miami-Opa Locka Executive Airport (OPF) Runway Incursion Mitigation (RIM) Hot Spot 3 Project No. AC042A, in an amount not to exceed $10,541,788.93. The project includes demolition of existing airfield pavements and taxiways, construction of new full-strength taxiway pavements, new shoulder pavements, installation of new taxiway lighting, signage, infield grading and drainage modifications, and removal and installation of pavement markings. The project is located at OPF, bounded by Runways 12/30 and 09R/27L and the convergence of Taxiways T, Y, D, and connectors T8 and Y7. The contract was recommended for approval by the Aviation and Seaport Committee on 7/13/2026 and is scheduled for the Board of County Commissioners on 9/1/2026. The total contract term is 480 consecutive calendar days. The funding sources are Future Financing ($10,109,788.93, 96%) and Federal Aviation Administration ($432,000.00, 4%). The base award amount is $9,559,545.62, with a 10% contingency of $955,954.56 and an Inspector's General Fee of $26,288.75. The project is subject to Davis Bacon Wages and the Buy American Iron and Steel Procurement Program. The applicant is the Miami-Dade Aviation Department. The case/file number is 261144. The decision is pending before the Board. Key dates include: Introduced 6/23/2026, Aviation and Seaport Committee 7/13/2026, Agenda Date 9/1/2026. The document does not state a street address for the project site, only 'OPF'. The document does not state the project acreage or number of units. The document does not state a zoning change. The document does not state any public comment or stakeholder sentiment.
- Board:
- Aviation and Seaport Committee
- Date:
- 2026-07-13
- Type:
- Resolution
- Decision:
- Pending before the Board; forwarded to BCC with a favorable recommendation from the Aviation and Seaport Committee
- Applicant:
- Miami-Dade Aviation Department
GENERAL ASPHALT CO. LLC FOR RIM HOT SPOT 3 AT OPF
Resolution approving a construction contract between Miami-Dade County and General Asphalt Co., LLC for the Runway Incursion Mitigation (RIM) Hot Spot 3 project at Miami-Opa Locka Executive Airport (OPF), Contract No. AC042A, in an amount not to exceed $10,541,788.93. The project includes demolition of existing airfield pavements and taxiways, construction of new full-strength taxiway pavements, new shoulder pavements, new taxiway lighting, signage, infield grading and drainage modifications, and new pavement markings. The contract was advertised on February 24, 2026, and closed on April 22, 2026, with four bids received. General Asphalt's base bid was $9,559,545.62, which is 18.22 percent below the base estimate of $11,689,350.00. The total contract amount includes a 10 percent contingency of $955,954.56 and an Inspector's General Fee of $26,288.75. The contract term is 480 consecutive calendar days. The Aviation and Seaport Committee forwarded the item to the Board of County Commissioners with a favorable recommendation on July 13, 2026. The Board adopted the resolution on September 1, 2026. The project is located at OPF, within District 1, represented by Commissioner Oliver G. Gilbert III, but the impact is countywide. Funding sources are Future Financing at $10,109,788.93 (96%) and Federal Aviation Administration at $432,000.00 (4%). The project is subject to Davis Bacon Wages and the Buy American Iron and Steel Procurement Program. The project manager is Sergio Mejia. The company principal is Jose A Bolanos, and the company location is 4850 NW 72 Ave, Miami, FL 33166. The project will enable MDAD to meet FAA standards in the 2024 Airport Design Advisory Circular, AC 150/5300-13B. Hot Spot 3 is bounded by Runways 12/30 and 09R/27L, and the convergence of Taxiways T, Y, D, and connectors T8 and Y7. The project will reconfigure this intersection by adding no-taxi islands, decommissioning pavement, modifying pavement geometry and fillets, and updating lighting and markings. Liquidated damages are specified for delays in various phases. The Engineer of Record is AtkinsRéalis USA, Inc. The cost consultant is RIB US Cost, Inc. The County Attorney's Office deemed General Asphalt's bid responsive on May 6, 2026. The Engineer of Record confirmed the low bidder qualifies for award on May 11, 2026. The project has a life expectancy of 20 years. The annualized maintenance cost is $38,574.86. Operations costs are $116,893.50. The total Engineer's Estimate is $12,890,431.00. The project is subject to sea level rise considerations. The project is a DBE project, but no measures are assigned due to the Interim Final Rule released by the U.S. Department of Transportation on October 3, 2025, which temporarily suspended DBE program requirements. General Asphalt has been in business for 60 years. The SBD's CIIS database has 50 evaluations for General Asphalt with an average rating of 3.5 out of 4.0. General Asphalt has been awarded four contracts in the last three years with a value of $45,745,258.00, and nine contracts as a Prime Contractor from March 2012 to October 2022 with a value of $117,019,789.00, for a total value of $162,765,047.00. The contract manager is Sylvia Novela, Assistant Aviation Director. The project manager is Sergio Mejia, Senior Section Chief, Civil Environmental Engineering. The resolution authorizes the County Mayor or designee to execute the contract and exercise termination provisions. The item was introduced on June 23, 2026. The final action was on September 1, 2026. The agenda date was September 1, 2026, and the agenda item number was 8A2. The file number is 261144. The reference is R-730-26. The requester is the Aviation Department. The status is Adopted. The file type is Resolution. The legislative history includes the Aviation and Seaport Committee on July 13, 2026, agenda item 3B, forwarded to BCC with a favorable recommendation. The report notes MDAD - No sponsor - pending July cmte - County attorney David Murray - attachments A-H - PGS 71. The County Attorney assigned to David M. Murray on June 25, 2026. The project is part of the $12 billion Modernization In Action (M.I.A.) Plan. The project will reduce the risk of runway incursions by improving airfield geometry and signage and enhancing situational awareness. The work includes modifications to taxiway geometry, updated pavement markings, enhanced airfield signage and lighting, and other FAA-recommended safety improvements. The project will implement specific airfield improvements to comply with regulatory standards and reduce the risk of collision and/or runway incursion. The project will enable MDAD to meet the most recent standards and recommendations published by the FAA in the 2024 Airport Design Advisory Circular, AC 150/5300-13B. The project is located at OPF. The project name is OPF RIM Hot Spot 3. The project number is AC042A. The contract number is AC042A. The project description is to enable MDAD to meet the most recent standards and recommendations published by the FAA in the 2024 Airport Design Advisory Circular, AC 150/5300-13B. The project will implement specific airfield improvements to comply with regulatory standards and reduce the risk of collision and/or runway incursion. The approval path is Board of County Commissioners, Section 2-8.1 of the Miami-Dade County Code. The background states that Hot Spot 3 at OPF has been identified as an area with elevated potential for runway incursions due to complex taxiway configurations and operational challenges. The proposed project will reconfigure this complex intersection by adding no-taxi islands, decommissioning pavement, modifying pavement geometry and fillets, and updating associated runway and taxiway lighting and markings. The liquidated damages are as follows: Phase 1 - Taxiway T - 180 Days - 2 sub-phases - $5,500 per day of delay in opening Taxiway T. Phase 2 - Runway 12-30 Connectors and Taxiway T8, Y7, and D - 60 Days - $5,500 per day of delay in opening Taxiway D, Taxiway T8, and/or Taxiway Y7. $1,300 per hour of delay in opening Runway 12-30. Phase 3 - Taxiway Y and Taxiway D - 60 Days - $5,500 per day of delay in opening Taxiway Y and/or Taxiway D. Closeout - Taxiway Electrical, Final Markins and all Punch List Items - 60 Days - $5,500 per day of delay in completing all Taxiway Electrical, Final Markins and all Punch List items. The fiscal impact and funding sources are Future Financing - $10,109,788.93 - 96% and Federal Aviation Administration - $432,000.00 - 4%. The capital program budget is Program No. #2000001049, General Aviation Airports Subprogram, FY2025-26 Adopted Budget and Multi-Year Capital Plan, Volume 3, Page 204. The base engineer's estimate is $11,689,350.00. The base award amount is $9,559,545.62. The contingency type is Allowance (Section 2-8.1 Construction Miami-Dade County Code) at 10% for $955,954.56. The IG Fee (Ordinance No. 97-215) is 0.25% for $26,288.75. The total contract award amount is $10,541,788.93. The total engineer's estimate is $12,890,431.00. The operations costs are $116,893.50. The maintenance costs are $38,574.86 annually. The total contract period is 480 consecutive calendar days. The life expectancy of the asset is 20 years. The applicable wages are Davis Bacon Wages. The project is subject to sea level rise considerations. The Buy American Iron and Steel Procurement Program is applicable. One bid package was issued and four were received. The delegation of authority is pursuant to Sections 2-285 and 285.2 of the Miami-Dade County Code. The track record and monitor: MDAD Project Manager Sergio Mejia will monitor the implementation. Due diligence was conducted pursuant to Resolution No. R-187-12. The Florida Department of State Division of Corporations records show the company's status as active. The SBD history of violations: Yes, all identified underpayment amounts have been recovered. The procurement history: advertised on February 24, 2026, closed on April 22, 2026, four bids received from Ranger Construction Industries, Inc., Quality Construction Performance, Inc., OHLA USA, Inc., and General Asphalt Co, LLC. On April 27, 2026, the County's Strategic Procurement Department issued its Compliance Review, concluding that a compliance review for AC042A cannot be conducted due to the Interim Final Rule released by the U.S. Department of Transportation on October 3, 2025. The project remains subject to all other applicable federal requirements, including Davis-Bacon Wage Rates. MDAD staff identified possible responsive irregularities where General Asphalt failed to acknowledge Addendum No. 5 and submitted their bid bond using the original form, which had been replaced via Addendum No. 1. The bid was referred to the County Attorney's Office, which on May 6, 2026, deemed General Asphalt's bid responsive. The SPD Project Worksheet shows this project is a DBE and no measures are assigned due to the Interim Final Rule. In a letter dated May 11, 2026, the Engineer of Record confirmed the recommended low bidder qualifies for award. The SBD's CIIS database has 50 evaluations for General Asphalt with an average rating of 3.5 out of 4.0. According to SPD's Firm History Report, General Asphalt has been awarded four contracts in the last three years with a value of $45,745,258.00, and nine contracts as a Prime Contractor from March 2012 to October 2022 with a value of $117,019,789.00, for a total value of $162,765,047.00. The contract summary, bid bond, and required affidavits executed by General Asphalt are enclosed as Attachment H. Company principals: Jose A Bolanos. Company location: 4850 NW 72 Ave, Miami, FL 33166. How long in business: 60 years. Responsible wages: Davis Bacon Wages. Contract manager name: Sylvia Novela, Assistant Aviation Director. Project manager name: Sergio Mejia, Senior Section Chief, Civil Environmental Engineering. The resolution was signed by Roy Coley, Deputy Mayor.
