Mr. Shay Hill, JEA, introduced Mr. Darrell Hamilton, Manager of Transmission and Substation Projects, JEA, who presented an update on the Fulton Cut Transmission Line Clearance Project.

Transportation, Energy & Utilities Committee · 2026-08-19 · agenda_item

JEA is undertaking the Fulton Cut Transmission Line Clearance Project to raise existing power lines over the St. Johns River. The project involves replacing four miles of wire and installing three Pyramax towers on both the north and south banks. The power lines will be raised 50 feet, from 175 feet to 225 feet above high tide, to allow larger ships to pass following river dredging. The project is currently under review and is planned to be operational by the end of 2026, with demolition of old towers scheduled for January to March 2027. This project will involve site preparation, tower construction, wire pulling, and utility work. Contractors specializing in heavy construction, electrical transmission, civil engineering, and demolition may find opportunities. Reaching out to JEA early could provide an advantage before final bids and permits are established.

transmission lines
6
Pyramax towers
3
miles of wire
4
feet
50
feet
175
feet
225
initial funding
45 million
overall project budget
117 million
Phase 3 budget
39.5 million
JEA's portion
32.5 million
years
50 to 75
planned transmission outages
2 weeks

Industries that could win this work

  • Utilities (Sub)
  • General Contractor
  • Site Prep, Grading & Hardscape
  • Concrete & Masonry
  • Electrical
  • Engineering & Architecture

Follow this across meetings

Applicants and firms

See the actual businesses behind these numbers

Get the real filings, with addresses and officers, free for 7 days. No credit card required.

Start your free trial