4. Aluminum Handrails $ 15,229.73

May 5, 2026 City Council Regular Session · 2026-05-05 · agenda_item

Faden Builders, Inc. is proposing to install aluminum handrails with a Gross Maximum Price of $226,464.34. This project is currently under review by the City of Mount Dora. The work involves a 4-week period for material procurement and submittals, followed by 6 weeks for mobilization and demolition. This project will require site preparation, demolition, and installation of new handrails. Local contractors, trades, suppliers, and service providers are encouraged to reach out to Faden Builders, Inc. early in the process, before bids and permits are finalized, to explore potential opportunities.

Aluminum Handrails
15229.73 $
Subtotal
193064.23 $
General Liability Insurance
2509.83 $
Contingency
9653.21 5%
Contractor’s Fee
21237.06 $
Permit Fee
1000.00 $
Gross Maximum Price
226464.34 $
material vendors
30 days
material procurement and submittals
4 weeks
mobilization and demolition
6 weeks

Industries that could win this work

  • General Contractor
  • Site Prep, Grading & Hardscape
  • Concrete & Masonry
  • Painting & Flooring
  • Building & Industrial Supply

Follow this across meetings

Mira los negocios reales detrás de estos números

Obtén los registros reales, con direcciones y directivos, respaldados por una garantía de reembolso de 14 días.

Crea tu cuenta