2. Staff recommends motion to approve: Change Order No. 16 to the contract with R &

Palm Beach County Board of County Commissioners · 2026-07-07 · agenda_item

Palm Beach County is considering a change order for the Lyons Road/Sansbury’s Way Buffered Bike Lanes project. This change order, number 16, requests a 264-day extension to the contract with R & D Paving, LLC. The extension is needed to cover the time between February 10, 2025, and November 1, 2025, for remobilization to complete additional drainage improvements requested by the County. The original contract was approved on September 13, 2022, for over $5.8 million. With this change order and others, the total contract amount is now over $6.7 million. The project is funded by a federal grant through the Florida Department of Transportation. This item is currently under review, with staff recommending approval. The project involves work related to bike lanes and drainage improvements. Contractors specializing in paving, site preparation, grading, concrete, and drainage systems may find opportunities related to this project. Reaching out to the county or the contractor R & D Paving, LLC early could provide insight into potential future needs as the project nears final completion and acceptance.

change order number
16
contract date
September 13, 2022
contract number
R2022-0914
time extension
264 days
demobilization date
February 10, 2025
remobilization period start
February 10, 2025
remobilization period end
November 1, 2025
original contract amount
5,862,084.91 $
total contract amount
6,791,719.75 $
final acceptance date
December 13, 2025
federal grant reference
R2021 -1899

Industries that could win this work

  • Site Prep, Grading & Hardscape
  • Concrete & Masonry
  • General Contractor
  • Building & Industrial Supply

Follow this across meetings

Mira los negocios reales detrás de estos números

Obtén los registros reales, con direcciones y directivos, respaldados por una garantía de reembolso de 14 días.

Crea tu cuenta