2. Such alternative action as the Commission may deem appropriate.
City Commission Meeting · 2026-04-13 · agenda_item
The City of Leesburg is reviewing a proposed budget increase for the Susan Street Sports Complex. This project involves additional costs for excavation, rock, bleachers, scoreboards, and field goal posts. The original construction budget is being increased by $650,000 to cover these overruns, bringing the total construction budget to $11,213,259.42. This item is currently under review by the City Commission. The work involves significant site preparation, including excavation and the addition of rock filtration for stormwater management. This project could create opportunities for contractors involved in site clearing, grading, concrete work, and potentially specialized trades for sports facility construction. Early engagement may be beneficial as the project moves through its review process.
- budget increase
- 650,000 $
- total construction budget
- 11,213,259.42 $
- overruns
- 175,000 $
- second overrun
- 252,686 $
- Bleachers
- 113,806 $
- Scoreboards
- 112,350 $
- Field Goal Posts
- 26,350 $
- initial payment for mitigation
- 140,000 $
- projected construction budget over budget
- 517,686 $
- estimated increase
- 125,000 $
- Championship Field excavation and rock overruns
- 751,250 $
- contingency
- 960,963 $
- Downtown Parking Lot Project shift
- 650,000 $
- Downtown Parking Lot Project under budget
- 1.5 million
- estimated project completion cost
- 11,163,259 $
- next lowest bid
- 12,306,470 $
Industries that could win this work
- General Contractor
- Site Prep, Grading & Hardscape
- Concrete & Masonry
- Engineering & Architecture
Follow this across meetings
Applicants and firms
Locations
Mira los negocios reales detrás de estos números
Obtén los registros reales, con direcciones y directivos, respaldados por una garantía de reembolso de 14 días.
Crea tu cuenta