A) Change Order No. 1 to the Contract (R2025-0675) with Browning Chapman, LLC

Palm Beach County Board of County Commissioners · 2026-06-09 · agenda_item

Palm Beach County is considering a change order for repairs to Parking Garage 3 at Palm Beach International Airport. This project involves extending the contract duration by 142 days and adding $228,434.65 to the existing contract with Browning Chapman, LLC. The item is currently under review by the Board of County Commissioners. This change order could lead to further work related to the parking garage repairs, potentially including site work, concrete, electrical, plumbing, HVAC, and finishing trades. Local contractors, suppliers, and service providers are encouraged to reach out to the county or the listed contractor early to learn more about potential opportunities as the project progresses before final bids and permits are set.

change_order_amount
228,434.65 $
project_duration_extension
142 calendar days

Industries that could win this work

  • General Contractor
  • Concrete & Masonry
  • Electrical
  • HVAC & Climate Control
  • Plumbing
  • Painting & Flooring
  • Site Prep, Grading & Hardscape
  • Building & Industrial Supply
  • Real Estate Development
  • Engineering & Architecture

Follow this across meetings

Applicants and firms

Mira los negocios reales detrás de estos números

Obtén los registros reales, con direcciones y directivos, respaldados por una garantía de reembolso de 14 días.

Crea tu cuenta