5. Staff recommends motion to receive and file: Change Order No. 12 in the amount
Palm Beach County Board of County Commissioners · 2026-08-25 · agenda_item
This notice concerns a change order for the Lawrence Road project, located south of Ponza Place to Lantana Road. The project involves road improvements. The original contract was approved on April 4, 2023, for $7,659,014.25. This is a notice about Change Order No. 12, which adds $187,608.65 to the contract, and Change Order No. 13, which adds $175,881.53. The total contract amount is now $9,269,990.49. A pending change order also requests a 39-day time extension for weather and holidays, moving the completion date to July 10, 2025. This item is currently under review by the Palm Beach County Board of County Commissioners. The work involves ongoing road construction and related infrastructure. Contractors, suppliers, and service providers involved in road construction, site work, and utility services may find opportunities. Early engagement before final bids and permits could be advantageous.
- Change Order No. 12 amount
- 187,608.65 $
- original contract date
- April 4, 2023
- original contract amount
- 7,659,014.25 $
- total contract amount including Change Order No. 12
- 9,094,108.96 $
- Change Order No. 13 amount
- 175,881.53 $
- final contract amount
- 9,269,990.49 $
- retroactive time extension
- 39 days
- original completion date
- June 2, 2025
- new completion date
- July 10, 2025
- Small Business Enterprise (SBE) participation minimum
- 15 %
- SBE participation committed
- 17.75 %
- SBE participation for Change Order No. 12
- 0 %
- overall SBE participation achieved to date
- 8.98 %
Industries that could win this work
- General Contractor
- Site Prep, Grading & Hardscape
- Utilities (Sub)
- Building & Industrial Supply
Follow this across meetings
Applicants and firms
Mira los negocios reales detrás de estos números
Obtén los registros reales, con direcciones y directivos, respaldados por una garantía de reembolso de 14 días.
Crea tu cuenta