9) EDO - Whiting Aviation Park Taxiway Construction Change Order
Commission Regular Meeting · 2026-06-11 · agenda_item
Santa Rosa County is considering a change order for the Whiting Aviation Park Taxiway Construction project. This change order, if approved, would add $893,495.56 to the contract and extend the project timeline by 70 days. The project involves the construction of taxiways at the Whiting Aviation Park. This item is currently under review by the Commission. The work would likely involve additional site preparation, grading, concrete, paving, and potentially utility adjustments related to the taxiway expansion. Contractors specializing in heavy civil construction, site work, concrete, and paving may find opportunities as this project moves forward. Engaging early could provide an advantage before final bids and permits are set.
- change order amount
- 893495.56 $
- contract extension
- 70 days
Industries that could win this work
- General Contractor
- Site Prep, Grading & Hardscape
- Concrete & Masonry
Follow this across meetings
Locations
Mira los negocios reales detrás de estos números
Obtén los registros reales, con direcciones y directivos, respaldados por una garantía de reembolso de 14 días.
Crea tu cuenta