B. Phase 2 of the project will be funded by the Owners capital funds. The second phase of this
City Commission Meeting · 2026-04-21 · agenda_item
The City of Ocoee is reviewing Phase 2 of a utility project that involves significant underground infrastructure work. This phase includes installing approximately 1,650 linear feet of 12-inch PVC gravity sewer pipe and about 400 linear feet of 12-inch PVC forcemain, along with nine new manholes and several PVC stub outs. The project also calls for installing around 2,900 linear feet of 12-inch ductile iron water main. Work will involve connecting to existing water mains and manholes, adding hydrants and valves, pressure testing, and restoring roadways, driveways, curbs, and landscaping. This project is currently under review, offering an early opportunity for contractors. The scope includes site preparation, underground utility installation, pipe fitting, testing, and extensive site restoration. Local contractors, suppliers, and service providers in utility construction, site preparation, concrete, paving, and landscaping can explore potential involvement by reaching out early before final plans and permits are set.
- gravity sewer system
- 1650 linear feet
- gravity sewer pipe diameter
- 12 inch
- forcemain
- 400 linear feet
- forcemain diameter
- 12 inch
- new manholes
- 9
- 8-inch PVC stub outs
- 5
- 4-inch PVC forcemain stub out
- 1
- watermain
- 2900 linear feet
- watermain diameter
- 12 inch
Industries that could win this work
- Utilities (Sub)
- Site Prep, Grading & Hardscape
- Concrete & Masonry
- General Contractor
- Plumbing
- Building & Industrial Supply
Follow this across meetings
Mira los negocios reales detrás de estos números
Obtén los registros reales, con direcciones y directivos, respaldados por una garantía de reembolso de 14 días.
Crea tu cuenta