b. Task Order No. DRMP-I-2025-007 to the Continuing Contract for

City Council Meeting · 2026-04-14 · agenda_item

The City of Melbourne is moving forward with the Hoag Avenue Roadway Improvements Project, Project No. 04126. This project involves the design for paving approximately 1,000 feet of a 2-lane roadway, including stormwater treatment and conveyance, signage, striping, and utility design for sewer lateral installations. The scope of work includes surveying, geotechnical design, and environmental permitting. Technical specifications, bid documents, and bid support are also part of the design services. This item is currently under review, with a task order for professional consulting services approved. The project is planned to address the paving of Hoag Avenue east of US Highway 1. Contractors specializing in site preparation, grading, concrete, paving, electrical, plumbing, HVAC, and landscaping could find opportunities as the project progresses through design and into construction phases. Early engagement with the city or the designated consultant may provide insight into upcoming bid opportunities.

Task Order No.
DRMP-I-2025-007
Project No.
04126
Task Order Amount
125,800 $
Roadway Length
1,000 feet
Task Order Completion Time
300 days
Estimated Construction Cost Range
400,000 to 800,000 $
FY19 Unpaved Roads Program Project No.
64219
Budget Transfer Amount
125,800 $

Industries that could win this work

  • Site Prep, Grading & Hardscape
  • Concrete & Masonry
  • Painting & Flooring
  • Electrical
  • Plumbing
  • HVAC & Climate Control
  • Engineering & Architecture
  • Building & Industrial Supply
  • Real Estate Development
  • Landscaping & Lawn Service
  • Government Authority

Follow this across meetings

Mira los negocios reales detrás de estos números

Obtén los registros reales, con direcciones y directivos, respaldados por una garantía de reembolso de 14 días.

Crea tu cuenta