2. UAB Solar Summary through February 2026 - April Meeting
Utilities Advisory Board Regular Meeting · 2026-04-28 · agenda_item
This notice concerns ongoing utility work in the City of Winter Park, as presented to the Utilities Advisory Board. The city is undertaking a significant undergrounding effort, with various projects at different completion stages. Project J is 100% complete, while Project L is 99.6% complete near Baldwin Park. Other projects, O, K, and S, are at 80%, 65.3%, and 29.4% completion, respectively. The city has a total of 20.42 miles of undergrounding work remaining citywide. The 2026 undergrounding budget is $9.2 million, with $3.8 million spent in FY26. The city is also managing transformer inventory and has a budget for submersible transformer programs. This ongoing work involves site clearing, grading, underground utility installation, and potentially road and paving work as projects progress. Contractors, suppliers, and service providers in site preparation, utility installation, and material supply may find opportunities as these projects continue. Early engagement is advised as the city progresses through its strategic planning and procurement processes, including solicitations for substation design, conductor covering, and meter replacement programs.
- miles of undergrounding performed
- 2.72 miles
- Project L completion
- 9.57 miles
- Project O completion
- 6.91 miles
- Project K completion
- 3.24 miles
- Project S completion
- 4.32 miles
- Residential Service Conversions
- 41
- Residential Service Conversions Year to Date
- 197
- Residential Service Conversions Lifetime
- 1739
- Total for FY 2026
- 2.11 miles
- Total Citywide Project Miles
- 127.5 miles
- Total Miles Completed
- 106.76 miles
- Percentage Completed as of This Month
- 83.98 %
- Total miles remaining
- 20.42 miles
- 2026 Undergrounding budget
- 9.2 M
- FY26 Spend
- 3.8
- Single phase transformer inventory reduction
- 47
- Single phase transformer value
- 359,000 $
- Three Phase transformer inventory reduction
- 23
- Three Phase transformer value
- 747,000 $
- transformer painting locations completed
- 45 locations
- Substation XFRM design lead time
- 3–4 yr
- Okonite 72K ordered
- July 2026
- Okonite 1000MCM additional
- 75K
- Okonite 1000MCM additional order date
- April FY27
- Okonite 1/0 primary cable
- 150K
- Okonite 1/0 primary cable order date
- April FY27
- Elastimold splices lead time
- 12- months
- Elastimold splices order date
- Sept.26
- Submersible XFRM program locations
- 4 locations
Industries that could win this work
- Utilities (Sub)
- Site Prep, Grading & Hardscape
- General Contractor
- Concrete & Masonry
- Electrical
- Plumbing
- Building & Industrial Supply
- Engineering & Architecture