- Board:
- Aviation and Seaport Committee
- Date:
- 2026-07-13
- Type:
- Resolution
- Decision:
- Adopted (Resolution approved by Board of County Commissioners on September 1, 2026; forwarded to BCC with favorable recommendation by Aviation and Seaport Committee on July 13, 2026)
- Address:
- Miami-Opa Locka Executive Airport (OPF)
- Applicant:
- Miami-Dade Aviation Department (MDAD); Contractor: General Asphalt Co., LLC
GENERAL ASPHALT CO. LLC FOR RIM HOT SPOT 3 AT OPF
Resolution approving a construction contract between Miami-Dade County and General Asphalt Co., LLC for the Runway Incursion Mitigation (RIM) Hot Spot 3 project at Miami-Opa Locka Executive Airport (OPF), Contract No. AC042A, in an amount not to exceed $10,541,788.93. The project includes demolition of existing airfield pavements and taxiways, construction of new full-strength taxiway pavements, new shoulder pavements, installation of new taxiway lighting, signage, infield grading and drainage modifications, and removal and installation of pavement markings. The project was forwarded to the Board of County Commissioners with a favorable recommendation by the Aviation and Seaport Committee on 7/13/2026. The agenda date is 9/1/2026. The contract term is 480 consecutive calendar days. Funding sources are Future Financing ($10,109,788.93, 96%) and Federal Aviation Administration ($432,000.00, 4%). The project is subject to Davis Bacon Wages and the Buy American Iron and Steel Procurement Program. Liquidated damages are specified for delays in opening various taxiways and runway. The project manager is Sergio Mejia. The contract manager is Sylvia Novela. The company principal is Jose A Bolanos. The company location is 4850 NW 72 Ave, Miami, FL 33166. The company has been in business for 60 years. The project is located within District 1, represented by Commissioner Oliver G. Gilbert III, but the impact is countywide. The project will enable MDAD to meet FAA standards in the 2024 Airport Design Advisory Circular, AC 150/5300-13B. Hot Spot 3 is an area bounded by Runways 12/30 and 09R/27L, and the convergence of Taxiways T, Y, D, and connectors T8 and Y7. The project will reconfigure this intersection by adding no-taxi islands, decommissioning pavement, modifying pavement geometry and fillets, and updating lighting and markings. The base bid was $9,559,545.62, which is 18.22 percent below the base estimate of $11,689,350.00. The total contract award amount includes a 10 percent contingency of $955,954.56 and an Inspector's General Fee of $26,288.75. The total Engineer's Estimate is $12,890,431.00. The project was advertised on February 24, 2026, and closed on April 22, 2026, with four bids received. The County Attorney's Office deemed General Asphalt's bid responsive on May 6, 2026. The Engineer of Record, AtkinsRéalis USA, Inc., confirmed the low bidder qualifies for award on May 11, 2026. The project has a life expectancy of 20 years. The annualized cost of routine maintenance is $38,574.86. Operations costs are $116,893.50. The project is subject to sea level rise considerations. The project has no DBE measures due to an Interim Final Rule. The project has a Small Business Development history of violations, but all identified underpayment amounts have been recovered. General Asphalt has 50 evaluations with an average rating of 3.5 out of 4.0. General Asphalt has been awarded four contracts in the last three years with a value of $45,745,258.00, and nine contracts as a Prime Contractor from March 2012 to October 2022 with a value of $117,019,789.00, for a total value of $162,765,047.00.
- Board:
- Aviation and Seaport Committee
- Date:
- 2026-07-13
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation
- Address:
- Miami-Opa Locka Executive Airport (OPF)
- Applicant:
- Miami-Dade Aviation Department (MDAD)
GENERAL ASPHALT CO. LLC FOR RIM HOT SPOT 3 AT OPF
Miami-Dade County Board of County Commissioners is approving a contract for the Runway Incursion Mitigation (RIM) Hot Spot 3 project at Miami-Opa Locka Executive Airport (OPF). The project aims to enhance safety by improving airfield geometry, signage, and lighting to reduce the risk of runway incursions. The contract is awarded to General Asphalt Co., LLC for an amount not to exceed $10,541,788.93. The project involves demolition of existing pavements, construction of new taxiway pavements and lighting, signage, infield grading, drainage modifications, and new pavement markings. The contract duration is 480 consecutive calendar days. The Aviation and Seaport Committee forwarded this item to the Board with a favorable recommendation. No public comment is stated in the document.
- Board:
- Aviation and Seaport Committee
- Date:
- 2026-07-13
- Type:
- Resolution
- Decision:
- Approved (Resolution)
- Address:
- Miami-Opa Locka Executive Airport (OPF)
- Applicant:
- General Asphalt Co., LLC
GENERAL ASPHALT CO. LLC FOR RIM HOT SPOT 3 AT OPF
Miami-Dade County Board of County Commissioners (BCC) is set to approve a contract for the Runway Incursion Mitigation (RIM) Hot Spot 3 Project at Miami-Opa Locka Executive Airport (OPF). The project, identified as AC042A, aims to enhance safety by reconfiguring taxiway geometry, updating pavement markings, and improving airfield signage and lighting to reduce the risk of runway incursions. The contract is awarded to General Asphalt Co., LLC for an amount not to exceed $10,541,788.93, with a completion timeframe of 480 consecutive calendar days. The Aviation and Seaport Committee forwarded this item to the BCC with a favorable recommendation. No public comment is stated in the document.
