AWARD TO ITG COMMUNICATIONS FOR S-20298

Resolution awarding Contract No. S-20298, Venetian Causeway Water Main and Sewer Force Main Relocation, to ITG Communications LLC for $3,096,425.02 with a 231-calendar-day contract period. The project is located at 1225 Venetian Causeway, Miami Beach, Florida 33139, in Commission District 3. The work involves relocating a 6-inch sewer force main and a 30-inch subaqueous water main at Bridge No. 2 between Biscayne Island and San Marco Island to accommodate a bridge replacement. The project includes approximately 1,500 linear feet of HDPE water main and approximately 2,100 linear feet of HDPE force main installed via horizontal direction drill. The resolution was adopted by the Board of County Commissioners on July 21, 2026. The contract period is 231 calendar days: 180 days to Substantial Completion, 210 days to Final Completion, and 21 days Contingency Time Allowance. The work must be completed before March 2027. The bid was approximately 44.43% below the Engineer of Record's Opinion of Probable Cost of $5,571,630.00. No public comment or stakeholder sentiment is stated in the document.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Adopted
Address:
1225 Venetian Causeway, Miami Beach, Florida 33139
Applicant:
ITG Communications LLC

AWARD TO ITG COMMUNICATIONS FOR S-20298

Miami-Dade County Board of County Commissioners adopted Resolution R-648-26 (File Number 261270) on July 21, 2026, awarding Contract No. S-20298, Venetian Causeway Water Main and Sewer Force Main Relocation, to ITG Communications LLC for $3,096,425.02 with a 231-calendar-day contract period. The project is located at 1225 Venetian Causeway, Miami Beach, Florida 33139, in Commission District 3. The work involves relocating a 6-inch sewer force main and a 30-inch subaqueous water main at Bridge No. 2 between Biscayne Island and San Marco Island to accommodate a bridge replacement. The project includes approximately 1,500 linear feet of HDPE water main and approximately 2,100 linear feet of HDPE force main installed via horizontal direction drill. The contract was recommended by the Infrastructure, Innovation & Technology Committee on July 15, 2026, and forwarded to the Board on July 20, 2026. The bid was approximately 44.43% below the Engineer of Record's Opinion of Probable Cost of $5,571,630.00. No public comment or stakeholder sentiment is stated in the document.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Adopted
Address:
1225 Venetian Causeway, Miami Beach, Florida 33139
Applicant:
Miami-Dade Water and Sewer Department (WASD); Contractor: ITG Communications LLC

AWARD TO ITG COMMUNICATIONS FOR S-20298

Miami-Dade County Board of County Commissioners adopted Resolution R-648-26 (File Number 261270) on July 21, 2026, awarding Contract No. S-20298, Venetian Causeway Water Main and Sewer Force Main Relocation, to ITG Communications LLC for $3,096,425.02 with a contract period of 231 calendar days. The project is located at 1225 Venetian Causeway, Miami Beach, Florida 33139, in Commission District 3. The work involves relocating a 6-inch sewer force main and a 30-inch subaqueous water main at Bridge No. 2, between Biscayne Island and San Marco Island, to accommodate a bridge replacement. The project includes approximately 1,500 linear feet of HDPE water main and approximately 2,100 linear feet of HDPE force main installed via horizontal directional drilling. The contract was recommended by the Infrastructure, Innovation & Technology Committee on July 15, 2026, and forwarded to the Board on July 20, 2026. ITG's bid was approximately 44.43% below the Engineer of Record's opinion of probable cost of $5,571,630.00. Nine bids were received on June 25, 2026. No public comment or stakeholder sentiment is stated in the document.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Adopted
Address:
1225 Venetian Causeway, Miami Beach, Florida 33139
Applicant:
ITG Communications LLC

AWARD TO ITG COMMUNICATIONS FOR S-20298

Miami-Dade County Board of County Commissioners adopted Resolution R-648-26 (File Number 261270) on July 21, 2026, awarding Contract No. S-20298, Venetian Causeway Water Main and Sewer Force Main Relocation, to ITG Communications LLC for $3,096,425.02 with a contract period of 231 calendar days. The project is located at 1225 Venetian Causeway, Miami Beach, Florida 33139, in Commission District 3. The work involves relocating a 6-inch sewer force main and a 30-inch subaqueous water main to accommodate the replacement of Bridge No. 2 between Biscayne Island and San Marco Island. The project includes approximately 1,500 linear feet of HDPE water main and approximately 2,100 linear feet of HDPE force main installed via horizontal direction drill. The contract period includes 180 calendar days to Substantial Completion, 210 calendar days to Final Completion, and 21 calendar days Contingency Time Allowance. The relocation must be completed before March 2027. The contract was awarded to the lowest responsive and responsible bidder, with ITG's bid approximately 44.43% below the Engineer of Record's Opinion of Probable Cost of $5,571,630.00. The Board also authorized the County Mayor or designee to use the Consent Decree and Capital Improvement Programs Acceleration Ordinance (Section 2-8.2.12) to manage the contract and to execute the contract and exercise termination provisions. The fiscal impact is $3,096,425.02, inclusive of the Inspector General Fee. The project is funded by WASD Revenue Bonds Sold, Future WASD Revenue Bonds, and Wastewater Renewal and Replacement Fund. Annual operations cost impact is $50,000.00 and annual maintenance cost impact is $50,000.00, both funded by WASD Operating Revenues. The project life expectancy is 50 years. The contract manager is Paul Adams (786-863-9425) and the project manager is David Vazquez (786-552-4447). The Infrastructure, Innovation & Technology Committee forwarded the item to the BCC with a favorable recommendation on July 15, 2026, and again on July 20, 2026. The item was introduced on July 9, 2026. No public comment or stakeholder sentiment is stated in the document.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Adopted
Address:
1225 Venetian Causeway, Miami Beach, Florida 33139
Applicant:
ITG Communications LLC

AWARD TO ITG COMMUNICATIONS FOR S-20298

The Miami-Dade Board of County Commissioners adopted Resolution R-648-26 (File Number 261270) on July 21, 2026, awarding Contract No. S-20298 for the Venetian Causeway Water Main and Sewer Force Main Relocation to ITG Communications LLC in the amount of $3,096,425.02 with a contract period of 231 calendar days. The project is located at 1225 Venetian Causeway, Miami Beach, Florida 33139, in Commission District 3. The work involves relocating a 6-inch sewer force main and a 30-inch subaqueous water main at Bridge No. 2, located between Biscayne Island and San Marco Island, to accommodate the bridge replacement. The project includes approximately 1,500 linear feet of HDPE water main and approximately 2,100 linear feet of HDPE force main installed via horizontal direction drill. The contract period includes 180 calendar days to Substantial Completion, 210 calendar days to Final Completion, and 21 calendar days Contingency Time Allowance. The relocation must be completed before March 2027. The bid was approximately 44.43% below the Engineer of Record's Opinion of Probable Cost of $5,571,630.00. The fiscal impact is $3,096,425.02, inclusive of the Inspector General Fee. The funding sources are WASD Revenue Bonds Sold, Future WASD Revenue Bonds, and Wastewater Renewal and Replacement Fund. The life expectancy of the project is 50 years. Annual operations cost impact is $50,000.00 and annual maintenance cost impact is $50,000.00, both funded by WASD Operating Revenues. The project does not include Art in Public Places. The contract manager is Paul Adams at 786-863-9425. The project manager is David Vazquez at 786-552-4447. The Infrastructure, Innovation & Technology Committee forwarded the item to the Board with a favorable recommendation on July 15, 2026, and again on July 20, 2026. The item was introduced on July 9, 2026. There were no protests to the award. No public comment or stakeholder sentiment is stated in the document.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Adopted on July 21, 2026
Address:
1225 Venetian Causeway, Miami Beach, Florida 33139
Applicant:
ITG Communications LLC

AWARD TO ITG COMMUNICATIONS FOR S-20298

Miami-Dade County Board of County Commissioners adopted Resolution R-648-26 (File Number 261270) on July 21, 2026, awarding Contract No. S-20298, Venetian Causeway Water Main and Sewer Force Main Relocation, to ITG Communications LLC for $3,096,425.02 with a contract period of 231 calendar days. The project is located at 1225 Venetian Causeway, Miami Beach, Florida 33139, in Commission District 3. The work involves relocating a 6-inch sewer force main and a 30-inch subaqueous water main at Bridge No. 2 between Biscayne Island and San Marco Island to accommodate a bridge replacement. The project includes approximately 1,500 linear feet of HDPE water main and approximately 2,100 linear feet of HDPE force main installed via horizontal direction drill. The contract was awarded to the lowest responsive and responsible bidder, with a bid approximately 44.43% below the Engineer of Record's Opinion of Probable Cost of $5,571,630.00. The project must be completed before March 2027. No public comment or stakeholder sentiment is stated in the document.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Adopted
Address:
1225 Venetian Causeway, Miami Beach, Florida 33139
Applicant:
Miami-Dade Water and Sewer Department (WASD); contractor ITG Communications LLC

