Skip to main content

Be First, Build Lasting Relationships

B. Phase 2 of the project will be funded by the Owners capital funds. The second phase of this

City Commission Meeting · 2026-04-21 · agenda_item

The City of Ocoee is reviewing Phase 2 of a utility project that involves significant underground infrastructure work. This phase includes installing approximately 1,650 linear feet of 12-inch PVC gravity sewer pipe and about 400 linear feet of 12-inch PVC forcemain, along with nine new manholes and several PVC stub outs. The project also calls for installing around 2,900 linear feet of 12-inch ductile iron water main. Work will involve connecting to existing water mains and manholes, adding hydrants and valves, pressure testing, and restoring roadways, driveways, curbs, and landscaping. This project is currently under review, offering an early opportunity for contractors. The scope includes site preparation, underground utility installation, pipe fitting, testing, and extensive site restoration. Local contractors, suppliers, and service providers in utility construction, site preparation, concrete, paving, and landscaping can explore potential involvement by reaching out early before final plans and permits are set.

gravity sewer system
1650 linear feet
gravity sewer pipe diameter
12 inch
forcemain
400 linear feet
forcemain diameter
12 inch
new manholes
9
8-inch PVC stub outs
5
4-inch PVC forcemain stub out
1
watermain
2900 linear feet
watermain diameter
12 inch

Industries that could win this work

  • Utilities (Sub)
  • Site Prep, Grading & Hardscape
  • Concrete & Masonry
  • General Contractor
  • Plumbing
  • Building & Industrial Supply

Follow this across meetings

See the actual businesses behind these numbers

Get the real filings, with addresses and officers, backed by a 14-day money-back guarantee.

Create your account