- Board:
- Aviation and Seaport Committee
- Date:
- 2026-07-13
- Type:
- Resolution
- Decision:
- Approved (Recommended by Aviation and Seaport Committee, pending BCC approval)
- Address:
- Miami-Opa Locka Executive Airport (OPF)
- Applicant:
- General Asphalt Co., LLC
GENERAL ASPHALT CO. LLC FOR RIM HOT SPOT 3 AT OPF
The document is a legislative item for a resolution approving a construction contract between Miami-Dade County and General Asphalt Co., LLC for the Runway Incursion Mitigation (RIM) Hot Spot 3 project at Miami-Opa Locka Executive Airport (OPF). The contract amount is not to exceed $10,541,788.93. The project involves reconfiguring Hot Spot 3, an area bounded by Runways 12/30 and 09R/27L and the convergence of Taxiways T, Y, D, and connectors T8 and Y7, to reduce runway incursion risk. The work includes demolition of existing pavements and taxiways, construction of new taxiway pavements, lighting and signage, and grading and drainage modifications. The resolution was adopted on 9/1/2026. The project was introduced on 6/23/2026 and forwarded to the Board of County Commissioners with a favorable recommendation from the Aviation and Seaport Committee on 7/13/2026. The base bid was $9,559,545.62, with a 10% contingency of $955,954.56 and an Inspector's General Fee of $26,288.75. The total contract term is 480 consecutive calendar days. The funding sources are Future Financing ($10,109,788.93) and Federal Aviation Administration ($432,000.00). The project is subject to Davis Bacon Wages and the Buy American Iron and Steel Procurement Program. The document does not state a specific street address for the project, only that it is at OPF. The applicant/developer is the Miami-Dade Aviation Department, and the contractor is General Asphalt Co., LLC. The case/file number is 261144, with reference R-730-26. The document does not state any public comment or stakeholder sentiment.
- Board:
- Aviation and Seaport Committee
- Date:
- 2026-07-13
- Type:
- Resolution
- Decision:
- Adopted
- Applicant:
- Miami-Dade Aviation Department
GENERAL ASPHALT CO. LLC FOR RIM HOT SPOT 3 AT OPF
Resolution approving a construction contract between Miami-Dade County and General Asphalt Co., LLC for the Runway Incursion Mitigation (RIM) Hot Spot 3 project at Miami-Opa Locka Executive Airport (OPF), Project No. AC042A, in an amount not to exceed $10,541,788.93. The project includes demolition of existing airfield pavements and taxiways, construction of new full-strength taxiway pavements, new shoulder pavements, installation of new taxiway lighting, signage, infield grading and drainage modifications, and removal and installation of pavement markings. The contract term is 480 consecutive calendar days. The item was forwarded to the Board of County Commissioners with a favorable recommendation by the Aviation and Seaport Committee on 7/13/2026 and is scheduled for the Board agenda on 9/1/2026. The project is located at OPF, within District 1, represented by Commissioner Oliver G. Gilbert III, but the impact is countywide. The base bid was $9,559,545.62, which is 18.22 percent below the base estimate of $11,689,350.00. The total contract award amount includes a 10 percent contingency of $955,954.56 and an Inspector's General Fee of $26,288.75. Funding sources are Future Financing at $10,109,788.93 (96%) and Federal Aviation Administration at $432,000.00 (4%). The project will implement airfield improvements to comply with FAA Advisory Circular 150/5300-13B. Hot Spot 3 is bounded by Runways 12/30 and 09R/27L, and the convergence of Taxiways T, Y, D, and connectors T8 and Y7. The project will reconfigure this intersection by adding no-taxi islands, decommissioning pavement, modifying pavement geometry and fillets, and updating lighting and markings. Liquidated damages are specified for delays in various phases. The project is subject to Davis Bacon Wages and the Buy American Iron and Steel Procurement Program. The project manager is Sergio Mejia. The contract was advertised on February 24, 2026, and closed on April 22, 2026, with four bids received. General Asphalt's bid was deemed responsive by the County Attorney's Office on May 6, 2026. The Engineer of Record, AtkinsRéalis USA, Inc., confirmed the low bidder qualifies for award on May 11, 2026. General Asphalt Co., LLC is located at 4850 NW 72 Ave, Miami, FL 33166, and has been in business for 60 years. Company principal is Jose A Bolanos. The document does not state any public comment or stakeholder sentiment.
- Board:
- Aviation and Seaport Committee
- Date:
- 2026-07-13
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation by the Aviation and Seaport Committee on 7/13/2026; pending before the Board of County Commissioners as of the document date
- Address:
- Miami-Opa Locka Executive Airport (OPF), not stated
- Applicant:
- Miami-Dade Aviation Department (MDAD), contractor General Asphalt Co., LLC
GENERAL ASPHALT CO. LLC FOR RIM HOT SPOT 3 AT OPF
Miami-Dade County Board of County Commissioners (BCC) is set to approve a contract for the Runway Incursion Mitigation (RIM) Hot Spot 3 project at Miami-Opa Locka Executive Airport (OPF). The project, identified as AC042A, aims to enhance safety by reconfiguring taxiway geometry, updating pavement markings, and improving airfield signage and lighting to reduce the risk of runway incursions. The contract is awarded to General Asphalt Co., LLC for an amount not to exceed $10,541,788.93, with a completion timeline of 480 consecutive calendar days. The Aviation and Seaport Committee forwarded this item to the BCC with a favorable recommendation. No public comment is stated in the document.
- Board:
- Aviation and Seaport Committee
- Date:
- 2026-07-13
- Type:
- Resolution
- Decision:
- Approved (Resolution approving contract, pending BCC assignment)
- Address:
- Miami-Opa Locka Executive Airport (OPF)
- Applicant:
- General Asphalt Co., LLC
GENERAL ASPHALT CO. LLC FOR RIM HOT SPOT 3 AT OPF
Miami-Dade County Board of County Commissioners is approving a contract for the Runway Incursion Mitigation (RIM) Hot Spot 3 project at Miami-Opa Locka Executive Airport (OPF). The project aims to enhance safety by improving airfield geometry, signage, and lighting to reduce the risk of runway incursions. General Asphalt Co., LLC was awarded the contract for construction services. The project includes demolition of existing pavements, construction of new taxiway pavements and lighting, infield grading, drainage modifications, and new pavement markings. The contract duration is 480 consecutive calendar days. The Aviation Department is procuring this project to meet FAA standards. The project was advertised on February 24, 2026, and closed on April 22, 2026, with four bids received. General Asphalt's bid was deemed responsive after a review by the County Attorney's Office. Public comment is not stated in this document.
- Board:
- Aviation and Seaport Committee
- Date:
- 2026-07-13
- Type:
- Resolution
- Decision:
- Approved
- Address:
- Miami-Opa Locka Executive Airport (OPF)
- Applicant:
- General Asphalt Co., LLC
GENERAL ASPHALT CO. LLC FOR RIM HOT SPOT 3 AT OPF
Resolution approving a construction contract between Miami-Dade County and General Asphalt Co., LLC for the Runway Incursion Mitigation (RIM) Hot Spot 3 project at Miami-Opa Locka Executive Airport (OPF), Contract No. AC042A, in an amount not to exceed $10,541,788.93. The project includes demolition of existing airfield pavements and taxiways, construction of new full-strength taxiway pavements, new shoulder pavements, new taxiway lighting, signage, infield grading and drainage modifications, and new pavement markings. The contract was advertised on February 24, 2026, and closed on April 22, 2026, with four bids received. General Asphalt's base bid was $9,559,545.62, which is 18.22 percent below the $11,689,350.00 base estimate. The total contract term is 480 consecutive calendar days. The resolution was introduced on June 23, 2026, forwarded to the Board of County Commissioners with a favorable recommendation by the Aviation and Seaport Committee on July 13, 2026, and adopted on September 1, 2026. The project is located within District 1, represented by Commissioner Oliver G. Gilbert III, but the impact is countywide as OPF is a regional asset. Funding sources are Future Financing ($10,109,788.93, 96%) and Federal Aviation Administration ($432,000.00, 4%). The project is subject to Davis Bacon Wages and the Buy American Iron and Steel Procurement Program. Liquidated damages are specified for delays in various phases. The project manager is Sergio Mejia. The contract manager is Sylvia Novela. The company principal is Jose A Bolanos. The company location is 4850 NW 72 Ave, Miami, FL 33166. The company has been in business for 60 years. The project will enable MDAD to meet FAA standards in the 2024 Airport Design Advisory Circular, AC 150/5300-13B. Hot Spot 3 is an area bounded by Runways 12/30 and 09R/27L, and the convergence of Taxiways T, Y, D, and connectors T8 and Y7. The project will reconfigure this complex intersection by adding no-taxi islands, decommissioning pavement, modifying pavement geometry and fillets, and updating associated runway and taxiway lighting