18) Environmental – Time Only Change Order for Phase V Landfill Expansion Cell D
Commission Regular Meeting · 2026-06-11 · agenda_item
Santa Rosa County is considering a change order for the Central Landfill Phase V, Expansion, Cell D project. This change order, identified as #2 for contract 25-0023, would add 60 days to the contract for Panhandle Grading and Paving, Inc. The project involves utility coordination and installation for FPL overhead power service. The substantial completion date would be extended to July 10, 2026, with an additional 30 days for final completion. This item is currently under review by the Commission. The work involves ongoing utility coordination and installation, which may lead to future needs for site preparation, grading, paving, and potentially specialized utility contractors. Local contractors, suppliers, and service providers are encouraged to monitor this project's progress, as early engagement before final bid and permit stages could offer a competitive advantage for upcoming phases.
- contract number
- 25-0023
- additional days for substantial completion
- 60 days
- substantial completion date
- July 10, 2026
- additional days for final completion
- 30 days
Industries that could win this work
- Site Prep, Grading & Hardscape
- Concrete & Masonry
- Electrical
- Utilities (Sub)
- Engineering & Architecture
- Building & Industrial Supply
Follow this across meetings
Applicants and firms
Mira los negocios reales detrás de estos números
Obtén los registros reales, con direcciones y directivos, respaldados por una garantía de reembolso de 14 días.
Crea tu cuenta