4. Staff recommends motion to approve: Change Order No. 15 in the amount of
Palm Beach County Board of County Commissioners · 2026-08-25 · agenda_item
Palm Beach County is considering a change order for the Westgate Avenue project, which extends from Wabasso Drive to Congress Avenue. This project involves work on Westgate Avenue. The proposed change order, number 15, is for $318,272.68 and adds 371 days to the contract completion time. The original contract was for $7,658,620.34, and with this change order, the total contract amount will be $8,432,197.08. The project's completion date is now expected to be July 16, 2026. This project is currently under review by the Board of County Commissioners. The work involves replacing stolen wiring and pull boxes, which will likely require site work, utility repairs, and potentially paving and electrical trades. Contractors, suppliers, and service providers interested in this project should reach out early, as this is an opportunity to engage before final bids and permits are set.
- change order amount
- 318,272.68 $
- time extension
- 371 days
- original contract date
- September 19, 2023
- original contract amount
- 7,658,620.34 $
- total contract amount
- 8,432,197.08 $
- new completion date
- July 16, 2026
- change order threshold
- 200,000 $
Industries that could win this work
- General Contractor
- Electrical
- Site Prep, Grading & Hardscape
- Building & Industrial Supply
- Engineering & Architecture
Follow this across meetings
Applicants and firms
Mira los negocios reales detrás de estos números
Obtén los registros reales, con direcciones y directivos, respaldados por una garantía de reembolso de 14 días.
Crea tu cuenta