and markings. The Engineer of Record is AtkinsRéalis USA, Inc. The cost consultant is RIB US Cost, Inc. The project number is AC042A. The contract number is AC042A. The capital program budget is Program No. #2000001049, General Aviation Airports Subprogram, FY2025-26 Adopted Budget and Multi-Year Capital Plan, Volume 3, Page 204. The total Engineer's Estimate is $12,890,431.00. Operations costs are $116,893.50. Annualized maintenance costs are $38,574.86. Life expectancy of asset is 20 years. The project is subject to sea level rise considerations per Miami-Dade County Resolution No. R-451-14. The project is a DBE project with no measures assigned due to the Interim Final Rule released by the U.S. Department of Transportation on October 3, 2025. The County Attorney's Office deemed General Asphalt's bid responsive on May 6, 2026. The Engineer of Record confirmed the recommended low bidder qualifies for award in a letter dated May 11, 2026. General Asphalt has 50 evaluations in SBD's CIIS database with an average rating of 3.5 out of 4.0. General Asphalt has been awarded four contracts in the last three years with a value of $45,745,258.00. For the period March 2012 to October 2022, General Asphalt received nine contracts as a Prime Contractor with a value of $117,019,789.00 for a total value of $162,765,047.00. The resolution authorizes the County Mayor or designee to execute the contract and exercise its termination provisions. The resolution was adopted on September 1, 2026. The agenda date was September 1, 2026. The agenda item number was 8A2. The file number is 261144. The reference is R-730-26. The requester is the Aviation Department. The final action date is September 1, 2026. The Aviation and Seaport Committee forwarded the item to the BCC with a favorable recommendation on July 13, 2026. The item was assigned to Roy Coley on June 23, 2026. The item was assigned to the County Attorney on June 23, 2026. The County Attorney assigned to David M. Murray on June 25, 2026. The report notes MDAD - No sponsor - pending July cmte - County attorney David Murray - attachments A-H - PGS 71. The resolution was introduced on June 23, 2026. The status is Adopted. The file type is Resolution. The version is 0. The control is Pending BCC Assignment. The sunset provision is No. The registered lobbyist is None Listed. The sponsors are NONE. The indexes are NONE. The effective date is not stated. The expiration date is not stated. The project location is OPF. The project name is OPF RIM Hot Spot 3. The project description is to enable MDAD to meet the most recent standards and recommendations published by the FAA in the 2024 Airport Design Advisory Circular, AC 150/5300-13B. The approval path is Board of County Commissioners, Section 2-8.1 of the Miami-Dade County Code. The delegation of authority is pursuant to Sections 2-285 and 285.2 of the Miami-Dade County Code. The due diligence was conducted pursuant to Resolution No. R-187-12. The SBD history of violations is yes, all identified underpayment amounts have been recovered. The procurement history includes four bids from Ranger Construction Industries, Inc., Quality Construction Performance, Inc., OHLA USA, Inc., and General Asphalt Co, LLC. The compliance review was issued on April 27, 2026, concluding that a compliance review cannot be conducted due to the Interim Final Rule. The project remains subject to all other applicable federal requirements, including Davis-Bacon Wage Rates. The liquidated damages are $5,500 per day of delay in opening Taxiway T for Phase 1, $5,500 per day of delay in opening Taxiway D, Taxiway T8, and/or Taxiway Y7 and $1,300 per hour of delay in opening Runway 12-30 for Phase 2, $5,500 per day of delay in opening Taxiway Y and/or Taxiway D for Phase 3, and $5,500 per day of delay in completing all Taxiway Electrical, Final Markins and all Punch List items for Closeout. The total contract award amount includes a 10 percent contingency of $955,954.56 and an Inspector's General Fee of $26,288.75. The base award amount is $9,559,545.62. The base engineer's estimate is $11,689,350.00. The contingency type is Allowance per Section 2-8.1 Construction 10%. The IG fee is per Ordinance No. 97-215 at 0.25%. The IG fee is included in the contract. PTP funding is no. GOB funding is no. ARRA funding is no. Art in Public Places is no. Applicable wages resolution is Davis Bacon Wages. Sustainable Buildings Ordinance is not applicable. Sea level rise is yes. Buy American Iron and Steel Procurement Program is yes. Bid packages issued is 1. Bid packages received is 4. The track record monitor is MDAD Project Manager Sergio Mejia. The contract manager name is Sylvia Novela, Assistant Aviation Director. The project manager name is Sergio Mejia, Senior Section Chief, Civil Environmental Engineering. The deputy mayor is Roy Coley. The document does not state a specific street address for the project site. The document does not state a parcel or folio number. The document does not state the project size in acreage, number of units, or square footage. The document does not state a zoning or use change. The document does not state any public comment or stakeholder sentiment.
- Board:
- Aviation and Seaport Committee
- Date:
- 2026-07-13
- Type:
- Resolution
- Decision:
- Adopted. Final Action: 9/1/2026. Agenda Date: 9/1/2026. Agenda Item Number: 8A2. Aviation and Seaport Committee forwarded to BCC with a favorable recommendation on 7/13/2026. Introduced: 6/23/2026.
- Address:
- Not stated. Project location is Miami-Opa Locka Executive Airport (OPF).
- Applicant:
- General Asphalt Co., LLC. Company location: 4850 NW 72 Ave, Miami, FL 33166. Company principal: Jose A Bolanos. Requester: Aviation Department.
GENERAL ASPHALT CO. LLC FOR RIM HOT SPOT 3 AT OPF
Miami-Dade County Board of County Commissioners is approving a contract for the Runway Incursion Mitigation (RIM) Hot Spot 3 project at Miami-Opa Locka Executive Airport (OPF). The project aims to enhance safety by improving airfield geometry, signage, and lighting to reduce the risk of runway incursions. General Asphalt Co., LLC was awarded the contract for construction services. The project involves demolition, construction of new taxiway pavements and lighting, infield grading, drainage modifications, and new pavement markings. The contract duration is 480 consecutive calendar days. The Aviation and Seaport Committee forwarded the item to the Board with a favorable recommendation.
- Board:
- Aviation and Seaport Committee
- Date:
- 2026-07-13
- Type:
- Resolution
- Decision:
- Approved
- Address:
- Miami-Opa Locka Executive Airport (OPF)
- Applicant:
- General Asphalt Co., LLC
GENERAL ASPHALT CO. LLC FOR RIM HOT SPOT 3 AT OPF
Resolution approving a contract between Miami-Dade County and General Asphalt Co., LLC for the Miami-Opa Locka Executive Airport (OPF) Runway Incursion Mitigation (RIM) Hot Spot 3 Project No. AC042A in an amount not to exceed $10,541,788.93. The project is located at OPF, within District 1, represented by Commissioner Oliver G. Gilbert III. The work includes demolition of existing airfield pavements and taxiways, construction of new full-strength taxiway pavements, new shoulder pavements, installation of new taxiway lighting, signage, infield grading and drainage modifications, and removal and installation of pavement markings. The project was forwarded to the Board of County Commissioners with a favorable recommendation by the Aviation and Seaport Committee on 7/13/2026. The agenda date is 9/1/2026. The contract term is 480 consecutive calendar days. The funding sources are Future Financing ($10,109,788.93, 96%) and Federal Aviation Administration ($432,000.00, 4%). The base award amount is $9,559,545.62, with a 10% contingency of $955,954.56 and an Inspector's General Fee of $26,288.75. The project was advertised on February 24, 2026, and closed on April 22, 2026, with four bids received. General Asphalt's bid was deemed responsive by the County Attorney's Office on May 6, 2026. The Engineer of Record, AtkinsRéalis USA, Inc., confirmed on May 11, 2026, that General Asphalt qualifies for award. The project is subject to Davis Bacon Wages and the Buy American Iron and Steel Procurement Program. Liquidated damages are specified for delays in various phases. The project manager is Sergio Mejia. The contract manager is Sylvia Novela. The company principal is Jose A Bolanos. The company location is 4850 NW 72 Ave, Miami, FL 33166. The company has been in business for 60 years. The project has a life expectancy of 20 years. The annualized maintenance cost is $38,574.86. The operations cost is $116,893.50. The total engineer's estimate is $12,890,431.00. The base engineer's estimate is $11,689,350.00. The project will enable MDAD to meet FAA standards in the 2024 Airport Design Advisory Circular, AC 150/5300-13B. Hot Spot 3 is bounded by Runways 12/30 and 09R/27L, and the convergence of Taxiways T, Y, D, and connectors T8 and Y7. The project will reconfigure this intersection by adding no-taxi islands, decommissioning pavement, modifying pavement geometry and fillets, and updating lighting and markings. The document does not state any public comment or stakeholder sentiment.
