24. Authorize Sheffield Way Dredge CIP MSBU Financing
Lee Board of County Commissioners · 2026-05-19 · agenda_item
This item concerns the permanent financing for the Sheffield Way Canal Dredge Capital Improvement Project Municipal Services Benefit Unit (CIP MSBU). The project involved dredging a canal north of Landmark Court and south of Sheffield Way in unincorporated Lee County. The final construction cost was $414,965. The Municipal Services Benefit Unit was established on March 1, 2022, with a majority of property owners petitioning for it. The project is now moving into the financing stage, with a term loan of up to $454,000 being authorized for permanent financing. This financing will cover the costs of the dredging work. The work completed included site clearing and grading related to the canal, and potentially underground utility work if any was impacted. This project represents an opportunity for contractors and suppliers involved in civil engineering, dredging, and potentially related utility work. Reaching out now, before final financing details are settled, could provide an advantage.
- term loan amount
- 454,000 $
- final construction cost
- 414,965 $
- county contribution
- 62,140 $
- assessed amount per parcel
- 18,569.76 $
- parcels
- 19 parcels
- petitioning parcels
- 11 parcels
Industries that could win this work
- Site Prep, Grading & Hardscape
- Utilities (Sub)
- Engineering & Architecture
Follow this across meetings
Locations
See the actual businesses behind these numbers
Get the real filings, with addresses and officers, backed by a 14-day money-back guarantee.
Create your account