CHANGE ORDER NO. 2 WITH JOHN BELL CONSTRUCTION, INC.

Board of County Commissioners · 2026-06-02 · resolution

Miami-Dade County approved Change Order No. 2 for the Coconut Grove Playhouse Phase 1 project, increasing the contract amount by $1,812,258.98 due to unforeseen structural deterioration and required repairs to the historic gateway building's facade walls and bracing. The total contract amount is now $6,805,189.97. Funding is from Convention Development Tax Bonds (Special Obligation Bond Series 2005). The original contract and Change Order No. 1 were approved under delegated authority, but this increase required Board approval. No public comment was noted in the document.