AWARD TO ITG COMMUNICATIONS FOR S-20298

Resolution awarding Contract No. S-20298, Venetian Causeway Water Main and Sewer Force Main Relocation, to ITG Communications LLC in the amount of $3,096,425.02 with a contract period of 231 calendar days. The project consists of two pipeline installations via horizontal direction drill (HDD) for water and sewer infrastructure to cross Biscayne Bay waterway under Venetian Causeway Bridge No. 2 between Biscayne Island and San Marco Island. The water portion includes approximately 1,500 linear feet of high-density polyethylene (HDPE) water main, and the sewer portion includes approximately 2,100 linear feet of HDPE force main. The contract was awarded to the lowest responsive and responsible bidder, with a bid approximately 44.43% below the Engineer of Record's Opinion of Probable Cost. The project supports the replacement of the historic Venetian Causeway Bridge No. 2. The Board of County Commissioners adopted the resolution on July 21, 2026. The Infrastructure, Innovation & Technology Committee forwarded it to the BCC with a favorable recommendation on July 15, 2026. The contract is managed under the Miami-Dade Water and Sewer Department's Consent Decree and Capital Improvement Programs Acceleration Ordinance, Section 2-8.2.12. No public comment or stakeholder sentiment is stated in the document.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Adopted
Address:
1225 Venetian Causeway, Miami Beach, Florida 33139
Applicant:
ITG Communications LLC

AWARD TO ITG COMMUNICATIONS FOR S-20298

Miami-Dade County Board of County Commissioners adopted Resolution R-648-26 (File No. 261270) on July 21, 2026, awarding Contract No. S-20298, Venetian Causeway Water Main and Sewer Force Main Relocation, to ITG Communications LLC for $3,096,425.02 with a 231-calendar-day contract period. The project is located at 1225 Venetian Causeway, Miami Beach, Florida 33139, in Commission District 3. The work involves relocating a 6-inch sewer force main and a 30-inch subaqueous water main at Bridge No. 2 between Biscayne Island and San Marco Island to accommodate bridge replacement. The project includes approximately 1,500 linear feet of HDPE water main and approximately 2,100 linear feet of HDPE force main installed via horizontal direction drill. The contract period is 231 calendar days: 180 days to Substantial Completion, 210 days to Final Completion, and 21 days Contingency Time Allowance. The bid was approximately 44.43% below the Engineer of Record's Opinion of Probable Cost of $5,571,630.00. The project is funded by WASD Revenue Bonds Sold, Future WASD Revenue Bonds, and Wastewater Renewal and Replacement Fund. Annual operations cost impact is $50,000.00 and annual maintenance cost impact is $50,000.00. The project life expectancy is 50 years. The contract manager is Paul Adams (786-863-9425). The project manager is David Vazquez (786-552-4447).

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Adopted
Address:
1225 Venetian Causeway, Miami Beach, Florida 33139
Applicant:
Miami-Dade Water and Sewer Department (WASD); Contractor: ITG Communications LLC

AWARD TO ITG COMMUNICATIONS FOR S-20298

Miami-Dade County Board of County Commissioners awarded Contract No. S-20298 for Venetian Causeway Water Main and Sewer Force Main Relocation to ITG Communications LLC for $3,096,425.02. The project involves relocating existing water and sewer facilities at Venetian Causeway Bridge No. 2, between Biscayne Island and San Marco Island, to accommodate bridge replacement. The contract period is 231 calendar days. The work includes approximately 1,500 linear feet of HDPE water main and 2,100 linear feet of HDPE force main installation via horizontal direction drill. The project is funded by WASD Revenue Bonds Sold, Future WASD Revenue Bonds, and Wastewater Renewal and Replacement Fund. No public comment was noted in the document.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Awarded
Address:
1225 Venetian Causeway, Miami Beach, Florida 33139
Applicant:
ITG Communications LLC

AWARD TO ITG COMMUNICATIONS FOR S-20298

Miami-Dade County Board of County Commissioners adopted Resolution R-648-26 (File Number 261270) on July 21, 2026, awarding Contract No. S-20298, Venetian Causeway Water Main and Sewer Force Main Relocation, to ITG Communications LLC for $3,096,425.02 with a contract period of 231 calendar days. The project is located at 1225 Venetian Causeway, Miami Beach, Florida 33139, in Commission District 3. The work involves relocating a 6-inch sewer force main and a 30-inch subaqueous water main to accommodate the replacement of Bridge No. 2 between Biscayne Island and San Marco Island. The project includes approximately 1,500 linear feet of HDPE water main and approximately 2,100 linear feet of HDPE force main installed via horizontal direction drill. The contract was recommended by the Infrastructure, Innovation & Technology Committee on July 15, 2026, and forwarded to the Board on July 20, 2026. The bid was approximately 44.43% below the Engineer of Record's Opinion of Probable Cost of $5,571,630.00. No public comment or stakeholder sentiment is stated in the document.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Adopted
Address:
1225 Venetian Causeway, Miami Beach, Florida 33139
Applicant:
Miami-Dade Water and Sewer Department (WASD); contractor ITG Communications LLC

AWARD TO ITG COMMUNICATIONS FOR S-20298

Miami-Dade County Board of County Commissioners adopted Resolution R-648-26 (File Number 261270) on July 21, 2026, awarding Contract No. S-20298 for the Venetian Causeway Water Main and Sewer Force Main Relocation to ITG Communications, LLC. The contract amount is $3,096,425.02 with a contract period of 231 calendar days (180 days to Substantial Completion, 210 days to Final Completion, 21 days Contingency Time Allowance). The project involves relocating a 6-inch sewer force main and a 30-inch subaqueous water main at Bridge No. 2 of the Venetian Causeway, located between Biscayne Island and San Marco Island, to accommodate a bridge replacement. The work includes approximately 1,500 linear feet of HDPE water main and approximately 2,100 linear feet of HDPE force main installed via horizontal direction drill (HDD), plus open-cut connections. The project must be completed before March 2027. ITG's bid was approximately 44.43% below the Engineer of Record's Opinion of Probable Cost of $5,571,630.00. Nine bids were received and opened on June 25, 2026. No public comment or stakeholder sentiment is stated in the document.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Adopted
Address:
1225 Venetian Causeway, Miami Beach, Florida 33139
Applicant:
ITG Communications, LLC

AWARD TO ITG COMMUNICATIONS FOR S-20298

Resolution awarding Contract No. S-20298, Venetian Causeway Water Main and Sewer Force Main Relocation, to ITG Communications LLC for $3,096,425.02 with a 231 calendar day contract period. The project is located at 1225 Venetian Causeway, Miami Beach, Florida 33139, in Commission District 3. The work involves relocating a 6-inch sewer force main and a 30-inch subaqueous water main at Bridge No. 2 between Biscayne Island and San Marco Island to accommodate a bridge replacement. The project includes approximately 1,500 linear feet of HDPE water main and approximately 2,100 linear feet of HDPE force main installed via horizontal direction drill. The resolution was adopted by the Board of County Commissioners on July 21, 2026. The contract period is 180 calendar days to Substantial Completion, 210 calendar days to Final Completion, and 21 calendar days Contingency Time Allowance. The bid was approximately 44.43% below the Engineer of Record's Opinion of Probable Cost of $5,571,630.00. No public comment or stakeholder sentiment is stated in the document.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Adopted
Address:
1225 Venetian Causeway, Miami Beach, Florida 33139
Applicant:
Miami-Dade Water and Sewer Department (WASD); Contractor: ITG Communications LLC

AWARD TO ITG COMMUNICATIONS FOR S-20298

Miami-Dade County Board of County Commissioners awarded Contract No. S-20298 for Venetian Causeway Water Main and Sewer Force Main Relocation to ITG Communications LLC. The project involves relocating existing water and sewer facilities at Venetian Causeway Bridge No. 2, between Biscayne Island and San Marco Island, to accommodate bridge replacement. The work includes approximately 1,500 linear feet of HDPE water main and 2,100 linear feet of HDPE force main to be installed via horizontal direction drill. The contract amount is $3,096,425.02 with a period of 231 calendar days. The project is funded by WASD Revenue Bonds Sold, Future WASD Revenue Bonds, and Wastewater Renewal and Replacement Fund. No public comment was recorded in this document.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Awarded
Address:
1225 Venetian Causeway, Miami Beach, Florida 33139
Applicant:
ITG Communications LLC

