16. Approve Contract Change Order for Lee Health Sports Complex
Lee Board of County Commissioners · 2026-05-19 · agenda_item
Lee County is reviewing a contract change order for the Lee Health Sports Complex. This change order, proposed by M. Gay Constructors, Inc., adds $59,818 in funding for electrical system upgrades. The work involves replacing aluminum wires with copper to improve safety and efficiency. A 120-day time extension is also included to manage project completion and contractor delays related to the 2026 spring training season. This project is currently under review by the Lee Board of County Commissioners. The scope of work includes electrical system modifications, potentially involving site work, underground utilities, and specialized electrical trades. Contractors and suppliers involved in electrical systems, construction services, and project management may find opportunities as this project moves forward. Early engagement is advised before final bids and permits are set.
- Current Year Dollar Amount
- 59,818 $
- new contract total
- 2,753,777.93 $
- Original contract
- 2,651,000 $
- CO 1
- 8,499.36 $
- CO 2
- 34,461.02 $
- CO 3 (current proposed)
- 59,817.55 $
- time extension
- 120 days
Industries that could win this work
- Electrical
- General Contractor
- Engineering & Architecture
Follow this across meetings
Applicants and firms
Locations
See the actual businesses behind these numbers
Get the real filings, with addresses and officers, backed by a 14-day money-back guarantee.
Create your account