- Board:
- Aviation and Seaport Committee
- Date:
- 2026-07-13
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation
- Address:
- Miami-Opa Locka Executive Airport (OPF)
- Applicant:
- Miami-Dade Aviation Department (MDAD)
GENERAL ASPHALT CO. LLC FOR RIM HOT SPOT 3 AT OPF
Resolution approving a contract between Miami-Dade County and General Asphalt Co., LLC for the Miami-Opa Locka Executive Airport (OPF) Runway Incursion Mitigation (RIM) Hot Spot 3 Project No. AC042A, in an amount not to exceed $10,541,788.93. The project is located at OPF, within District 1, represented by Commissioner Oliver G. Gilbert III, with countywide impact. The work includes demolition of existing airfield pavements and taxiways, construction of new full-strength taxiway pavements, new shoulder pavements, installation of new taxiway lighting, signage, connections to the existing airfield lighting system, infield grading and drainage modifications, and removal and installation of pavement markings. The project was forwarded to the Board of County Commissioners (BCC) with a favorable recommendation by the Aviation and Seaport Committee on 7/13/2026. The agenda date is 9/1/2026. The total contract term is 480 consecutive calendar days. The funding sources are Future Financing ($10,109,788.93, 96%) and Federal Aviation Administration ($432,000.00, 4%). The base award amount is $9,559,545.62, with a 10% contingency of $955,954.56 and an Inspector's General Fee of $26,288.75. The project was advertised on February 24, 2026, and closed on April 22, 2026, with four bids received. General Asphalt's bid was deemed responsive by the County Attorney's Office on May 6, 2026. The Engineer of Record, AtkinsRéalis USA, Inc., confirmed on May 11, 2026, that General Asphalt qualifies for award. The project manager is Sergio Mejia. The contract manager is Sylvia Novela. The company principal is Jose A Bolanos. The company location is 4850 NW 72 Ave, Miami, FL 33166. The company has been in business for 60 years. Liquidated damages are specified for delays in various phases. The project is subject to Davis Bacon Wages and the Buy American Iron and Steel Procurement Program. The project considers sea level rise projections. The project has a life expectancy of 20 years. The annualized cost of routine maintenance is $38,574.86. The operations cost is $116,893.50. The total engineer's estimate is $12,890,431.00. The base engineer's estimate is $11,689,350.00. The project is funded under Program No. #2000001049, General Aviation Airports Subprogram, FY2025-26 Adopted Budget and Multi-Year Capital Plan, Volume 3, Page 204. The resolution authorizes the County Mayor or designee to execute the contract and exercise its termination provisions. The project will enable MDAD to meet FAA standards in the 2024 Airport Design Advisory Circular, AC 150/5300-13B. Hot Spot 3 is bounded by Runways 12/30 and 09R/27L, and the convergence of Taxiways T, Y, D, and connectors T8 and Y7. The project will reconfigure this intersection by adding no-taxi islands, decommissioning pavement, modifying pavement geometry and fillets, and updating lighting and markings. The document does not state any public comment or stakeholder sentiment.
- Board:
- Aviation and Seaport Committee
- Date:
- 2026-07-13
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation by the Aviation and Seaport Committee on 7/13/2026; pending BCC assignment; agenda date 9/1/2026
- Address:
- Miami-Opa Locka Executive Airport (OPF); not stated
- Applicant:
- Miami-Dade Aviation Department (MDAD); General Asphalt Co., LLC
GENERAL ASPHALT CO. LLC FOR RIM HOT SPOT 3 AT OPF
Miami-Dade County Board of County Commissioners (BCC) is approving a contract for the Runway Incursion Mitigation (RIM) Hot Spot 3 project at Miami-Opa Locka Executive Airport (OPF). The project aims to enhance safety by improving airfield geometry, signage, and lighting to reduce the risk of runway incursions. The contract is awarded to General Asphalt Co., LLC for an amount not to exceed $10,541,788.93. The project involves demolition of existing pavements, construction of new taxiway pavements and lighting, signage, infield grading, drainage modifications, and new pavement markings. The contract duration is 480 consecutive calendar days. The Aviation and Seaport Committee forwarded this item to the BCC with a favorable recommendation.
- Board:
- Aviation and Seaport Committee
- Date:
- 2026-07-13
- Type:
- Resolution
- Decision:
- Approved (Resolution)
- Address:
- Miami-Opa Locka Executive Airport (OPF)
- Applicant:
- General Asphalt Co., LLC
GENERAL ASPHALT CO. LLC FOR RIM HOT SPOT 3 AT OPF
Miami-Dade County is approving a contract for the Runway Incursion Mitigation (RIM) Hot Spot 3 project at Miami-Opa Locka Executive Airport (OPF). The project aims to enhance safety by improving airfield geometry, signage, and lighting to reduce the risk of runway incursions. General Asphalt Co., LLC was awarded the contract for construction services. The project involves demolition of existing pavements, construction of new taxiways and pavements, installation of lighting and signage, infield grading, drainage modifications, and new pavement markings. The contract duration is 480 consecutive calendar days. The project is funded by Future Financing (96%) and the Federal Aviation Administration (4%). Davis Bacon Wages are applicable. The project is subject to sea level rise considerations and the Buy American Iron and Steel Procurement Program.
- Board:
- Aviation and Seaport Committee
- Date:
- 2026-07-13
- Type:
- Resolution
- Decision:
- Approved (Resolution)
- Address:
- Miami-Opa Locka Executive Airport (OPF)
- Applicant:
- General Asphalt Co., LLC
GENERAL ASPHALT CO. LLC FOR RIM HOT SPOT 3 AT OPF
Miami-Dade County Board of County Commissioners (BCC) is set to approve a contract for the Runway Incursion Mitigation (RIM) Hot Spot 3 project at Miami-Opa Locka Executive Airport (OPF). The project aims to enhance safety by reconfiguring taxiways, improving signage, and updating pavement markings to reduce the risk of runway incursions. The contract is awarded to General Asphalt Co., LLC for an amount not to exceed $10,541,788.93, with a contract period of 480 consecutive calendar days. The Aviation and Seaport Committee forwarded this item to the BCC with a favorable recommendation. No public comment is stated in the document.
- Board:
- Aviation and Seaport Committee
- Date:
- 2026-07-13
- Type:
- Resolution
- Decision:
- Approved (Recommended by Aviation and Seaport Committee, pending BCC approval)
- Address:
- Miami-Opa Locka Executive Airport (OPF)
- Applicant:
- General Asphalt Co., LLC
GENERAL ASPHALT CO. LLC FOR RIM HOT SPOT 3 AT OPF
Resolution approving a contract between Miami-Dade County and General Asphalt Co., LLC for the Miami-Opa Locka Executive Airport (OPF) Runway Incursion Mitigation (RIM) Hot Spot 3 Project No. AC042A, in an amount not to exceed $10,541,788.93. The project includes demolition of existing airfield pavements and taxiways, construction of new full-strength taxiway pavements, new shoulder pavements, installation of new taxiway lighting, signage, infield grading and drainage modifications, and removal and installation of pavement markings. The project is located at OPF, bounded by Runways 12/30 and 09R/27L and the convergence of Taxiways T, Y, D, and connectors T8 and Y7. The total contract term is 480 consecutive calendar days. The Aviation and Seaport Committee forwarded the item to the Board of County Commissioners with a favorable recommendation on 7/13/2026. The agenda date is 9/1/2026. The resolution authorizes the County Mayor or designee to execute the contract and exercise termination provisions. The contract was advertised on February 24, 2026, and closed on April 22, 2026, with four bids received. General Asphalt's base bid was $9,559,545.62, which is 18.22 percent below the $11,689,350.00 base estimate. The total contract award amount includes a 10 percent contingency of $955,954.56 and an Inspector's General Fee of $26,288.75. Funding sources are Future Financing at $10,109,788.93 (96%) and Federal Aviation Administration at $432,000.00 (4%). The project is subject to Davis Bacon Wages and the Buy American Iron and Steel Procurement Program. The project manager is Sergio Mejia. The company principal is Jose A Bolanos, and the company location is 4850 NW 72 Ave, Miami, FL 33166. The document does not state a street address for the project site, only 'OPF' and the description of Hot Spot 3. The document does not state any public comment or stakeholder sentiment.
