5. Direct Labor Hourly Estimated Estimated

City Commission Meeting · 2026-06-11 · agenda_item

This item concerns a planned civic project for the City of Palatka. The project involves engineering and design services, with estimated direct labor costs totaling $96,353.50. The work includes roles such as Project Manager, Senior Engineer, Engineer, Engineering Intern, Senior Designer, and Secretary/Clerical. This agenda item is currently under review by the City Commission. The project scope will likely involve detailed design, planning, and potentially site assessment phases. Local contractors, trades, suppliers, and service providers are encouraged to engage early to understand the project's progression before final bid and permit stages are set. This early engagement can provide a competitive advantage.

Chief Engineer
360.00 $
Project Manager
50 hours
Project Manager
14,500.00 $
Senior Engineer
294.00 $
Senior Engineer
102 hours
Senior Engineer
29,988.00 $
Engineer 1
153.50 $
Engineer 1
134 hours
Engineer 1
20,569.00 $
Engineering Intern
123.00 $
Engineering Intern
133 hours
Engineering Intern
16,359.00 $
GIS Specialist/Planner
178.00 $
Senior Designer
186.50 $
Senior Designer
67 hours
Senior Designer
12,495.50 $
Secretary/Clerical
111.00 $
Secretary/Clerical
22 hours
Secretary/Clerical
2,442.00 $
Total Direct Labor
189.67 $
Total Direct Labor
508 hours
Total Direct Labor
96,353.50 $

Industries that could win this work

  • Engineering & Architecture
  • Business Consulting
  • Office & Business Support Services

Follow this across meetings

Mira los negocios reales detrás de estos números

Obtén los registros reales, con direcciones y directivos, respaldados por una garantía de reembolso de 14 días.

Crea tu cuenta