AWARD TO ITG COMMUNICATIONS FOR S-20298

Resolution awarding Contract No. S-20298, Venetian Causeway Water Main and Sewer Force Main Relocation, to ITG Communications LLC for $3,096,425.02 with a 231 calendar day contract period. The project is located at 1225 Venetian Causeway, Miami Beach, Florida 33139, in Commission District 3. The work involves relocating a 6-inch sewer force main and a 30-inch subaqueous water main to accommodate the replacement of Bridge No. 2 between Biscayne Island and San Marco Island. The project includes approximately 1,500 linear feet of HDPE water main and approximately 2,100 linear feet of HDPE force main installed via horizontal direction drill. The resolution was adopted by the Board of County Commissioners on July 21, 2026. The contract was awarded to the lowest responsive and responsible bidder, with a bid approximately 44.43% below the Engineer of Record's Opinion of Probable Cost. No public comment or stakeholder sentiment is stated in the document.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Adopted
Address:
1225 Venetian Causeway, Miami Beach, Florida 33139
Applicant:
Miami-Dade Water and Sewer Department (WASD); Contractor: ITG Communications LLC

AWARD TO ITG COMMUNICATIONS FOR S-20298

Miami-Dade County Board of County Commissioners adopted Resolution R-648-26 (File Number 261270) on July 21, 2026, awarding Contract No. S-20298, Venetian Causeway Water Main and Sewer Force Main Relocation, to ITG Communications LLC for $3,096,425.02 with a contract period of 231 calendar days. The project is located at 1225 Venetian Causeway, Miami Beach, Florida 33139, in Commission District 3. The work involves relocating a 6-inch sewer force main and a 30-inch subaqueous water main to accommodate the replacement of Bridge No. 2 between Biscayne Island and San Marco Island. The project includes approximately 1,500 linear feet of HDPE water main and approximately 2,100 linear feet of HDPE force main installed via horizontal direction drill. The contract was recommended by the Infrastructure, Innovation & Technology Committee on July 15, 2026, and forwarded to the Board on July 20, 2026. ITG's bid was approximately 44.43% below the Engineer of Record's Opinion of Probable Cost of $5,571,630.00. The project must be completed before March 2027 to avoid impacts to the bridge replacement schedule. No public comment or stakeholder sentiment is stated in the document.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Adopted on July 21, 2026
Address:
1225 Venetian Causeway, Miami Beach, Florida 33139
Applicant:
Miami-Dade Water and Sewer Department (WASD); Contractor: ITG Communications LLC

AWARD TO ITG COMMUNICATIONS FOR S-20298

Miami-Dade County Board of County Commissioners adopted Resolution R-648-26 (File Number 261270) on July 21, 2026, awarding Contract No. S-20298, Venetian Causeway Water Main and Sewer Force Main Relocation, to ITG Communications LLC for $3,096,425.02 with a 231-calendar-day contract period. The project is located at 1225 Venetian Causeway, Miami Beach, Florida 33139, in Commission District 3. The work involves relocating a 6-inch sewer force main and a 30-inch subaqueous water main at Bridge No. 2 between Biscayne Island and San Marco Island to accommodate a bridge replacement. The project includes approximately 1,500 linear feet of HDPE water main and approximately 2,100 linear feet of HDPE force main installed via horizontal direction drill. The contract period is 231 calendar days: 180 days to Substantial Completion, 210 days to Final Completion, and 21 days Contingency Time Allowance. The work must be completed before March 2027. ITG's bid was approximately 44.43% below the Engineer of Record's Opinion of Probable Cost of $5,571,630.00. The fiscal impact is $3,096,425.02, inclusive of the Inspector General Fee. The project is funded by WASD Revenue Bonds Sold, Future WASD Revenue Bonds, and Wastewater Renewal and Replacement Fund. Annual operations cost impact is $50,000.00 and annual maintenance cost impact is $50,000.00, both funded by WASD Operating Revenues. The project life expectancy is 50 years. The contract manager is Paul Adams at 786-863-9425. The project manager is David Vazquez at 786-552-4447. The Infrastructure, Innovation & Technology Committee forwarded the item to the BCC with a favorable recommendation on July 15, 2026. The Board adopted the resolution on July 21, 2026. No public comment or stakeholder sentiment is stated in the document.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Adopted
Address:
1225 Venetian Causeway, Miami Beach, Florida 33139
Applicant:
Miami-Dade Water and Sewer Department (WASD); Contractor: ITG Communications LLC

AWARD TO ITG COMMUNICATIONS FOR S-20298

Miami-Dade County legislative item File Number 261270 is a Resolution to award Contract No. S-20298, Venetian Causeway Water Main and Sewer Force Main Relocation, to ITG Communications LLC for $3,096,425.02 with a 231-calendar-day contract period. The project is located at 1225 Venetian Causeway, Miami Beach, Florida 33139, in Commission District 3. The work involves relocating a 6-inch sewer force main and a 30-inch subaqueous water main to accommodate the replacement of Bridge No. 2 between Biscayne Island and San Marco Island. The project includes approximately 1,500 linear feet of HDPE water main and approximately 2,100 linear feet of HDPE force main installed via horizontal direction drill. The Infrastructure, Innovation & Technology Committee forwarded the item to the Board of County Commissioners with a favorable recommendation on 7/15/2026, and the item was placed on the 7/21/2026 Board agenda. The document does not state a final decision by the Board. The contract period is 231 calendar days: 180 days to Substantial Completion, 210 days to Final Completion, and 21 days Contingency Time Allowance. The work must be completed before March 2027. The funding sources are WASD Revenue Bonds Sold, Future WASD Revenue Bonds, and Wastewater Renewal and Replacement Fund. The annual operations and maintenance cost impact is $50,000.00 each, funded by WASD Operating Revenues. The project life expectancy is 50 years. The contract manager is Paul Adams (786-863-9425), and the project manager is David Vazquez (786-552-4447). No public comment or stakeholder sentiment is stated in the document.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Forwarded to BCC with a favorable recommendation by the Infrastructure, Innovation & Technology Committee on 7/15/2026; placed on the 7/21/2026 Board agenda; final Board decision not stated
Address:
1225 Venetian Causeway, Miami Beach, Florida 33139
Applicant:
Miami-Dade Water and Sewer Department (WASD); contractor ITG Communications LLC

AWARD TO ITG COMMUNICATIONS FOR S-20298

Miami-Dade County Board of County Commissioners awarded Contract No. S-20298 for Venetian Causeway Water Main and Sewer Force Main Relocation to ITG Communications LLC. The project involves relocating existing water and sewer facilities to accommodate the replacement of Bridge No. 2 on the Venetian Causeway. The contract amount is $3,096,425.02, with a contract period of 231 calendar days. The work includes approximately 1,500 linear feet of HDPE water main and 2,100 linear feet of HDPE force main to be installed via horizontal direction drill under Biscayne Bay. The project is necessary to avoid impacts to the bridge replacement schedule, which must be completed before March 2027. ITG Communications LLC was the lowest responsive and responsible bidder. No public comment or stakeholder sentiment was stated in the document.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Awarded
Address:
1225 Venetian Causeway, Miami Beach, Florida 33139
Applicant:
ITG Communications LLC

AWARD TO ITG COMMUNICATIONS FOR S-20298

Resolution awarding Contract No. S-20298, Venetian Causeway Water Main and Sewer Force Main Relocation, to ITG Communications LLC in the amount of $3,096,425.02 with a contract period of 231 calendar days. The project involves relocating water and sewer facilities to accommodate the replacement of Bridge No. 2 on the Venetian Causeway. The work includes approximately 1,500 linear feet of HDPE water main and approximately 2,100 linear feet of HDPE force main installed via horizontal direction drill. The contract was adopted by the Board of County Commissioners on July 21, 2026. The project is located at 1225 Venetian Causeway, Miami Beach, Florida 33139. ITG's bid was approximately 44.43% below the Engineer of Record's Opinion of Probable Cost of $5,571,630.00. The contract is managed under the Miami-Dade Water and Sewer Department's Consent Decree and Capital Improvement Programs Acceleration Ordinance. No public comment or stakeholder sentiment is stated in the document.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Adopted
Address:
1225 Venetian Causeway, Miami Beach, Florida 33139
Applicant:
ITG Communications LLC

AWARD TO ITG COMMUNICATIONS FOR S-20298

Miami-Dade County Board of County Commissioners awarded Contract No. S-20298 for Venetian Causeway Water Main and Sewer Force Main Relocation to ITG Communications LLC. The project involves relocating existing water and sewer facilities at Bridge No. 2 between Biscayne Island and San Marco Island to accommodate bridge replacement. The work includes approximately 1,500 linear feet of HDPE water main and 2,100 linear feet of HDPE force main via horizontal direction drill. The contract amount is $3,096,425.02 with a period of 231 calendar days. The project is funded by WASD Revenue Bonds Sold, Future WASD Revenue Bonds, and Wastewater Renewal and Replacement Fund. No public comment was recorded in this document.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Awarded
Address:
1225 Venetian Causeway, Miami Beach, Florida 33139
Applicant:
ITG Communications LLC

