10. Task Order No. CDM-08 to the Professional Services Agreement for the Water
City Council Meeting · 2026-04-14 · agenda_item
The City of Melbourne is planning improvements to the electrical and emergency power systems at the Joe Mullins Reverse Osmosis Water Treatment Plant (ROWTP). This project involves providing dedicated standby generators for Production Wells No. 1 and No. 2. The work will include geotechnical studies, design, permitting, and bidding. The project is expected to take about 305 days to complete once started. This is an early stage opportunity, as the task order has just been approved. The project will require site clearing and grading, underground utility work, electrical system upgrades, and installation of new generators. Local contractors, suppliers, and service providers in electrical, heavy construction, and utility services may find opportunities. Reaching out now, before detailed plans and bids are finalized, could provide a competitive advantage.
- Task Order No.
- CDM-08
- Project No.
- 31223
- Task Order amount
- 327,322 $
- number of existing production wells
- 4
- number of additional production wells under construction
- 2
- number of production wells sharing one generator
- 2
- number of new generators to be installed
- 2
- project duration
- 305 calendar days
Industries that could win this work
- Electrical
- Site Prep, Grading & Hardscape
- Utilities (Sub)
- Building & Industrial Supply
- Engineering & Architecture
- Waste Management
Follow this across meetings
Board
City Council MeetingApplicants and firms
Locations
Mira los negocios reales detrás de estos números
Obtén los registros reales, con direcciones y directivos, respaldados por una garantía de reembolso de 14 días.
Crea tu cuenta