April 21, 2026 City Council Regular Session · 2026-04-21 · agenda_item
The City of Mount Dora is reviewing a project with a total estimated cost of $124,796. This project involves materials, labor, and fees, with a federal share of $112,316.40 and a non-federal share of $12,479.60. The project has a total performance period of 46 months, including 3 months for state contracting, 3 months for construction plans, 3 months for bidding, 3 months for permitting, 18 months for construction, and 6 months for inspections and closeout. This item is currently under review by the City Council. The scope of work will likely involve planning, procurement, and construction phases. Local contractors, suppliers, and service providers are encouraged to reach out early to learn more about potential opportunities as this project moves through the review process, before bids and permits are finalized.
- Total Period of Performance
- 46 Months
- State Contracting
- 3 Months
- Construction Plan/Technical Specifications
- 3 Months
- Bidding / Local Procurement
- 3 Months
- Permitting
- 3 Months
- Construction / Installation
- 18 Months
- Local Inspections / Compliance
- 6 Months
- State Final Inspection / Compliance
- 6 Months
- Closeout Compliance
- 4 Months
- Project Cost - Materials
- 47344.00 $
- Federal Cost - Materials
- 42609.60 $
- Non-Federal Cost - Materials
- 4734.40 $
- Project Cost - Labor
- 63570.00 $
- Federal Cost - Labor
- 57213.00 $
- Non-Federal Cost - Labor
- 6357.00 $
- Project Cost - Fees
- 13882.00 $
- Federal Cost - Fees
- 12493.80 $
- Non-Federal Cost - Fees
- 1388.20 $
- Initial Agreement Amount - Project Cost
- 124796.00 $
- Initial Agreement Amount - Federal Cost
- 112316.40 $
- Initial Agreement Amount - Non-Federal Cost
- 12479.60 $
- Contingency Funds - Project Cost
- 0.00 $
- Contingency Funds - Federal Cost
- 0.00 $
- Contingency Funds - Non-Federal Cost
- 0.00 $
- Project Total - Project Cost
- 124796.00 $
- Project Total - Federal Cost
- 112316.40 $
- Project Total - Non-Federal Cost
- 12479.60 $
- SRMC - SRMC
- 2435.20 $
- SRMC - SRMC Total
- 2435.20 $
- Funding Summary Totals - Federal Share
- 112316.40 $
- Funding Summary Totals - Federal Share Percentage
- 90.00 %
- Funding Summary Totals - Non-Federal Share
- 12479.60 $
- Funding Summary Totals - Non-Federal Share Percentage
- 10.00 %
- Funding Summary Totals - Total Project Cost
- 124796.00 $
- Funding Summary Totals - Total Project Cost Percentage
- 100.00 %
- SRMC - SRMC (100% Federal)
- 2435.20 $
Industries that could win this work
- General Contractor
- Building & Industrial Supply
- Engineering & Architecture
- Legal Services
- Government Authority
Follow this across meetings
Mira los negocios reales detrás de estos números
Obtén los registros reales, con direcciones y directivos, respaldados por una garantía de reembolso de 14 días.
Crea tu cuenta