3. Staff recommends motion to approve: Change Order No. 22 in the amount of

Palm Beach County Board of County Commissioners · 2026-08-25 · agenda_item

Palm Beach County staff recommends approval of a change order for the Seminole Pratt Whitney Road and Northlake Boulevard Intersection Improvements Project. This change order adds $286,228.36 to the existing contract and grants a retroactive 61-day time extension. The additional work is due to unforeseen sinkhole repairs caused by the collapse of two existing 72-inch corrugated metal pipes. The project is currently under review by the Board of County Commissioners. This change order will involve site work and repairs related to the pipe collapses. Contractors, suppliers, and service providers interested in future work related to infrastructure projects should monitor this and similar county initiatives. Early engagement with county staff and the prime contractor can provide valuable insights as plans and bids are developed.

change_order_amount
286,228.36 $
retroactive_time_extension
61 days
pipe_diameter
72 inch
number_of_pipes_collapsed
2
contract_time_extension_for_repairs
13 day
contract_time_extension_for_delays
48 day
original_contract_amount
17,999,999 $
total_contract_amount_including_change_order
22,588,698.82 $
original_completion_date_extension
61 -day
estimated_completion
September 2026
small_business_enterprise_participation_goal
20 %
committed_sbe_participation
20.20 %
proposed_sbe_participation_for_change_order
20 %
achieved_sbe_participation_to_date
23.96 %

Industries that could win this work

  • General Contractor
  • Site Prep, Grading & Hardscape
  • Building & Industrial Supply
  • Engineering & Architecture
  • Real Estate Development

Follow this across meetings

Mira los negocios reales detrás de estos números

Obtén los registros reales, con direcciones y directivos, respaldados por una garantía de reembolso de 14 días.

Crea tu cuenta