CHANGE ORDER NO. 2 WITH JOHN BELL CONSTRUCTION, INC.

Board of County Commissioners · 2026-06-02 · resolution

Miami-Dade County approved Change Order No. 2 for the Coconut Grove Playhouse Phase 1 project, increasing the contract amount by $1,812,258.98 to a total of $6,805,189.97. This increase is due to unforeseen conditions, specifically extensive deterioration of the historic gateway building's facade walls and revised structural bracing requirements. The work is funded by Convention Development Tax Bonds (Special Obligation Bond Series 2005). The original contract and Change Order No. 1 were approved under delegated authority, but this change order required Board approval due to exceeding the delegated authority threshold. No public comment was noted in the document.