- Board:
- Aviation and Seaport Committee
- Date:
- 2026-07-13
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation
- Applicant:
- General Asphalt Co., LLC
GENERAL ASPHALT CO. LLC FOR RIM HOT SPOT 3 AT OPF
Resolution approving a contract between Miami-Dade County and General Asphalt Co., LLC for the Miami-Opa Locka Executive Airport (OPF) Runway Incursion Mitigation (RIM) Hot Spot 3 Project No. AC042A, in an amount not to exceed $10,541,788.93. The project will reduce the risk of runway incursions by improving airfield geometry and signage, including modifications to taxiway geometry, updated pavement markings, enhanced airfield signage and lighting, and other FAA-recommended safety improvements. The project is located at OPF, within District 1, represented by Commissioner Oliver G. Gilbert III. The total contract term is 480 consecutive calendar days. The Aviation and Seaport Committee forwarded the item to the Board of County Commissioners with a favorable recommendation on 7/13/2026. The agenda date is 9/1/2026. The project is funded by Future Financing ($10,109,788.93, 96%) and the Federal Aviation Administration ($432,000.00, 4%). The base award amount is $9,559,545.62, with a 10% contingency of $955,954.56 and an Inspector's General Fee of $26,288.75. The base engineer's estimate was $11,689,350.00. The project was advertised on February 24, 2026, and closed on April 22, 2026, with four bids received. The County Attorney deemed General Asphalt's bid responsive on May 6, 2026. The Engineer of Record, AtkinsRéalis USA, Inc., confirmed the low bidder qualifies for award on May 11, 2026. The project includes demolition of existing airfield pavements and taxiways, construction of new full-strength taxiway pavements, new shoulder pavements, installation of new taxiway lighting, signage, infield grading and drainage modifications, and removal and installation of pavement markings. Liquidated damages are specified for delays in various phases. The project is subject to Davis Bacon Wages and the Buy American Iron and Steel Procurement Program. The contract manager is Sylvia Novela, and the project manager is Sergio Mejia. The company principal is Jose A Bolanos, and the company location is 4850 NW 72 Ave, Miami, FL 33166. The company has been in business for 60 years. The project has a life expectancy of 20 years. The document does not state a specific street address for the project site, only 'OPF'. The document does not state a parcel or folio number. The document does not state the project size in acreage, number of units, or square footage. The document does not state a zoning or use change. The document does not state any public comment or stakeholder sentiment.
- Board:
- Aviation and Seaport Committee
- Date:
- 2026-07-13
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation by the Aviation and Seaport Committee on 7/13/2026; pending before the Board of County Commissioners (agenda date 9/1/2026)
- Address:
- not stated (project location is stated as OPF, Miami-Opa Locka Executive Airport)
- Applicant:
- Miami-Dade Aviation Department (MDAD); Contractor: General Asphalt Co., LLC
GENERAL ASPHALT CO. LLC FOR RIM HOT SPOT 3 AT OPF
Miami-Dade County is approving a contract for the Runway Incursion Mitigation (RIM) Hot Spot 3 Project at Miami-Opa Locka Executive Airport (OPF). The project aims to enhance safety by improving airfield geometry, signage, and lighting to reduce the risk of runway incursions. The contract is awarded to General Asphalt Co., LLC for an amount not to exceed $10,541,788.93. The project involves demolition of existing pavements, construction of new taxiway pavements and lighting, signage, infield grading, drainage modifications, and new pavement markings. The contract duration is 480 consecutive calendar days. The project is funded by Future Financing (96%) and the Federal Aviation Administration (4%). The Aviation and Seaport Committee is reviewing the matter, with an agenda date of September 1, 2026. No public comment is stated in the document.
- Board:
- Aviation and Seaport Committee
- Date:
- 2026-07-13
- Type:
- Resolution
- Decision:
- In Committee
- Address:
- Miami-Opa Locka Executive Airport (OPF)
- Applicant:
- General Asphalt Co., LLC
GENERAL ASPHALT CO. LLC FOR RIM HOT SPOT 3 AT OPF
Miami-Dade County Board of County Commissioners (BCC) is set to approve a contract for the Runway Incursion Mitigation (RIM) Hot Spot 3 project at Miami-Opa Locka Executive Airport (OPF). The project, identified as AC042A, aims to enhance airfield safety by reconfiguring taxiways, improving signage, and updating pavement markings to reduce the risk of runway incursions. The contract is awarded to General Asphalt Co., LLC for an amount not to exceed $10,541,788.93. The project involves demolition of existing pavements, construction of new taxiways and shoulders, installation of new lighting and signage, infield grading, drainage modifications, and new pavement markings. The contract duration is 480 consecutive calendar days. The Aviation and Seaport Committee forwarded this item to the BCC with a favorable recommendation. Public comment is not stated in this document.
- Board:
- Aviation and Seaport Committee
- Date:
- 2026-07-13
- Type:
- Resolution
- Decision:
- Approved (Resolution approving contract, pending BCC assignment)
- Address:
- Miami-Opa Locka Executive Airport (OPF)
- Applicant:
- General Asphalt Co., LLC
GENERAL ASPHALT CO. LLC FOR RIM HOT SPOT 3 AT OPF
Miami-Dade County is approving a contract for the Runway Incursion Mitigation (RIM) Hot Spot 3 Project at Miami-Opa Locka Executive Airport (OPF). The project aims to enhance safety by modifying taxiway geometry, updating pavement markings, and improving airfield signage and lighting. General Asphalt Co., LLC was awarded the contract for $10,541,788.93. The project involves demolition of existing airfield pavements, construction of new taxiway and shoulder pavements, installation of new lighting and signage, infield grading, drainage modifications, and new pavement markings. The contract duration is 480 calendar days. The Aviation and Seaport Committee forwarded the item to the Board of County Commissioners (BCC) with a favorable recommendation. No public comment is stated in the document.
- Board:
- Aviation and Seaport Committee
- Date:
- 2026-07-13
- Type:
- Resolution
- Decision:
- Approved (Resolution)
- Address:
- Miami-Opa Locka Executive Airport (OPF)
- Applicant:
- General Asphalt Co., LLC
GENERAL ASPHALT CO. LLC FOR RIM HOT SPOT 3 AT OPF
Resolution approving a construction contract between Miami-Dade County and General Asphalt Co., LLC for the Runway Incursion Mitigation (RIM) Hot Spot 3 project at Miami-Opa Locka Executive Airport (OPF), Project No. AC042A, in an amount not to exceed $10,541,788.93. The project will reconfigure the intersection bounded by Runways 12/30 and 09R/27L and Taxiways T, Y, D, and connectors T8 and Y7, including demolition of existing pavements, construction of new taxiway pavements, new lighting and signage, and drainage modifications. The contract was forwarded to the Board of County Commissioners with a favorable recommendation from the Aviation and Seaport Committee on 7/13/2026. The agenda date is 9/1/2026. The base bid was $9,559,545.62, which is 18.22 percent below the $11,689,350.00 base estimate. The total contract term is 480 consecutive calendar days. Funding sources are Future Financing at $10,109,788.93 (96%) and Federal Aviation Administration at $432,000.00 (4%). The project is located at OPF, within District 1, represented by Commissioner Oliver G. Gilbert III. The project manager is Sergio Mejia. The contract manager is Sylvia Novela. The company principal is Jose A Bolanos. The company location is 4850 NW 72 Ave, Miami, FL 33166. The project was advertised on February 24, 2026, and closed on April 22, 2026, with four bids received. The County Attorney deemed General Asphalt's bid responsive on May 6, 2026. The Engineer of Record confirmed the low bidder qualifies for award on May 11, 2026. Liquidated damages are specified for delays in opening various taxiways and Runway 12-30. The project is subject to Davis Bacon Wages and the Buy American Iron and Steel Procurement Program. The project has a life expectancy of 20 years. The annualized maintenance cost is $38,574.86. The operations cost is $116,893.50. The total engineer's estimate is $12,890,431.00. The project considers sea level rise projections. The document does not state any public comment or stakeholder sentiment.
