CEI SERVICES CONTRACT FOR THE UNDERLINE

Board of County Commissioners · 2026-07-21 · resolution

Resolution authorizing Supplemental Agreement No. 1 for Construction, Engineering, and Inspection (CEI) services for The Underline Phase 3, Segments 3 to 9. The agreement increases the contract maximum value to $8,252,721.83 and extends the contract term to 1,654 non-compensable calendar days. The project is a 7.36-mile multimodal corridor beneath the Metrorail system. The original contract was valued at $6,000,000. The supplemental agreement increases the amount by $2,252,721.83 and extends the term by 270 non-compensable calendar days. The project is located within Districts 5 and 7. The resolution was adopted on 7/21/2026.