Skip to main content

Be First, Build Lasting Relationships

CHANGE ORDER NO. 2 WITH JOHN BELL CONSTRUCTION, INC.

Board of County Commissioners · 2026-06-02 · resolution

Miami-Dade County approved Change Order No. 2 for the Coconut Grove Playhouse Phase 1 project, increasing the contract amount by $1,812,258.98 due to unforeseen deterioration of the historic gateway building's facade walls and revised structural bracing needs. The total contract amount is now $6,805,189.97. The project is funded by Convention Development Tax Bonds (Special Obligation Bond Series 2005). The original contract and Change Order No. 1 were approved under delegated authority, but this increase required Board approval. No public comment was stated in the document.

Follow this across meetings

Applicants and firms

See the actual businesses behind these numbers

Get the real filings, with addresses and officers, free for 7 days. No credit card required.

Start your free trial