AWARD TO ITG COMMUNICATIONS FOR S-20298

Miami-Dade County Board of County Commissioners awarded Contract No. S-20298 for Venetian Causeway Water Main and Sewer Force Main Relocation to ITG Communications LLC. The project involves relocating existing water and sewer facilities to accommodate bridge replacement at Bridge No. 2 between Biscayne Island and San Marco Island. The work includes approximately 1,500 linear feet of HDPE water main and 2,100 linear feet of HDPE force main via horizontal direction drill. The contract amount is $3,096,425.02 with a period of 231 calendar days. The project is funded by WASD Revenue Bonds Sold, Future WASD Revenue Bonds, and Wastewater Renewal and Replacement Fund. No public comment was noted in the document.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Awarded
Address:
1225 Venetian Causeway, Miami Beach, Florida 33139
Applicant:
ITG Communications LLC

AWARD TO ITG COMMUNICATIONS FOR S-20298

Miami-Dade County Board of County Commissioners adopted Resolution R-648-26 (File Number 261270) on July 21, 2026, awarding Contract No. S-20298, Venetian Causeway Water Main and Sewer Force Main Relocation, to ITG Communications LLC for $3,096,425.02 with a contract period of 231 calendar days. The project is located at 1225 Venetian Causeway, Miami Beach, Florida 33139, in Commission District 3. The work involves relocating a 6-inch sewer force main and a 30-inch subaqueous water main at Bridge No. 2 between Biscayne Island and San Marco Island to accommodate a bridge replacement. The project includes approximately 1,500 linear feet of HDPE water main and approximately 2,100 linear feet of HDPE force main installed via horizontal direction drill. The contract was recommended by the Infrastructure, Innovation & Technology Committee on July 15, 2026, and forwarded to the Board on July 20, 2026. ITG's bid was approximately 44.43% below the Engineer of Record's Opinion of Probable Cost of $5,571,630.00. No public comment or stakeholder sentiment is stated in the document.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Adopted
Address:
1225 Venetian Causeway, Miami Beach, Florida 33139
Applicant:
Miami-Dade Water and Sewer Department (WASD); Contractor: ITG Communications LLC

AWARD TO ITG COMMUNICATIONS FOR S-20298

Miami-Dade County Board of County Commissioners adopted Resolution R-648-26 (File Number 261270) on July 21, 2026, awarding Contract No. S-20298, Venetian Causeway Water Main and Sewer Force Main Relocation, to ITG Communications LLC for $3,096,425.02 with a 231-calendar-day contract period. The project is located at 1225 Venetian Causeway, Miami Beach, Florida 33139, in Commission District 3. The work involves relocating a 6-inch sewer force main and a 30-inch subaqueous water main at Bridge No. 2 between Biscayne Island and San Marco Island to accommodate a bridge replacement. The project includes approximately 1,500 linear feet of HDPE water main and approximately 2,100 linear feet of HDPE force main installed via horizontal direction drill. The contract period includes 180 calendar days to Substantial Completion, 210 calendar days to Final Completion, and 21 calendar days Contingency Time Allowance. The bid was approximately 44.43% below the Engineer of Record's Opinion of Probable Cost of $5,571,630.00. The project must be completed before March 2027. No public comment or stakeholder sentiment is stated in the document.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Adopted
Address:
1225 Venetian Causeway, Miami Beach, Florida 33139
Applicant:
Miami-Dade Water and Sewer Department (WASD); Contractor: ITG Communications LLC

AWARD TO ITG COMMUNICATIONS FOR S-20298

Miami-Dade County Board of County Commissioners adopted Resolution R-648-26 (File Number 261270) on July 21, 2026, awarding Contract No. S-20298, Venetian Causeway Water Main and Sewer Force Main Relocation, to ITG Communications LLC for $3,096,425.02 with a contract period of 231 calendar days. The project is located at 1225 Venetian Causeway, Miami Beach, Florida 33139, in Commission District 3. The work involves relocating a 6-inch sewer force main and a 30-inch subaqueous water main at Bridge No. 2 between Biscayne Island and San Marco Island to accommodate a bridge replacement. The project includes approximately 1,500 linear feet of HDPE water main and approximately 2,100 linear feet of HDPE force main installed via horizontal direction drill. The contract was recommended by the Infrastructure, Innovation & Technology Committee on July 15, 2026, and forwarded to the Board on July 20, 2026. The bid was approximately 44.43% below the Engineer of Record's Opinion of Probable Cost of $5,571,630.00. No public comment or stakeholder sentiment is stated in the document.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Adopted
Address:
1225 Venetian Causeway, Miami Beach, Florida 33139
Applicant:
ITG Communications LLC

AWARD TO ITG COMMUNICATIONS FOR S-20298

Miami-Dade County Board of County Commissioners adopted Resolution R-648-26 (File Number 261270) on July 21, 2026, awarding Contract No. S-20298, Venetian Causeway Water Main and Sewer Force Main Relocation, to ITG Communications LLC for $3,096,425.02 with a contract period of 231 calendar days. The project is located at 1225 Venetian Causeway, Miami Beach, Florida 33139, in Commission District 3. The work involves relocating a 6-inch sewer force main and a 30-inch subaqueous water main to accommodate the replacement of Bridge No. 2 between Biscayne Island and San Marco Island. The water portion includes approximately 1,500 linear feet of HDPE water main via one horizontal direction drill (HDD) installation, and the sewer portion includes approximately 2,100 linear feet of HDPE force main via two HDD applications. The contract period includes 180 calendar days to Substantial Completion, 210 calendar days to Final Completion, and 21 calendar days Contingency Time Allowance. The project must be completed before March 2027. ITG's total bid was approximately 44.43% below the Engineer of Record's Opinion of Probable Cost of $5,571,630.00. Nine bids were received and opened on June 25, 2026. The fiscal impact is $3,096,425.02, inclusive of the Inspector General Fee. Annual operations cost impact is $50,000.00 and annual maintenance cost impact is $50,000.00. The project has a life expectancy of 50 years. The County Mayor or designee is authorized to manage the contract under the Consent Decree and Capital Improvement Programs Acceleration Ordinance, Section 2-8.2.12, and may execute change orders not exceeding ten percent of the base contract amount. There were no protests to the award. The contract manager is Paul Adams at 786-863-9425. The project manager is David Vazquez at 786-552-4447.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Adopted
Address:
1225 Venetian Causeway, Miami Beach, Florida 33139
Applicant:
ITG Communications LLC

AWARD TO ITG COMMUNICATIONS FOR S-20298

Miami-Dade County Board of County Commissioners adopted Resolution R-648-26 (File Number 261270) awarding Contract No. S-20298, Venetian Causeway Water Main and Sewer Force Main Relocation, to ITG Communications LLC for $3,096,425.02 with a 231-calendar-day contract period. The project is at 1225 Venetian Causeway, Miami Beach, Florida 33139, in Commission District 3. The work involves relocating a 6-inch sewer force main and a 30-inch subaqueous water main at Bridge No. 2 between Biscayne Island and San Marco Island to accommodate a bridge replacement. The project includes approximately 1,500 linear feet of HDPE water main and approximately 2,100 linear feet of HDPE force main installed via horizontal direction drill. The contract was adopted on July 21, 2026, after being forwarded with a favorable recommendation from the Infrastructure, Innovation & Technology Committee on July 15, 2026. ITG's total bid was approximately 44.43% below the Engineer of Record's Opinion of Probable Cost of $5,571,630.00. No public comment or stakeholder sentiment is stated in the document.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Adopted
Address:
1225 Venetian Causeway, Miami Beach, Florida 33139
Applicant:
ITG Communications LLC

AWARD TO ITG COMMUNICATIONS FOR S-20298

Miami-Dade County Board of County Commissioners adopted Resolution R-648-26 (File Number 261270) awarding Contract No. S-20298, Venetian Causeway Water Main and Sewer Force Main Relocation, to ITG Communications LLC for $3,096,425.02 with a 231-calendar-day contract period. The project is at 1225 Venetian Causeway, Miami Beach, Florida 33139, Commission District 3. The work involves relocating a 6-inch sewer force main and a 30-inch subaqueous water main at Bridge No. 2 between Biscayne Island and San Marco Island to accommodate a bridge replacement. The project includes approximately 1,500 linear feet of HDPE water main and approximately 2,100 linear feet of HDPE force main installed via horizontal direction drill. The contract was competitively bid with nine bids received; ITG was the lowest responsive and responsible bidder, with a bid approximately 44.43% below the Engineer of Record's Opinion of Probable Cost. The final action was adoption on July 21, 2026. The Infrastructure, Innovation & Technology Committee forwarded it with a favorable recommendation on July 15, 2026. The contract is managed under WASD's Acceleration Ordinance, allowing change orders up to 10% of the base contract amount. No public comment or stakeholder sentiment is stated in the document.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Adopted
Address:
1225 Venetian Causeway, Miami Beach, Florida 33139
Applicant:
Miami-Dade Water and Sewer Department (WASD); contractor ITG Communications LLC

