1. The original completion date: May 11, 2026 2. Previously modified date:3. Number of Days to Add: 604. New completion date: July 10, 2026

Commission Regular Meeting · 2026-06-11 · agenda_item

Santa Rosa County is moving forward with the Madura Five Pump Station Rehabilitation and Hydraulic Improvements Project. The project was paused for property acquisition, which has now been completed. County staff have asked the project's design consultant to add a new task: creating a separate bid package for long-lead-time equipment. This is planned to speed up getting materials and allow more time to confirm state funding. This change order is currently under review by the Board of County Commissioners. The work will involve developing bid documents for specialized equipment. This early stage offers opportunities for suppliers of long-lead-time equipment and components, as well as contractors who can support the procurement process before final bids and permits are settled.

amount
28,000.00 $

Industries that could win this work

  • General Contractor
  • Construction (Other)
  • Utilities (Sub)
  • Building & Industrial Supply
  • Engineering & Architecture

Follow this across meetings

Applicants and firms

Mira los negocios reales detrás de estos números

Obtén los registros reales, con direcciones y directivos, respaldados por una garantía de reembolso de 14 días.

Crea tu cuenta