Skip to main content

Sé el Primero, Construye Relaciones Duraderas

CHANGE ORDER #1 WITH RIC-MAN INTERNATIONAL S-945

Board of County Commissioners · 2026-07-21 · resolution

Resolution ratifying Change Order No. 1 to Contract No. S-945 between Miami-Dade County and Ric-Man International, Inc. for construction of a 60-inch Force Main (NL-1A) (West Segment) along NW 162 Street from NW 6 Avenue to NE 8 Avenue. The change order increases the contract amount by $1,662,315.17 and grants a 426-calendar day compensable time extension, extending the Substantial Completion Date from June 6, 2023 to August 5, 2024 and the Final Completion Date from August 5, 2023 to October 4, 2024. The project is approximately 10,000 linear feet of 60-inch Prestressed Concrete Cylinder Pipe (PCCP) Force Main. The change order addresses utility conflicts, required roadway repairs, tree mitigation, pipe interconnection, failures of asbestos cement pipe water mains, and utility conflicts with Florida Power & Light. The total contract value increases from $19,314,785.95 to $20,977,101.12. The resolution was adopted by the Board of County Commissioners on July 21, 2026. The project has been successfully completed and this change order serves as final contract closeout. The project is in Commission District 4, represented by Commissioner Micky Steinberg. The contract was awarded on January 7, 2021 and ratified by the Board on April 20, 2021 via Resolution No. R-343-21. The project is part of WASD's $8.6 billion Capital Improvement Program. The change order includes $2,439,364.31 in additional costs, offset by a $56,150.00 Value Engineering credit and reallocation of $720,899.14 in unused Contract funds. The compensable time extension is based on a rate of $1,893.61 per day. The change order includes costs for pipe interconnection ($687,529.39), tree mitigation ($394,260.99), failures of asbestos cement pipe water mains ($345,757.80), utility conflicts ($198,596.92), and road repairs ($6,541.35). The interconnection between the 60-inch force main and the existing 72-inch pipeline has not been completed and will be performed under a separate contract. The project required permits from the Department of Regulatory and Economic Resources due to tree canopies and root systems, including removal and replacement of more than 115 trees. The Contractor encountered failures of existing asbestos cement pipe water mains during installation. The Contractor encountered two conflicts with Florida Power & Light utilities. The Contractor removed deteriorated asphalt and repaved an affected area due to a latent drainage issue. The Strategic Procurement Department reviewed the Contract for compliance with Resolution No. R-1001-15 on March 18, 2026. The Contract was awarded with a 4.73 percent Small Business Enterprise Construction goal, a 0.56 percent SBE Goods goal, and a 0.45 percent SBE Services goal. Upon approval, SBE Construction firms will have been paid $1,212,276; SBE Goods firms will have been paid $441,097; and SBE Services firms will have paid $172,034. The change order will be funded through WASD Revenue Bonds Sold and Future WASD Revenue Bonds. There is no impact to the General Fund. The project is in WASD's Fiscal Year 2025-26 Adopted Budget and Multi-Year Capital Plan under North District Force Main Network Infrastructure Improvements, Program #9652101, Volume #3, Page #107. WASD's Deputy Director of Planning, Regulatory Compliance and Capital Infrastructure, Marisela Aranguiz-Cueto, P.E., will oversee implementation. The resolution was introduced on June 30, 2026. The requester is the Water & Sewer Department. The County Attorney was assigned on July 1, 2026. Roy Coley assigned the item on June 30, 2026. The Office of Agenda Coordination assigned the item on June 30, 2026. The Board of County Commissioners adopted the resolution on July 21, 2026. The report was prepared by Sarah E. Davis. The item has 15 pages. The resolution was sponsored by no one. No registered lobbyist is listed. The resolution has no sunset provision. The effective date and expiration date are not stated. The resolution ratifies action by the County Mayor or County Mayor's designee pursuant to Section 2-8.2.12 of the Code of Miami-Dade County, Florida. The Contract was awarded pursuant to WASD's Acceleration Ordinance, which delegates authority to execute change orders that do not exceed ten percent of the base contract amount, subject to ratification by the Board. The change order includes a total amount of $2,439,364.31 in additional costs, partially offset by a $56,150.00 Value Engineering credit and reallocation of $720,899.14 in previously unused Contract funds. The unused funds include $223,221.60 in base Contract funds, $494,850.69 from Dedicated Allowances for permitting and off-duty police services, and $2,826.85 from the Contingency Allowance. The Value Engineering credit relates to the Contractor proposing standard short pipe sections in lieu of closures, eliminating the need for two closures and three double-spigot adapters. The total cost savings associated with the closures and double-spigot adapters amounted to $112,300.00, of which $56,150.00 is credited to WASD and $56,150.00 is paid to the Contractor. The Contractor experienced multiple delays attributable to permitting issues, late design responses, revised requirements, and differing site conditions beyond the Contractor's control. The Contract documents required the new 60-inch force main to connect to an existing 72-inch ductile iron pipe at the intersection of NW 6th Avenue and NW 159th Street. Field conditions were found to differ from those reflected in the design drawings. The cost associated with the relocation of a 16-inch water main belonging to the City of North Miami Beach as well as the exploratory excavation was $171,443.06. The Contractor incurred $516,086.33 in costs associated with planning and attempting the connection. The existing 72-inch pipeline could not be taken out of service without disrupting wastewater conveyance for the service area. The Contractor will be paid $687,529.39 for its efforts. The Project required permits from the Department of Regulatory and Economic Resources due to tree canopies and root systems located along the pipeline installation corridor. Permit requirements included an arborist study, tree risk assessments, preparation of a landscape plan, and the removal and replacement of more than 115 trees. The Contractor will be paid $394,260.99 for the work associated with the RER permits. The Contractor encountered failures of existing asbestos cement pipe during installation of the 60-inch force main along NE and NW 162nd Street and the surrounding areas. Six separate failures occurred, which resulted in production delays, installation interruptions, flooded trenches that required emergency site cleanup, coordination with NMB crews for repairs, safety hazards due to trench instability and underground voids, and repeated remobilizations and traffic control adjustments. The Contractor will be paid $345,757.80 for this work. During installation of the sheet pile on NW 161st Street, the Contractor encountered utilities and site conditions not shown on the design plans. The Contractor relocated the existing conduits. The cost associated with this work is $46,309.59. During installation of the 60-inch force main along the Project corridor, the Contractor encountered underground utilities that had not been identified despite the submission of 811 Sunshine locate tickets and completion of field verification efforts. Attempts to obtain as-built drawings from FPL were unsuccessful. The total cost associated with these efforts is $152,287.33. Additional roadway restoration was required following installation of the 60-inch force main due to deteriorated roadway conditions in the areas of NW 6th Avenue, North Miami Avenue, and NE 162nd Street. The Contractor removed the deteriorated asphalt and repaved the affected area. The Contractor will be compensated $6,541.35 for this roadway work. The document does not state any public comment or stakeholder sentiment.

Follow this across meetings

Mira los negocios reales detrás de estos números

Obtén los registros reales, con direcciones y directivos, respaldados por una garantía de reembolso de 14 días.

Crea tu cuenta