AWARD TO ITG COMMUNICATIONS FOR S-20298

Miami-Dade County Board of County Commissioners adopted Resolution R-648-26 (File Number 261270) on July 21, 2026, awarding Contract No. S-20298, Venetian Causeway Water Main and Sewer Force Main Relocation, to ITG Communications LLC for $3,096,425.02 with a contract period of 231 calendar days. The project is located at 1225 Venetian Causeway, Miami Beach, Florida 33139, in Commission District 3. The work involves relocating a 6-inch sewer force main and a 30-inch subaqueous water main to accommodate the replacement of Bridge No. 2 between Biscayne Island and San Marco Island. The water portion includes approximately 1,500 linear feet of HDPE water main via one horizontal direction drill (HDD) installation, and the sewer portion includes approximately 2,100 linear feet of HDPE force main via two HDD applications. The project must be completed before March 2027. The contract period includes 180 calendar days to Substantial Completion, 210 calendar days to Final Completion, and 21 calendar days Contingency Time Allowance. ITG's total bid was approximately 44.43% below the Engineer of Record's Opinion of Probable Cost of $5,571,630.00. The fiscal impact is $3,096,425.02, inclusive of the Inspector General Fee. The project is in WASD's FY 2025-2026 Adopted Budget and Multi-Year Capital Plan under Program #9654041 and Program #9653281. The life expectancy of the project is 50 years. Annual operations cost impact is $50,000.00 and annual maintenance cost impact is $50,000.00. The County Mayor or designee is authorized to manage the contract under the Consent Decree and Capital Improvement Programs Acceleration Ordinance, Section 2-8.2.12, and to execute the contract and exercise termination provisions. The contract was competitively solicited with bids opened on June 25, 2026, in response to a May 14, 2026 advertisement. Nine bids were received. ITG was determined to be the lowest responsive and responsible bidder. No protests were filed. The contract monitor is Marisela Aranguiz-Cueto, P.E., Deputy Director of Planning, Development, Regulatory, and Infrastructure. The contract manager is Paul Adams at 786-863-9425. The project manager is David Vazquez at 786-552-4447. The project was forwarded to the Board with a favorable recommendation by the Infrastructure, Innovation & Technology Committee on July 15, 2026, and again on July 20, 2026. The item was introduced on July 9, 2026. The document does not state any public comment or stakeholder sentiment.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Adopted
Address:
1225 Venetian Causeway, Miami Beach, Florida 33139
Applicant:
ITG Communications LLC

AWARD TO ITG COMMUNICATIONS FOR S-20298

The Miami-Dade Board of County Commissioners adopted Resolution R-648-26, awarding Contract No. S-20298 for the Venetian Causeway Water Main and Sewer Force Main Relocation to ITG Communications LLC in the amount of $3,096,425.02, with a contract period of 231 calendar days. The project is located at 1225 Venetian Causeway, Miami Beach, Florida 33139, in Commission District 3. The work involves relocating a 6-inch sewer force main and a 30-inch subaqueous water main to accommodate the replacement of Bridge No. 2 between Biscayne Island and San Marco Island. The project includes approximately 1,500 linear feet of HDPE water main and approximately 2,100 linear feet of HDPE force main installed via horizontal direction drill. The contract was awarded to the lowest responsive and responsible bidder, with a bid approximately 44.43% below the Engineer of Record's Opinion of Probable Cost. The resolution also authorizes the County Mayor or designee to manage the contract under the WASD Acceleration Ordinance and to execute the contract. The final action was taken on July 21, 2026. No public comment or stakeholder sentiment is stated in the document.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Adopted
Address:
1225 Venetian Causeway, Miami Beach, Florida 33139
Applicant:
Miami-Dade Water and Sewer Department (WASD); Contractor: ITG Communications LLC

AWARD TO ITG COMMUNICATIONS FOR S-20298

Miami-Dade County Board of County Commissioners approved Resolution File Number 261270, awarding Contract No. S-20298 for Venetian Causeway Water Main and Sewer Force Main Relocation to ITG Communications LLC. The contract amount is $3,096,425.02, with a period of 231 calendar days. This project involves relocating existing water and sewer facilities to accommodate the replacement of Bridge No. 2 on the Venetian Causeway, which spans Biscayne Bay connecting Miami to Miami Beach. The work includes approximately 1,500 linear feet of HDPE water main and 2,100 linear feet of HDPE force main to be installed via horizontal direction drill. The project is funded through WASD Revenue Bonds, Future WASD Revenue Bonds, and Wastewater Renewal and Replacement Fund. ITG Communications LLC was the lowest responsive and responsible bidder, with no prior county contracts. No public comment or stakeholder sentiment was noted in the document.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Approved
Address:
1225 Venetian Causeway, Miami Beach, Florida 33139
Applicant:
ITG Communications LLC

AWARD TO ITG COMMUNICATIONS FOR S-20298

Miami-Dade County Board of County Commissioners adopted Resolution R-648-26 (File Number 261270) on July 21, 2026, awarding Contract No. S-20298, Venetian Causeway Water Main and Sewer Force Main Relocation, to ITG Communications LLC for $3,096,425.02 with a contract period of 231 calendar days. The project is located at 1225 Venetian Causeway, Miami Beach, Florida 33139, in Commission District 3. The work involves relocating a 6-inch sewer force main and a 30-inch subaqueous water main at Bridge No. 2 between Biscayne Island and San Marco Island to accommodate a bridge replacement. The project includes approximately 1,500 linear feet of HDPE water main and approximately 2,100 linear feet of HDPE force main installed via horizontal direction drill. The contract was awarded to the lowest responsive and responsible bidder, with a bid approximately 44.43% below the Engineer of Record's Opinion of Probable Cost of $5,571,630.00. The project must be completed before March 2027 to avoid impacts to the bridge replacement schedule. The contract will be managed under the WASD Acceleration Ordinance, Section 2-8.2.12. No public comment or stakeholder sentiment is stated in the document.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Adopted
Address:
1225 Venetian Causeway, Miami Beach, Florida 33139
Applicant:
ITG Communications LLC

AWARD TO ITG COMMUNICATIONS FOR S-20298

Miami-Dade County Board of County Commissioners adopted Resolution R-648-26 (File Number 261270) on July 21, 2026, awarding Contract No. S-20298, Venetian Causeway Water Main and Sewer Force Main Relocation, to ITG Communications LLC for $3,096,425.02 with a contract period of 231 calendar days. The project is located at 1225 Venetian Causeway, Miami Beach, Florida 33139, in Commission District 3. The work involves relocating a 6-inch sewer force main and a 30-inch subaqueous water main to accommodate the replacement of Bridge No. 2 between Biscayne Island and San Marco Island. The project includes approximately 1,500 linear feet of HDPE water main and approximately 2,100 linear feet of HDPE force main installed via horizontal direction drill. The contract period includes 180 calendar days to Substantial Completion, 210 calendar days to Final Completion, and 21 calendar days Contingency Time Allowance. The work must be completed before March 2027. The bid was approximately 44.43% below the Engineer of Record's Opinion of Probable Cost of $5,571,630.00. The contract is managed under the WASD Consent Decree and Capital Improvement Programs Acceleration Ordinance, Section 2-8.2.12. The project is funded by WASD Revenue Bonds Sold, Future WASD Revenue Bonds, and Wastewater Renewal and Replacement Fund. Annual operations cost impact is $50,000.00 and annual maintenance cost impact is $50,000.00, both funded by WASD Operating Revenues. The project life expectancy is 50 years. No public comment or stakeholder sentiment is stated in the document.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Adopted
Address:
1225 Venetian Causeway, Miami Beach, Florida 33139
Applicant:
Miami-Dade Water and Sewer Department (WASD); contractor ITG Communications LLC