- Board:
- Aviation and Seaport Committee
- Date:
- 2026-07-13
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation from the Aviation and Seaport Committee on 7/13/2026; pending before the Board of County Commissioners with an agenda date of 9/1/2026
- Address:
- Miami-Opa Locka Executive Airport (OPF)
- Applicant:
- Miami-Dade Aviation Department (MDAD); Contractor: General Asphalt Co., LLC
GENERAL ASPHALT CO. LLC FOR RIM HOT SPOT 3 AT OPF
Resolution approving a construction contract between Miami-Dade County and General Asphalt Co., LLC for the Runway Incursion Mitigation (RIM) Hot Spot 3 project at Miami-Opa Locka Executive Airport (OPF), Contract No. AC042A, in an amount not to exceed $10,541,788.93. The project will reconfigure Hot Spot 3, an area bounded by Runways 12/30 and 09R/27L and the convergence of Taxiways T, Y, D, and connectors T8 and Y7, including demolition of existing pavements and taxiways, construction of new full-strength taxiway pavements, new shoulder pavements, new taxiway lighting, signage, infield grading and drainage modifications, and new pavement markings. The contract was awarded to General Asphalt Co., LLC, whose base bid of $9,559,545.62 was 18.22 percent below the base estimate. The total contract term is 480 consecutive calendar days. The resolution was adopted on September 1, 2026. The project is funded by Future Financing ($10,109,788.93, 96%) and the Federal Aviation Administration ($432,000.00, 4%). The project is located at OPF, within District 1, represented by Commissioner Oliver G. Gilbert III, but the impact is countywide. The project manager is Sergio Mejia. The contract manager is Sylvia Novela. The company principal is Jose A Bolanos, located at 4850 NW 72 Ave, Miami, FL 33166. The project was advertised on February 24, 2026, and closed on April 22, 2026, with four bids received. The County Attorney deemed General Asphalt's bid responsive on May 6, 2026. The Engineer of Record confirmed the low bidder qualifies for award on May 11, 2026. The Aviation and Seaport Committee forwarded the item to the BCC with a favorable recommendation on July 13, 2026. The resolution was introduced on June 23, 2026. Liquidated damages are specified for delays in various phases. The project is subject to Davis-Bacon Wages and the Buy American Iron and Steel Procurement Program. The project has a life expectancy of 20 years. The annualized cost of routine maintenance is $38,574.86. Operations costs are $116,893.50. The total Engineer's Estimate is $12,890,431.00. The base Engineer's Estimate is $11,689,350.00. The contingency is 10% ($955,954.56) and the IG Fee is 0.25% ($26,288.75). The project will enable MDAD to meet FAA standards in the 2024 Airport Design Advisory Circular, AC 150/5300-13B. The project includes three phases and a closeout period with specific liquidated damages. The project is a DBE project, but DBE requirements are temporarily suspended due to an Interim Final Rule. General Asphalt has been in business for 60 years. The project is part of the FY2025-26 Adopted Budget and Multi-Year Capital Plan, Volume 3, Page 204, Program No. #2000001049. The project considers sea level rise projections. The document does not state any public comment or stakeholder sentiment.
- Board:
- Aviation and Seaport Committee
- Date:
- 2026-07-13
- Type:
- Resolution
- Decision:
- Adopted
- Address:
- Miami-Opa Locka Executive Airport (OPF)
- Applicant:
- Miami-Dade Aviation Department (MDAD); Contractor: General Asphalt Co., LLC
GENERAL ASPHALT CO. LLC FOR RIM HOT SPOT 3 AT OPF
Miami-Dade County Board of County Commissioners (BCC) is set to approve a contract for the Runway Incursion Mitigation (RIM) Hot Spot 3 project at Miami-Opa Locka Executive Airport (OPF). The project aims to enhance safety by reconfiguring taxiway geometry, improving signage and lighting, and updating pavement markings to reduce the risk of runway incursions. The contract is awarded to General Asphalt Co., LLC for an amount not to exceed $10,541,788.93. The project involves demolition of existing airfield pavements, construction of new taxiway pavements and lighting, signage, infield grading, drainage modifications, and new pavement markings. The contract duration is 480 consecutive calendar days. The Aviation and Seaport Committee forwarded this item to the BCC with a favorable recommendation.
- Board:
- Aviation and Seaport Committee
- Date:
- 2026-07-13
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation by Aviation and Seaport Committee; pending BCC approval
- Address:
- Miami-Opa Locka Executive Airport (OPF)
- Applicant:
- General Asphalt Co., LLC
GENERAL ASPHALT CO. LLC FOR RIM HOT SPOT 3 AT OPF
Miami-Dade County Board of County Commissioners adopted Resolution R-730-26 (File Number 261144) approving a construction contract with General Asphalt Co., LLC for the Runway Incursion Mitigation (RIM) Hot Spot 3 project at Miami-Opa Locka Executive Airport (OPF), Contract No. AC042A, in an amount not to exceed $10,541,788.93. The project will reconfigure Hot Spot 3, an area bounded by Runways 12/30 and 09R/27L and the convergence of Taxiways T, Y, D, and connectors T8 and Y7, including demolition of existing pavements and taxiways, construction of new full-strength taxiway pavements and shoulder pavements, new taxiway lighting and signage, infield grading and drainage modifications, and new pavement markings. The contract term is 480 consecutive calendar days. The project was introduced on 6/23/2026, forwarded with favorable recommendation by the Aviation and Seaport Committee on 7/13/2026, and adopted on 9/1/2026. The base bid was $9,559,545.62, which is 18.22 percent below the $11,689,350.00 base estimate. The total contract award includes a 10 percent contingency of $955,954.56 and an Inspector's General Fee of $26,288.75. Funding sources are Future Financing at $10,109,788.93 (96%) and Federal Aviation Administration at $432,000.00 (4%). The project is located at OPF, which is in District 1, represented by Commissioner Oliver G. Gilbert III. The applicant is the Miami-Dade Aviation Department. The contractor is General Asphalt Co., LLC, located at 4850 NW 72 Ave, Miami, FL 33166. The project manager is Sergio Mejia. The contract manager is Sylvia Novela. Liquidated damages are specified for delays in various phases. The project is subject to Davis Bacon Wages and the Buy American Iron and Steel Procurement Program. The document does not state any public comment or stakeholder sentiment.
- Board:
- Aviation and Seaport Committee
- Date:
- 2026-07-13
- Type:
- Resolution
- Decision:
- Adopted
- Address:
- Miami-Opa Locka Executive Airport (OPF); not stated
- Applicant:
- Miami-Dade Aviation Department
GENERAL ASPHALT CO. LLC FOR RIM HOT SPOT 3 AT OPF
Miami-Dade County Board of County Commissioners (BCC) is set to approve a contract for the Runway Incursion Mitigation (RIM) Hot Spot 3 Project at Miami-Opa Locka Executive Airport (OPF). The project, identified as AC042A, aims to enhance safety by reconfiguring taxiways, improving signage, and updating pavement markings to reduce the risk of runway incursions. The contract is awarded to General Asphalt Co., LLC for an amount not to exceed $10,541,788.93. The project involves demolition of existing airfield pavements, construction of new taxiways and shoulders, installation of new lighting and signage, infield grading, drainage modifications, and new pavement markings. The contract duration is 480 consecutive calendar days. The Aviation and Seaport Committee forwarded this item to the BCC with a favorable recommendation.
- Board:
- Aviation and Seaport Committee
- Date:
- 2026-07-13
- Type:
- Resolution
- Decision:
- Approved (Resolution)
- Address:
- Miami-Opa Locka Executive Airport (OPF)
- Applicant:
- General Asphalt Co., LLC
GENERAL ASPHALT CO. LLC FOR RIM HOT SPOT 3 AT OPF
Miami-Dade County Board of County Commissioners (BCC) is set to approve a contract for the Runway Incursion Mitigation (RIM) Hot Spot 3 Project at Miami-Opa Locka Executive Airport (OPF). The project, identified as AC042A, aims to enhance airfield safety by reconfiguring taxiways, improving signage, and updating pavement markings to reduce the risk of runway incursions. The contract is awarded to General Asphalt Co., LLC for an amount not to exceed $10,541,788.93, with a completion timeframe of 480 consecutive calendar days. The Aviation and Seaport Committee forwarded this item to the BCC with a favorable recommendation.
- Board:
- Aviation and Seaport Committee
- Date:
- 2026-07-13
- Type:
- Resolution
- Decision:
- Approved (Recommended by Aviation and Seaport Committee, pending BCC approval)
- Address:
- Miami-Opa Locka Executive Airport (OPF)
- Applicant:
- General Asphalt Co., LLC
GENERAL ASPHALT CO. LLC FOR RIM HOT SPOT 3 AT OPF
Miami-Dade County Board of County Commissioners (BCC) is set to approve a contract for the Runway Incursion Mitigation (RIM) Hot Spot 3 Project at Miami-Opa Locka Executive Airport (OPF). The project, identified as AC042A, aims to enhance safety by reconfiguring taxiway geometry, updating pavement markings, and improving airfield signage and lighting to reduce the risk of runway incursions. The contract is awarded to General Asphalt Co., LLC for an amount not to exceed $10,541,788.93. The project involves demolition of existing airfield pavements, construction of new taxiway and shoulder pavements, installation of new lighting and signage, infield grading, drainage modifications, and new pavement markings. The Aviation and Seaport Committee forwarded this item to the BCC with a favorable recommendation. No public comment is stated in the document.
