2. Such alternative action as the Commission may deem appropriate.

City Commission Meeting · 2026-04-13 · agenda_item

The City of Leesburg is reviewing a proposed budget increase for the Susan Street Sports Complex. This project involves additional costs for excavation, rock, bleachers, scoreboards, and field goal posts. The original construction budget is being increased by $650,000 to cover these overruns, bringing the total construction budget to $11,213,259.42. This item is currently under review by the City Commission. The work involves significant site preparation, including excavation and the addition of rock filtration for stormwater management. This project could create opportunities for contractors involved in site clearing, grading, concrete work, and potentially specialized trades for sports facility construction. Early engagement may be beneficial as the project moves through its review process.

budget increase
650,000 $
total construction budget
11,213,259.42 $
overruns
175,000 $
second overrun
252,686 $
Bleachers
113,806 $
Scoreboards
112,350 $
Field Goal Posts
26,350 $
initial payment for mitigation
140,000 $
projected construction budget over budget
517,686 $
estimated increase
125,000 $
Championship Field excavation and rock overruns
751,250 $
contingency
960,963 $
Downtown Parking Lot Project shift
650,000 $
Downtown Parking Lot Project under budget
1.5 million
estimated project completion cost
11,163,259 $
next lowest bid
12,306,470 $

Industries that could win this work

  • General Contractor
  • Site Prep, Grading & Hardscape
  • Concrete & Masonry
  • Engineering & Architecture

Follow this across meetings

Applicants and firms

Locations

See the actual businesses behind these numbers

Get the real filings, with addresses and officers, backed by a 14-day money-back guarantee.

Create your account