AWARD TO ITG COMMUNICATIONS FOR S-20298

Resolution awarding Contract No. S-20298, Venetian Causeway Water Main and Sewer Force Main Relocation, to ITG Communications LLC for $3,096,425.02 with a 231 calendar day contract period. The project is located at 1225 Venetian Causeway, Miami Beach, Florida 33139, in Commission District 3. The work involves relocating a 6-inch sewer force main and a 30-inch subaqueous water main to accommodate Bridge No. 2 replacement between Biscayne Island and San Marco Island. The project includes approximately 1,500 linear feet of HDPE water main and approximately 2,100 linear feet of HDPE force main installed via horizontal direction drill. The resolution was adopted by the Board of County Commissioners on July 21, 2026. The contract must be completed before March 2027 to avoid impacts to the bridge replacement schedule. ITG's bid was approximately 44.43% below the Engineer of Record's Opinion of Probable Cost of $5,571,630.00. The contract is managed under the WASD Acceleration Ordinance, Section 2-8.2.12. The contract monitor is Marisela Aranguiz-Cueto, P.E., and the project manager is David Vazquez, P.E. The contract manager is Paul Adams. The fiscal impact is $3,096,425.02, inclusive of the Inspector General Fee. Annual operations cost impact is $50,000.00 and annual maintenance cost impact is $50,000.00. The project life expectancy is 50 years. The funding sources are WASD Revenue Bonds Sold, Future WASD Revenue Bonds, and Wastewater Renewal and Replacement Fund. The project does not include Art in Public Places. There are no protests to this award. The project supports the replacement and restoration of the historic Venetian Causeway. The existing bridge structures exhibit significant deterioration and no longer meet current structural and safety requirements. The Venetian Causeway is listed on the National Register of Historic Places and is designated as a historic resource by both the City of Miami and the City of Miami Beach. The project requires accommodation for major regional events, such as Art Week. ITG has not been awarded any contracts from the County previously. ITG was deemed qualified and eligible for the work on May 15, 2026. The bid opening was June 25, 2026. The advertisement for the solicitation was May 14, 2026. Nine bids were received. The project is in WASD's FY 2025-2026 Adopted Budget and Multi-Year Capital Plan under Program #9654041, Central Region Water Transmission Mains - Infrastructure Improvements, Volume #3, Page #103, and Program #9653281, Sanitary Sewer System Extension, Volume #3, Page #110. The funding sources do not include Building Better Communities - General Obligation Bond funds or impact the General Fund. The project was introduced on July 9, 2026. The Infrastructure, Innovation & Technology Committee forwarded it to the BCC with a favorable recommendation on July 15, 2026. The Office of the Chairperson added it on July 20, 2026. The Board of County Commissioners adopted it on July 21, 2026. The project was a late item. The requester is the Water & Sewer Department. The County Attorney assigned to the item is Sarah E. Davis. The resolution is R-648-26. The agenda item number was 8O5. The contract period includes 180 calendar days to Substantial Completion, 210 calendar days to Final Completion, and 21 calendar days Contingency Time Allowance. The project consists of performing two pipeline installations via horizontal direction drill for water and sewer infrastructure to cross the Biscayne Bay waterway under Venetian Causeway Bridge No. 2 between Biscayne Island and San Marco Island. Open-cut connections shall be constructed to place the new mains in service. The project supports the priority of Miami-Dade County to replace and restore the historic Venetian Causeway. The project will enhance transportation safety and mobility along this critical regional corridor. WASD will be able to continue providing uninterrupted and reliable service to residents, businesses, and visitors in the City of Miami and the City of Miami Beach. The project does not include Art in Public Places. The applicable ordinances include Local Preference Code Section 2-8.5, Sustainable Buildings Program Implementing Order 8-8, Buy American Iron & Steel Procurement Program Code Section 2-8.2.6.1, Office of Inspector General Fee Code Section 2-1076, and User Access Program Code Section 2-8.10. The Sea Level Rise Ordinance 14-79 is not applicable. The Local Certified Veteran Business Enterprise Preference Code Section 2-8.5.1 is not applicable. The due diligence performed included verifying corporate status, performance, and safety record including OSHA records. The lists reviewed included convicted vendors, debarred vendors, delinquent contractors, suspended vendors, and federal excluded parties. There were no adverse findings related to ITG's responsibility. The information is provided pursuant to Resolution No. R-187-12 and Resolution No. R-1181-18. The EOR, David Vazquez, P.E., recommended the award on June 28, 2026. The project chronology lists the pre-bid meeting date as May 27, 2026, and the bid opening date as June 25, 2026. The planned bid award date, pre-construction meeting date, notice to proceed date, groundbreaking date, and completion date are listed as TBD. The contract manager is Paul Adams, phone 786-863-9425, email [email protected]. The project manager is David Vazquez, phone 786-552-4447, email [email protected]. The WASD Deputy Director of Planning, Development, Regulatory, and Infrastructure, Marisela Aranguiz-Cueto, P.E., will oversee the implementation of the Contract. The County Mayor or County Mayor's designee is authorized to execute the Contract and exercise the termination and other provisions. The County Mayor or County Mayor's designee may negotiate and settle claims and execute change orders that do not exceed ten percent (10%) of the base contract amount, subject to ratification by the Board. The total bid amount includes the contingency and dedicated allowances. The other bidders were Metro Equipment Service, Inc. with a total bid of $4,382,237.35, R.P. Utility & Excavation Corp with a total bid of $4,914,642.50, JVA Engineering Contractor Inc with a total bid of $5,029,959.00, Amici Engineering Contractors LLC with a total bid of $5,091,498.80, Lanzo Construction Co., Florida with a total bid of $5,678,805.00, Quality Enterprises, Inc. with a total bid of $6,276,072.15, David Mancini & Sons, Inc. with a total bid of $6,513,443.34, and Ric Man International, Inc. with a total bid of $6,890,175.95. The document does not state any public comment or stakeholder sentiment.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Adopted
Address:
1225 Venetian Causeway, Miami Beach, Florida 33139
Applicant:
ITG Communications LLC

AWARD TO ITG COMMUNICATIONS FOR S-20298

Miami-Dade County Board of County Commissioners adopted Resolution R-648-26 (Legislative Item File Number 261270) awarding Contract No. S-20298, Venetian Causeway Water Main and Sewer Force Main Relocation, to ITG Communications LLC for $3,096,425.02 with a contract period of 231 calendar days. The project is located at 1225 Venetian Causeway, Miami Beach, Florida 33139, in Commission District 3. The work involves relocating water and sewer facilities to accommodate the replacement of Bridge No. 2 on the Venetian Causeway, between Biscayne Island and San Marco Island. The project includes approximately 1,500 linear feet of HDPE water main and approximately 2,100 linear feet of HDPE force main installed via horizontal direction drill. The contract was adopted on July 21, 2026, after being forwarded with a favorable recommendation by the Infrastructure, Innovation & Technology Committee on July 15, 2026. The bid was approximately 44.43% below the Engineer of Record's Opinion of Probable Cost of $5,571,630.00. No public comment or stakeholder sentiment is stated in the document.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Adopted
Address:
1225 Venetian Causeway, Miami Beach, Florida 33139
Applicant:
Miami-Dade Water and Sewer Department (WASD); Contractor: ITG Communications LLC

AWARD TO ITG COMMUNICATIONS FOR S-20298

Miami-Dade County Board of County Commissioners adopted Resolution R-648-26 (File Number 261270) on July 21, 2026, awarding Contract No. S-20298, Venetian Causeway Water Main and Sewer Force Main Relocation, to ITG Communications LLC for $3,096,425.02 with a contract period of 231 calendar days. The project is located at 1225 Venetian Causeway, Miami Beach, Florida 33139, in Commission District 3. The work involves relocating a 6-inch sewer force main and a 30-inch subaqueous water main to accommodate the replacement of Bridge No. 2 between Biscayne Island and San Marco Island. The project includes approximately 1,500 linear feet of HDPE water main and approximately 2,100 linear feet of HDPE force main installed via horizontal direction drill. The contract period includes 180 calendar days to Substantial Completion, 210 calendar days to Final Completion, and 21 calendar days Contingency Time Allowance. The relocation must be completed before March 2027. The bid was approximately 44.43% below the Engineer of Record's Opinion of Probable Cost of $5,571,630.00. The contract is managed under the Miami-Dade Water and Sewer Department's Consent Decree and Capital Improvement Programs Acceleration Ordinance, Section 2-8.2.12. The contract manager is Paul Adams (786-863-9425), and the project manager is David Vazquez (786-552-4447). No public comment or stakeholder sentiment is stated in the document.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Adopted
Address:
1225 Venetian Causeway, Miami Beach, Florida 33139
Applicant:
Miami-Dade Water and Sewer Department (WASD); Contractor: ITG Communications LLC

AWARD TO ITG COMMUNICATIONS FOR S-20298

Miami-Dade County Board of County Commissioners adopted Resolution R-648-26 (File Number 261270) on July 21, 2026, awarding Contract No. S-20298, Venetian Causeway Water Main and Sewer Force Main Relocation, to ITG Communications LLC for $3,096,425.02 with a contract period of 231 calendar days. The project is located at 1225 Venetian Causeway, Miami Beach, Florida 33139, in Commission District 3. The work involves relocating a 6-inch sewer force main and a 30-inch subaqueous water main to accommodate the replacement of Bridge No. 2 between Biscayne Island and San Marco Island. The project includes approximately 1,500 linear feet of HDPE water main and approximately 2,100 linear feet of HDPE force main installed via horizontal direction drill. The contract was recommended by the Infrastructure, Innovation & Technology Committee on July 15, 2026, and forwarded to the Board on July 20, 2026. The bid was approximately 44.43% below the Engineer of Record's Opinion of Probable Cost of $5,571,630.00. No public comment or stakeholder sentiment is stated in the document.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Adopted
Address:
1225 Venetian Causeway, Miami Beach, Florida 33139
Applicant:
ITG Communications LLC