- Board:
- Aviation and Seaport Committee
- Date:
- 2026-07-13
- Type:
- Resolution
- Decision:
- Approved (Resolution)
- Address:
- Miami-Opa Locka Executive Airport (OPF)
- Applicant:
- General Asphalt Co., LLC
GENERAL ASPHALT CO. LLC FOR RIM HOT SPOT 3 AT OPF
Miami-Dade County is approving a contract for the Runway Incursion Mitigation (RIM) Hot Spot 3 project at Miami-Opa Locka Executive Airport (OPF). The project aims to enhance safety by improving airfield geometry, signage, and lighting to reduce the risk of runway incursions. The contract is awarded to General Asphalt Co., LLC for an amount not to exceed $10,541,788.93. The project involves demolition of existing pavements, construction of new taxiways and pavements, installation of lighting and signage, infield grading, drainage modifications, and new pavement markings. The contract duration is 480 consecutive calendar days. The project is funded by Future Financing (96%) and the Federal Aviation Administration (4%). Public comment is not stated in the document.
- Board:
- Aviation and Seaport Committee
- Date:
- 2026-07-13
- Type:
- Resolution
- Decision:
- Approved (Resolution)
- Address:
- Miami-Opa Locka Executive Airport (OPF)
- Applicant:
- General Asphalt Co., LLC
GENERAL ASPHALT CO. LLC FOR RIM HOT SPOT 3 AT OPF
Miami-Dade County is approving a contract for the Runway Incursion Mitigation (RIM) Hot Spot 3 project at Miami-Opa Locka Executive Airport (OPF). The project aims to enhance safety by improving airfield geometry, signage, and lighting to reduce the risk of runway incursions. General Asphalt Co., LLC was awarded the contract for construction services. The project involves demolition of existing pavements, construction of new taxiways and shoulders, installation of lighting and signage, infield grading, drainage modifications, and new pavement markings. The contract duration is 480 consecutive calendar days. The project is funded by Future Financing (96%) and the Federal Aviation Administration (4%). Davis Bacon Wages are applicable. Due diligence was conducted on General Asphalt Co., LLC, and their performance history is satisfactory. The project was advertised on February 24, 2026, and closed on April 22, 2026, with four bids received. Due to an Interim Final Rule from the U.S. Department of Transportation, DBE program requirements were temporarily suspended for this project.
- Board:
- Aviation and Seaport Committee
- Date:
- 2026-07-13
- Type:
- Resolution
- Decision:
- Approved (Resolution)
- Address:
- Miami-Opa Locka Executive Airport (OPF)
- Applicant:
- General Asphalt Co., LLC
PASSENGER BOARDING BRIDGES (MOD)
Resolution authorizing a five-year extension and $147,080,000 in additional expenditure authority for Prequalification Pool No. RTQ-01841, Passenger Boarding Bridges, for the Miami-Dade Aviation Department (MDAD) and PortMiami. The pool covers purchase and installation of new passenger boarding bridges, refurbishment of existing ones, and purchase of parts and supplies. MDAD requests $137,080,000 for 40 new bridges, refurbishment of 50 existing ones, and parts; PortMiami requests $10,000,000 for new bridges for the North Bulkhead project and modifications/repairs. Current cumulative allocation is $150,384,300; modified cumulative allocation would be $297,464,300. Pool term expires December 31, 2026; extension would expire December 31, 2031. Any contract award over $5,000,000, or $1,500,000 for MDAD, requires Board ratification. Status is In Committee; introduced June 23, 2026; agenda date September 1, 2026. No public comment sentiment is stated in the document.
- Board:
- Aviation and Seaport Committee
- Date:
- 2026-07-13
- Type:
- Resolution
- Decision:
- In Committee (not yet approved/denied/deferred)
- Applicant:
- Strategic Procurement (requester); Miami-Dade Aviation Department and PortMiami (departments)
PASSENGER BOARDING BRIDGES (MOD)
This legislative item concerns a resolution to authorize an additional five years and $147,080,000.00 in expenditure authority for Prequalification Pool No. RTQ-01841, Passenger Boarding Bridges. This pool serves the Miami-Dade Aviation Department (MDAD) and PortMiami. The extension will allow for the continued procurement of new passenger boarding bridges, refurbishment of existing ones, and purchase of parts and supplies. MDAD is allocated $137,080,000.00 for approximately 40 new bridges, 50 refurbishments, and parts. PortMiami is allocated $10,000,000.00 for their operational needs, including the North Bulkhead project. The pool was initially established on November 2, 2021, and will now expire on December 31, 2031, with a modified cumulative allocation of $297,464,300.00. The item is currently 'In Committee' with an Agenda Date of 9/1/2026. There are currently eight prequalified vendors, including two certified Small Business Enterprises (SBE). Public comment is not stated in this document.
- Board:
- Aviation and Seaport Committee
- Date:
- 2026-07-13
- Type:
- Resolution
- Decision:
- In Committee
- Applicant:
- Miami-Dade Aviation Department and PortMiami
PASSENGER BOARDING BRIDGES (MOD)
The document is a legislative item for Miami-Dade County, File Number 261140, a Resolution to authorize an additional five years and $147,080,000 in expenditure authority for Prequalification Pool No. RTQ-01841, Passenger Boarding Bridges, for the Miami-Dade Aviation Department (MDAD) and PortMiami. The total modified cumulative pool amount would be $297,464,300. The pool covers the purchase and installation of new passenger boarding bridges, refurbishment of existing ones, and purchase of parts and supplies. The item was forwarded to the Board of County Commissioners (BCC) with a favorable recommendation from the Aviation and Seaport Committee on 7/13/2026, and is scheduled for the BCC agenda on 9/1/2026. The document does not state a final decision. The pool was established on November 2, 2021, via Resolution No. 1028-21, and expires on December 31, 2026. If approved, the pool would expire on December 31, 2031. MDAD is requesting $137,080,000 for 40 new passenger boarding bridges, refurbishment of 50 existing ones, and parts. PortMiami is requesting $10,000,000 for the North Bulkhead project and modifications/repairs. The document lists eight prequalified vendors. No public comment or stakeholder sentiment is stated in the document.
- Board:
- Aviation and Seaport Committee
- Date:
- 2026-07-13
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation (from Aviation and Seaport Committee on 7/13/2026); final decision not stated
- Applicant:
- Strategic Procurement Department (Requester); Daniella Levine Cava, Mayor (From)
PASSENGER BOARDING BRIDGES (MOD)
Miami-Dade County Board of County Commissioners is considering a resolution to extend Prequalification Pool No. RTQ-01841 for Passenger Boarding Bridges. The extension seeks an additional five years and $147,080,000 in expenditure authority, bringing the total modified cumulative pool amount to $297,464,300. This pool supports the Miami-Dade Aviation Department (MDAD) and PortMiami for the purchase and installation of new passenger boarding bridges, refurbishment of existing ones, and procurement of parts and supplies. MDAD requests $137,080,000 for 40 new bridges, 50 refurbishments, and maintenance parts. PortMiami requests $10,000,000 for new bridges for the North Bulkhead project and modifications. The pool was established on November 2, 2021, and currently has eight prequalified vendors, including four local vendors, two of which are certified Small Business Enterprises (SBE). The extension aims to streamline procurement, reduce administrative work for vendors, and ensure continued operational efficiency. The Aviation and Seaport Committee forwarded this item to the Board with a favorable recommendation.
- Board:
- Aviation and Seaport Committee
- Date:
- 2026-07-13
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation
- Applicant:
- Miami-Dade Aviation Department and PortMiami
PASSENGER BOARDING BRIDGES (MOD)
Resolution adopted on 9/1/2026 authorizing a five-year extension and $147,080,000 in additional expenditure authority for Prequalification Pool No. RTQ-01841, Passenger Boarding Bridges, for the Miami-Dade Aviation Department (MDAD) and PortMiami, bringing the total modified cumulative pool amount to $297,464,300. The pool covers purchase and installation of new passenger boarding bridges, refurbishment of existing ones, and purchase of parts and supplies. MDAD requests $137,080,000 for 40 new bridges, refurbishment of 50 existing ones, and parts; PortMiami requests $10,000,000 for new bridges for the North Bulkhead project and modifications/repairs. Pool expires 12/31/2031. Contract awards over $5,000,000, or $1,500,000 for MDAD, require Board ratification. Eight prequalified vendors are listed, including two certified Small Business Enterprises (SBEs). No public comment or stakeholder sentiment is stated in the document.
- Board:
- Aviation and Seaport Committee
- Date:
- 2026-07-13
- Type:
- Resolution
- Decision:
- Adopted
- Applicant:
- Miami-Dade County Strategic Procurement Department
Mira los negocios reales detrás de estos números
Obtén los registros reales, con direcciones y directivos, respaldados por una garantía de reembolso de 14 días.
Crea tu cuenta