2. UAB Solar Summary through February 2026 - April Meeting

Utilities Advisory Board Regular Meeting · 2026-04-28 · agenda_item

This notice concerns ongoing utility work in the City of Winter Park, as presented to the Utilities Advisory Board. The city is undertaking a significant undergrounding effort, with various projects at different completion stages. Project J is 100% complete, while Project L is 99.6% complete near Baldwin Park. Other projects, O, K, and S, are at 80%, 65.3%, and 29.4% completion, respectively. The city has a total of 20.42 miles of undergrounding work remaining citywide. The 2026 undergrounding budget is $9.2 million, with $3.8 million spent in FY26. The city is also managing transformer inventory and has a budget for submersible transformer programs. This ongoing work involves site clearing, grading, underground utility installation, and potentially road and paving work as projects progress. Contractors, suppliers, and service providers in site preparation, utility installation, and material supply may find opportunities as these projects continue. Early engagement is advised as the city progresses through its strategic planning and procurement processes, including solicitations for substation design, conductor covering, and meter replacement programs.

miles of undergrounding performed
2.72 miles
Project L completion
9.57 miles
Project O completion
6.91 miles
Project K completion
3.24 miles
Project S completion
4.32 miles
Residential Service Conversions
41
Residential Service Conversions Year to Date
197
Residential Service Conversions Lifetime
1739
Total for FY 2026
2.11 miles
Total Citywide Project Miles
127.5 miles
Total Miles Completed
106.76 miles
Percentage Completed as of This Month
83.98 %
Total miles remaining
20.42 miles
2026 Undergrounding budget
9.2 M
FY26 Spend
3.8
Single phase transformer inventory reduction
47
Single phase transformer value
359,000 $
Three Phase transformer inventory reduction
23
Three Phase transformer value
747,000 $
transformer painting locations completed
45 locations
Substation XFRM design lead time
3–4 yr
Okonite 72K ordered
July 2026
Okonite 1000MCM additional
75K
Okonite 1000MCM additional order date
April FY27
Okonite 1/0 primary cable
150K
Okonite 1/0 primary cable order date
April FY27
Elastimold splices lead time
12- months
Elastimold splices order date
Sept.26
Submersible XFRM program locations
4 locations

Industries that could win this work

  • Utilities (Sub)
  • Site Prep, Grading & Hardscape
  • General Contractor
  • Concrete & Masonry
  • Electrical
  • Plumbing
  • Building & Industrial Supply
  • Engineering & Architecture

Follow this across meetings

Mira los negocios reales detrás de estos números

Obtén los registros reales, con direcciones y directivos, respaldados por una garantía de reembolso de 14 días.

Crea tu cuenta