AWARD TO ITG COMMUNICATIONS FOR S-20298

Miami-Dade County Board of County Commissioners adopted Resolution R-648-26 (File Number 261270) on July 21, 2026, awarding Contract No. S-20298, Venetian Causeway Water Main and Sewer Force Main Relocation, to ITG Communications LLC for $3,096,425.02 with a contract period of 231 calendar days. The project is located at 1225 Venetian Causeway, Miami Beach, Florida 33139, in Commission District 3. The work involves relocating a 6-inch sewer force main and a 30-inch subaqueous water main at Bridge No. 2 between Biscayne Island and San Marco Island to accommodate a bridge replacement. The project includes approximately 1,500 linear feet of HDPE water main and approximately 2,100 linear feet of HDPE force main installed via horizontal direction drill. The contract was awarded to the lowest responsive and responsible bidder, with a bid approximately 44.43% below the Engineer of Record's Opinion of Probable Cost of $5,571,630.00. The project must be completed before March 2027. No public comment or stakeholder sentiment is stated in the document.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Adopted
Address:
1225 Venetian Causeway, Miami Beach, Florida 33139
Applicant:
Miami-Dade Water and Sewer Department (WASD); contractor ITG Communications LLC

AWARD TO ITG COMMUNICATIONS FOR S-20298

Miami-Dade County Board of County Commissioners adopted Resolution R-648-26 (File Number 261270) on July 21, 2026, awarding Contract No. S-20298, Venetian Causeway Water Main and Sewer Force Main Relocation, to ITG Communications LLC for $3,096,425.02 with a 231-calendar-day contract period. The project is located at 1225 Venetian Causeway, Miami Beach, Florida 33139, in Commission District 3. The work involves relocating a 6-inch sewer force main and a 30-inch subaqueous water main to accommodate the replacement of Bridge No. 2 between Biscayne Island and San Marco Island. The project includes approximately 1,500 linear feet of HDPE water main and approximately 2,100 linear feet of HDPE force main installed via horizontal direction drill. The contract period includes 180 calendar days to Substantial Completion, 210 calendar days to Final Completion, and 21 calendar days Contingency Time Allowance. The relocation must be completed before March 2027. ITG's bid was approximately 44.43% below the Engineer of Record's Opinion of Probable Cost of $5,571,630.00. The contract will be managed under the WASD Acceleration Ordinance, Section 2-8.2.12. The fiscal impact is $3,096,425.02, inclusive of the Inspector General Fee. The project is funded by WASD Revenue Bonds Sold, Future WASD Revenue Bonds, and Wastewater Renewal and Replacement Fund. Annual operations cost impact is $50,000.00 and annual maintenance cost impact is $50,000.00, both funded by WASD Operating Revenues. The project life expectancy is 50 years. The contract manager is Paul Adams at 786-863-9425. The project manager is David Vazquez at 786-552-4447. Nine bids were received on June 25, 2026. There were no protests to this award. The Infrastructure, Innovation & Technology Committee forwarded the item to the Board with a favorable recommendation on July 15, 2026. The item was introduced on July 9, 2026, and adopted on July 21, 2026.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Adopted
Address:
1225 Venetian Causeway, Miami Beach, Florida 33139
Applicant:
ITG Communications LLC

AWARD TO ITG COMMUNICATIONS FOR S-20298

Miami-Dade County Board of County Commissioners awarded Contract No. S-20298 for Venetian Causeway Water Main and Sewer Force Main Relocation to ITG Communications LLC. The project involves relocating existing water and sewer facilities to accommodate the replacement of Bridge No. 2 on the Venetian Causeway. The contract amount is $3,096,425.02, with a contract period of 231 calendar days. The work includes approximately 1,500 linear feet of HDPE water main and 2,100 linear feet of HDPE force main to be installed via horizontal direction drill under Biscayne Bay. The project is necessary to avoid impacts to the bridge replacement schedule, which must be completed before March 2027. ITG Communications LLC was the lowest responsive and responsible bidder, with their bid being approximately 44.3% below the Engineer of Record's estimate. No public comment or stakeholder sentiment was stated in the document.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Awarded
Address:
1225 Venetian Causeway, Miami Beach, Florida 33139
Applicant:
ITG Communications LLC

AWARD TO ITG COMMUNICATIONS FOR S-20298

Miami-Dade County Board of County Commissioners awarded Contract No. S-20298 for Venetian Causeway Water Main and Sewer Force Main Relocation to ITG Communications LLC. The project involves relocating existing water and sewer facilities to accommodate the replacement of Bridge No. 2 on the Venetian Causeway. The contract amount is $3,096,425.02 with a period of 231 calendar days. The work includes approximately 1,500 linear feet of HDPE water main and 2,100 linear feet of HDPE force main to be installed via horizontal direction drill under Biscayne Bay. The project supports the restoration of the Venetian Causeway and ensures continued utility service. No public comment was noted in the document.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Awarded
Address:
1225 Venetian Causeway, Miami Beach, Florida 33139
Applicant:
ITG Communications LLC

AWARD TO ITG COMMUNICATIONS FOR S-20298

Miami-Dade County Board of County Commissioners adopted Resolution R-648-26 (File Number 261270) awarding Contract No. S-20298, Venetian Causeway Water Main and Sewer Force Main Relocation, to ITG Communications LLC for $3,096,425.02 with a contract period of 231 calendar days. The work is at 1225 Venetian Causeway, Miami Beach, Florida 33139, in Commission District 3. The project involves relocating a 6-inch sewer force main and a 30-inch subaqueous water main at Bridge No. 2 between Biscayne Island and San Marco Island to accommodate bridge replacement. The work includes approximately 1,500 linear feet of HDPE water main and approximately 2,100 linear feet of HDPE force main installed via horizontal direction drill. The contract was adopted on July 21, 2026, after being forwarded with a favorable recommendation by the Infrastructure, Innovation & Technology Committee on July 15, 2026. The bid was approximately 44.43% below the Engineer of Record's Opinion of Probable Cost of $5,571,630.00. No public comment or stakeholder sentiment is stated in the document.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Adopted
Address:
1225 Venetian Causeway, Miami Beach, Florida 33139
Applicant:
Miami-Dade Water and Sewer Department (WASD); contractor ITG Communications LLC

AWARD TO ITG COMMUNICATIONS FOR S-20298

Miami-Dade County Board of County Commissioners adopted Resolution R-648-26 (File Number 261270) on July 21, 2026, awarding Contract No. S-20298 for the Venetian Causeway Water Main and Sewer Force Main Relocation to ITG Communications LLC in the amount of $3,096,425.02 with a contract period of 231 calendar days. The project is located at 1225 Venetian Causeway, Miami Beach, Florida 33139, in Commission District 3. The work involves relocating a 6-inch sewer force main and a 30-inch subaqueous water main to accommodate the replacement of Bridge No. 2 between Biscayne Island and San Marco Island. The project includes approximately 1,500 linear feet of HDPE water main and approximately 2,100 linear feet of HDPE force main installed via horizontal direction drill. The contract was recommended by the Infrastructure, Innovation & Technology Committee on July 15, 2026, and forwarded to the BCC on July 20, 2026. ITG's total bid was approximately 44.43% below the Engineer of Record's Opinion of Probable Cost of $5,571,630.00. The project must be completed before March 2027. The contract manager is Paul Adams (786-863-9425) and the project manager is David Vazquez (786-552-4447).

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Adopted
Address:
1225 Venetian Causeway, Miami Beach, Florida 33139
Applicant:
Miami-Dade Water and Sewer Department (WASD); Contractor: ITG Communications LLC

AWARD TO ITG COMMUNICATIONS FOR S-20298

Miami-Dade County Board of County Commissioners approved the award of Contract No. S-20298 for the Venetian Causeway Water Main and Sewer Force Main Relocation to ITG Communications LLC. The project involves relocating existing water and sewer facilities to accommodate the replacement of Bridge No. 2 on the Venetian Causeway. The contract amount is $3,096,425.02 with a period of 231 calendar days. The work includes approximately 1,500 linear feet of HDPE water main and 2,100 linear feet of HDPE force main to be installed via horizontal direction drill under Biscayne Bay. This project is crucial to avoid impacts on the bridge replacement schedule, which must be completed before March 2027. ITG Communications LLC was the lowest responsive and responsible bidder, with their bid being approximately 44.43% below the Engineer of Record's estimate. No public comment or stakeholder sentiment was noted in the document.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Approved
Address:
1225 Venetian Causeway, Miami Beach, Florida 33139
Applicant:
ITG Communications LLC

