4. Aluminum Handrails $ 15,229.73
May 5, 2026 City Council Regular Session · 2026-05-05 · agenda_item
Faden Builders, Inc. is proposing to install aluminum handrails with a Gross Maximum Price of $226,464.34. This project is currently under review by the City of Mount Dora. The work involves a 4-week period for material procurement and submittals, followed by 6 weeks for mobilization and demolition. This project will require site preparation, demolition, and installation of new handrails. Local contractors, trades, suppliers, and service providers are encouraged to reach out to Faden Builders, Inc. early in the process, before bids and permits are finalized, to explore potential opportunities.
- Aluminum Handrails
- 15229.73 $
- Subtotal
- 193064.23 $
- General Liability Insurance
- 2509.83 $
- Contingency
- 9653.21 5%
- Contractor’s Fee
- 21237.06 $
- Permit Fee
- 1000.00 $
- Gross Maximum Price
- 226464.34 $
- material vendors
- 30 days
- material procurement and submittals
- 4 weeks
- mobilization and demolition
- 6 weeks
Industries that could win this work
- General Contractor
- Site Prep, Grading & Hardscape
- Concrete & Masonry
- Painting & Flooring
- Building & Industrial Supply
Follow this across meetings
Applicants and firms
Mira los negocios reales detrás de estos números
Obtén los registros reales, con direcciones y directivos, respaldados por una garantía de reembolso de 14 días.
Crea tu cuenta