B. Alco Groves Mine Conditional Use Permit
Planning & Zoning Commission Meeting · 2026-04-16 · agenda_item
A conditional use permit is under review for a proposed mining operation on approximately 980 acres located south of Indrio Road and west of I-95. The project, proposed by Alco Groves, plans to mine about 311 acres in phases over a 10-year period. The operation would involve creating five mining cells, dewatering systems, and measures to control dust and noise. This project is currently under review and requires major site plan approval by the Board of County Commissioners. The work would likely involve site clearing and grading, extensive dewatering and underground utility work for settling and recharge systems, and potentially road improvements including a turn lane on Indrio Road. Contractors specializing in site preparation, grading, heavy equipment operation, and utility work could find opportunities. Suppliers of construction materials and equipment, as well as environmental consultants, may also be needed. Reaching out early before final site plans and permits are set could provide a competitive advantage.
- acres
- 980 acres
- acres to be mined
- 311 acres
- mining cells
- five
- daily trips
- 644 trips
- project duration
- 10 years
- stockpile height
- 25 feet
- allowable decibel levels increase
- 50 %
Industries that could win this work
- Site Prep, Grading & Hardscape
- Utilities (Sub)
- Building & Industrial Supply
- Engineering & Architecture
- Business Consulting
- Mining & Extraction
Follow this across meetings
Applicants and firms
Mira los negocios reales detrás de estos números
Obtén los registros reales, con direcciones y directivos, respaldados por una garantía de reembolso de 14 días.
Crea tu cuenta