Skip to main content

Be First, Build Lasting Relationships

City Council Budget Workshop & Regular Meeting of June 2, 2026 minutes 2026-06-02

City Council · 2026-06-02 · minutes

[Bry Lynn Drive] The City Council discussed and approved the award of contracts for several infrastructure projects. A contract for a replacement in-plant lift station duplex control panel was awarded to Barney's Pumps, Inc. for $37,563.00, with CTS Electric Service handling the installation for $5,405.69. Additionally, a contract for annual u-lining of 1,994 feet of storm pipes on Bry Lynn Drive was authorized to Insituform Technologies, LLC for $149,947.00. Public comment was not a factor in these decisions.

Follow this across meetings

See the actual businesses behind these numbers

Get the real filings, with addresses and officers, free for 7 days. No credit card required.

Start your free trial