4. Final Deliverable – Final Plans, Specifications & Estimate signed and sealed along with
Lee Board of County Commissioners · 2026-05-19 · agenda_item
The Lee Board of County Commissioners is reviewing plans for a weir upgrade project at the 10 Mile Canal, Page Field location. This project involves structural design, surface water modeling, and surveying to improve the existing weir. The project is currently in the planning and review phase, with final plans, specifications, and estimates being prepared. The work will likely involve site assessment, design analysis, permitting, and bidding services, with construction phase services to follow. Contractors specializing in civil engineering, surveying, and potentially heavy construction could find opportunities. Engaging early allows businesses to understand project needs before bids and permits are finalized.
- Project Coordination and Mgmt
- 49,599.00 $
- Survey
- 17,418.00 $
- Design Analysis
- 49,230.00 $
- Permitting
- 33,942.00 $
- Design Plans
- 75,805.00 $
- Bidding Phase Services
- 7,845.00 $
- Construction Phase Services
- 64,210.00 $
- Geotech Report
- 25,185.00 $
- SCADA Design Services
- 7,500.00 $
- Electrical Eng Services
- 6,450.00 $
- Total Project Cost
- 337,184.00 $
- Total amount authorized by this CO or STA
- 337,184.00 $
- Project Coordination and Management
- 270 days
- Survey
- 270 days
- Design Analysis
- 270 days
- Permitting
- 270 days
- Design Plans
- 270 days
- Bidding Phase Services
- 330 days
- Construction Phase Services
- 695 days
- Geotech Report
- 270 days
- SCADA Design
- 270 days
- Electrical Eng Services
- 270 days
- Total Number of Calendar Days for Completion of Project from Notice to Proceed
- 695 days
Industries that could win this work
- Engineering & Architecture
- Business Consulting
- Accounting & Tax
- Site Prep, Grading & Hardscape
- General Contractor
- Concrete & Masonry
- Painting & Flooring
- Plumbing
- Restoration & Waterproofing
- Roofing
- Construction (Other)
- Utilities (Sub)
- Building & Industrial Supply
- Real Estate Development
- Landscaping & Lawn Service
Follow this across meetings
Applicants and firms
See the actual businesses behind these numbers
Get the real filings, with addresses and officers, backed by a 14-day money-back guarantee.
Create your account