AWARD TO ITG COMMUNICATIONS FOR S-20298

Miami-Dade County Board of County Commissioners adopted Resolution R-648-26 (File No. 261270) on July 21, 2026, awarding Contract No. S-20298, Venetian Causeway Water Main and Sewer Force Main Relocation, to ITG Communications LLC for $3,096,425.02 with a contract period of 231 calendar days. The project is located at 1225 Venetian Causeway, Miami Beach, Florida 33139, in Commission District 3. The work involves relocating a 6-inch sewer force main and a 30-inch subaqueous water main to accommodate the replacement of Bridge No. 2 between Biscayne Island and San Marco Island. The project includes approximately 1,500 linear feet of HDPE water main and approximately 2,100 linear feet of HDPE force main installed via horizontal direction drill. The contract period includes 180 calendar days to Substantial Completion, 210 calendar days to Final Completion, and 21 calendar days Contingency Time Allowance. The bid was approximately 44.43% below the Engineer of Record's Opinion of Probable Cost of $5,571,630.00. The project must be completed before March 2027 to avoid impacts to the bridge replacement schedule. The County Mayor or designee is authorized to manage the contract under the WASD Acceleration Ordinance, Section 2-8.2.12, including executing change orders not exceeding 10% of the base contract amount. The fiscal impact is $3,096,425.02, inclusive of the Inspector General Fee. Annual operations and maintenance cost impact is $50,000.00 each, funded by WASD Operating Revenues. The project life expectancy is 50 years. The contract manager is Paul Adams (786-863-9425) and the project manager is David Vazquez (786-552-4447). No public comment or stakeholder sentiment is stated in the document.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Adopted on July 21, 2026
Address:
1225 Venetian Causeway, Miami Beach, Florida 33139
Applicant:
ITG Communications LLC

AWARD TO ITG COMMUNICATIONS FOR S-20298

Miami-Dade County Board of County Commissioners adopted Resolution R-648-26 (File Number 261270) on July 21, 2026, awarding Contract No. S-20298, Venetian Causeway Water Main and Sewer Force Main Relocation, to ITG Communications LLC for $3,096,425.02 with a contract period of 231 calendar days. The project is located at 1225 Venetian Causeway, Miami Beach, Florida 33139, in Commission District 3. The work involves relocating a 6-inch sewer force main and a 30-inch subaqueous water main at Bridge No. 2 between Biscayne Island and San Marco Island to accommodate a bridge replacement. The project includes approximately 1,500 linear feet of HDPE water main and approximately 2,100 linear feet of HDPE force main installed via horizontal direction drill. The contract was awarded to the lowest responsive and responsible bidder, with ITG's bid approximately 44.43% below the Engineer of Record's Opinion of Probable Cost of $5,571,630.00. The project must be completed before March 2027 to avoid impacts to the bridge replacement schedule. No public comment or stakeholder sentiment is stated in the document.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Adopted
Address:
1225 Venetian Causeway, Miami Beach, Florida 33139
Applicant:
Miami-Dade Water and Sewer Department (WASD); contractor ITG Communications LLC

BBEETF DISBURSEMENT OF $650K FOR MOORING BUOY PROGRAM

Miami-Dade County Board of County Commissioners adopted Resolution R-658-26 (Legislative Item File Number 260942) authorizing the disbursement of up to $650,000.00 from the Biscayne Bay Environmental Enhancement Trust Fund for the installation, maintenance, and management of mooring buoys through the Miami-Dade County Mooring Buoy Program. The program protects offshore natural and artificial reefs, with buoys located offshore of Commission Districts 4, 5, and 7. The program was established in 2009 and expanded in 2023, with 54 mooring buoys placed at 14 snorkeling/diving sites from Golden Beach south to the northern border of Biscayne National Park. The funds will be used for quarterly maintenance by a contractor, interim inspections by DERM staff, and education/outreach. A previous disbursement of $350,000.00 was authorized in 2018 under Resolution R-1172-18 and has been fully utilized. The unencumbered balance of the trust fund as of December 31, 2025, is $9,908,471.94. The item was introduced on 5/20/2026, forwarded to the Board with a favorable recommendation by the Recreation, Tourism, and Resiliency Committee on 6/9/2026, and adopted on 7/21/2026. The prime sponsor is Commissioner Vicki L. Lopez. The requester is the Department of Environmental Resources Management. The manager of the Restoration & Enhancement Section within DERM, Laura Eldredge, will monitor activities. No public comment or stakeholder sentiment is stated in the document.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Adopted
Applicant:
Department of Environmental Resources Management (DERM); Prime Sponsor Commissioner Vicki L. Lopez

BBEETF DISBURSEMENT OF $650K FOR MOORING BUOY PROGRAM

The document is a resolution authorizing the disbursement of up to $650,000.00 from the Biscayne Bay Environmental Enhancement Trust Fund for the installation, maintenance, and management of mooring buoys through the Miami-Dade County Mooring Buoy Program. The buoys are located in the coastal waters of Miami-Dade County, offshore of Commission Districts 4, 5, and 7. The program has 54 mooring buoys at 14 sites from Golden Beach south to the northern border of Biscayne National Park. The resolution was adopted by the Board of County Commissioners on 7/21/2026. The applicant/requester is the Department of Environmental Resources Management. The case/file number is 260942. The fund balance as of December 31, 2025, was $9,908,471.94. A previous disbursement of $350,000.00 was authorized in 2018 under Resolution No. R-1172-18 and has been fully utilized. The resolution was introduced on 5/20/2026 and forwarded to the Board with a favorable recommendation by the Recreation, Tourism, and Resiliency Committee on 6/9/2026. The sponsor is Vicki L. Lopez. The monitor is Laura Eldredge, Manager of the Restoration & Enhancement Section within DERM. No public comment or stakeholder sentiment is stated in the document.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Adopted
Applicant:
Department of Environmental Resources Management

BBEETF DISBURSEMENT OF $650K FOR MOORING BUOY PROGRAM

Miami-Dade County Board of County Commissioners is considering a resolution to authorize the disbursement of up to $650,000.00 from the Biscayne Bay Environmental Enhancement Trust Fund for the Miami-Dade County Mooring Buoy Program. This program involves the installation, maintenance, and management of mooring buoys in the coastal waters of Miami-Dade County, specifically offshore of Commission Districts 4, 5, and 7. The program, established in 2009 and expanded in 2023, aims to protect natural and artificial reefs from anchor damage and provide boating, fishing, and diving access. The work will be overseen by the Restoration and Enhancement Section of the Department of Environmental Resources Management (DERM). Quarterly maintenance by a contractor is required, along with interim inspections by DERM staff. Education and outreach are also part of the program. A previous disbursement of $350,000.00 was authorized in 2018 and fully utilized. The Recreation, Tourism, and Resiliency Committee forwarded this item with a favorable recommendation to the Board of County Commissioners (BCC).

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Forwarded to BCC with a favorable recommendation by the Recreation, Tourism, and Resiliency Committee; pending Board of County Commissioners approval.
Address:
Coastal waters of Miami-Dade County
Applicant:
Department of Environmental Resources Management (DERM)

BBEETF DISBURSEMENT OF $650K FOR MOORING BUOY PROGRAM

Miami-Dade County is authorizing the disbursement of up to $650,000.00 from the Biscayne Bay Environmental Enhancement Trust Fund for the installation, maintenance, and management of mooring buoys within the Miami-Dade County Mooring Buoy Program. This program, established in 2009 and expanded in 2023, aims to protect natural and artificial reefs by providing designated mooring locations and preventing anchor damage. The funds will cover quarterly contractor maintenance, including repairs, replacements, and installations of anchors, hardware, lines, and buoys, as well as DERM staff's interim inspections and public education/outreach efforts. The program's mooring buoys are located offshore in coastal waters of Miami-Dade County, specifically in areas offshore of Commission Districts 4, 5, and 7. A previous disbursement of $350,000.00 in 2018 for this program has been fully utilized. The Recreation, Tourism, and Resiliency Committee forwarded this item with a favorable recommendation to the Board of County Commissioners (BCC).

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Forwarded to BCC with a favorable recommendation by the Recreation, Tourism, and Resiliency Committee; resolution seeks authorization for disbursement.
Address:
Coastal waters of Miami-Dade County
Applicant:
Department of Environmental Resources Management (DERM)

BBEETF DISBURSEMENT OF $650K FOR MOORING BUOY PROGRAM

The Miami-Dade Board of County Commissioners adopted Resolution R-658-26 (File Number 260942) on 7/21/2026, authorizing the disbursement of up to $650,000.00 from the Biscayne Bay Environmental Enhancement Trust Fund for the installation, maintenance, and management of mooring buoys through the Miami-Dade County Mooring Buoy Program. The program covers 54 mooring buoys at 14 snorkeling/diving sites in coastal waters from Golden Beach south to the northern border of Biscayne National Park, offshore of Commission Districts 4, 5, and 7. The program was established in 2009 and expanded in 2023. The Department of Environmental Resources Management will oversee the activities. The item was introduced on 5/20/2026, forwarded with a favorable recommendation by the Recreation, Tourism, and Resiliency Committee on 6/9/2026, and adopted by the Board of County Commissioners on 7/21/2026. The unencumbered balance of the trust fund as of December 31, 2025, is $9,908,471.94. A previous disbursement of $350,000.00 was authorized in 2018 under Resolution R-1172-18 and has been fully utilized. The prime sponsor is Commissioner Vicki L. Lopez. The requester is the Department of Environmental Resources Management. No public comment or stakeholder sentiment is stated in the document.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Adopted
Applicant:
Department of Environmental Resources Management

Mira los negocios reales detrás de estos números

Obtén los registros reales, con direcciones y directivos, respaldados por una garantía de reembolso de 14 días.

Crea tu cuenta