Skip to main content

Be First, Build Lasting Relationships

Board of County Commissioners: July 2026

Miami-Dade County

WATER AND WASTEWATER RETAIL RATE ADJUSTMENT REPORT

This is a legislative report to the Miami-Dade Board of County Commissioners regarding a proposed 6% water and wastewater retail rate adjustment for the Miami-Dade Water and Sewer Department (WASD), effective October 1, 2026. The report was introduced on 7/9/2026 and accepted on 7/21/2026. The adjustment is projected to generate approximately $65.6 million in recurring annual revenue to support approximately $435 million in bond financing. The report states that without the increase, approximately $435 million in projects would be cancelled, including specific projects and Professional Services Agreements (PSAs) listed in Figure 1. The report also details the impacts of maintaining flat rates, including potential violations of bond covenants and the Consent Decree. The document does not state a specific street address, parcel, or acreage. The decision is 'Accepted' as a report; the document does not state an approval or denial of the rate adjustment itself.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Report
Decision:
Accepted (report)
Applicant:
Mayor Daniella Levine Cava (Requester: Mayor)

WATER AND WASTEWATER RETAIL RATE ADJUSTMENT REPORT

This is a legislative report to the Miami-Dade Board of County Commissioners regarding a proposed 6% water and wastewater retail rate adjustment for the Miami-Dade Water and Sewer Department (WASD), effective October 1, 2026. The adjustment is projected to generate approximately $65.6 million in recurring annual revenue to support approximately $435 million in bond financing. The report states that without the increase, approximately $435 million in projects would be cancelled, including specific projects and professional service agreements listed in Figure 1. The report is a legislative matter with file number 261269, introduced on 7/9/2026, and scheduled for the agenda on 7/21/2026 as item 14B1. The report is before the Board, with no final action stated. The proposed rate adjustment would increase the monthly bill for low-usage households by approximately $0.82 and for the typical residential customer by approximately $3.77. The report states the adjustment is necessary to fulfill obligations under the Consent Decree, the Ocean Outfall Legislation Program, the Advanced Metering Infrastructure (AMI) Implementation, and other regulatory requirements. The report notes that the average combined water and sewer bill will remain below 1% of the median household income. The report does not state any public comment or stakeholder sentiment.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Report
Decision:
Before the Board
Applicant:
Mayor Daniella Levine Cava

WATER AND WASTEWATER RETAIL RATE ADJUSTMENT REPORT

The document is a report regarding a proposed 6% water and wastewater retail rate adjustment for the Miami-Dade Water and Sewer Department, effective October 1, 2026. The adjustment is countywide and would increase the monthly bill for low-usage households by approximately $0.82 and for the typical residential customer by approximately $3.77. It is projected to generate approximately $65.6 million in recurring annual revenue to support approximately $435 million in bond financing. The report was accepted by the Board of County Commissioners on 7/21/2026. The document does not state a specific street address, parcel, or acreage. It lists numerous projects that would be cancelled if the rate adjustment is not approved, including specific projects and professional services agreements with contractors such as Jacobs Engineering, AECOM, Hazen and Sawyer, Black and Veatch, Brown and Caldwell, HDR Engineering, and others. The document does not state any public comment or stakeholder sentiment.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Report
Decision:
Accepted
Applicant:
Miami-Dade County Mayor Daniella Levine Cava

WATER AND WASTEWATER RETAIL RATE ADJUSTMENT REPORT

Miami-Dade County is considering a 6% water and wastewater retail rate adjustment for the Miami-Dade Water and Sewer Department (WASD), effective October 1, 2026. This adjustment is necessary to fund critical infrastructure improvements required by a Consent Decree with federal and state agencies, the Ocean Outfall Legislation Program, Advanced Metering Infrastructure (AMI) implementation, and other regulatory obligations. The proposed increase is projected to generate approximately $65.6 million in annual revenue, supporting approximately $435 million in bond financing for projects. Without this adjustment, critical projects, including those under Professional Service Agreements (PSAs) with firms like Jacobs Engineering, AECOM, and Hazen and Sawyer, would be cancelled, potentially leading to penalties, claims, and service disruptions. The report lists numerous specific projects and associated PSAs that would be immediately cancelled if the rate adjustment is not approved. The County aims to maintain compliance with regulatory mandates and avoid financial penalties and credit rating downgrades. Public comment is not detailed in this document.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Report
Decision:
Report presented for consideration by the Board of County Commissioners; final decision not stated.
Applicant:
Miami-Dade Water and Sewer Department (WASD)

WATER AND WASTEWATER RETAIL RATE ADJUSTMENT REPORT

The document is a report regarding a proposed 6% water and wastewater retail rate adjustment for the Miami-Dade Water and Sewer Department, effective October 1, 2026. The adjustment is countywide and applies to retail customers in WASD's service areas. The report was accepted by the Board of County Commissioners on 7/21/2026. The adjustment is projected to generate approximately $65.6 million in recurring annual revenue to support approximately $435 million in bond financing. The report states that without the increase, approximately $435 million in projects would be cancelled, including specific projects and professional service agreements listed in Figure 1. The report also states that the adjustment would increase the monthly bill for low-usage households by approximately $0.82 and for the typical residential customer by approximately $3.77. The report does not state a specific street address, parcel, or acreage. The report does not state any public comment or stakeholder sentiment.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Report
Decision:
Accepted
Applicant:
Miami-Dade County Mayor Daniella Levine Cava

WATER AND WASTEWATER RETAIL RATE ADJUSTMENT REPORT

The document is a report to the Board of County Commissioners regarding a proposed 6% water and wastewater retail rate adjustment for the Miami-Dade Water and Sewer Department, effective October 1, 2026. The adjustment is projected to generate approximately $65.6 million in recurring annual revenue to support approximately $435 million in bond financing. The report was accepted by the Board on July 21, 2026. The document lists projects and professional services agreements that would be immediately cancelled if the rate adjustment is not approved, including specific projects with associated costs and contractors. No public comment or stakeholder sentiment is stated in the document.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Report
Decision:
Accepted
Applicant:
Miami-Dade County Mayor Daniella Levine Cava

WATER AND WASTEWATER RETAIL RATE ADJUSTMENT REPORT

The document is a report regarding a proposed 6% water and wastewater retail rate adjustment for the Miami-Dade Water and Sewer Department, effective October 1, 2026. The adjustment is countywide for retail customers in WASD service areas. It is projected to generate approximately $65.6 million in recurring annual revenue to support approximately $435 million in bond financing. The report was accepted by the Board of County Commissioners on 7/21/2026. The report lists projects and professional services agreements that would be immediately cancelled if the rate adjustment is not approved, including specific projects such as the Oxygen Production Facility, RAS Pump Station Upgrade Plant 1, Digesters Rehabilitation Cluster 3, 48-in PCCP Forcemain Replacement - Opa Locka (Phase 2), Pump Station Upgrades (Regional), Industrial Reuse System (South), Treatment Filters Upgrade (Orr Plant), Effluent Pump Station Upgrade, Hypochlorite Building Hardening, New Headwork Facility (Central), Monitoring Well Installation, Co-Generation Facility HVAC Improvements (South), Transmission Main Replacement, FED Required - Inflow and Infiltration Inspection & Repairs, JPA with City of Miami - Auburndale Neighborhood, Compliance Upgrade: Lab and Control Room, Control Room Facility Upgrade (Hialeah), Supply Wells Upgrade, Everglades Plant Upgrade, Naranja Plant Upgrade, Sludge Line Replacement (Orr), Connect 2 Protect - Lateral Expansion, New Regional Pump Station - Downtown Miami, 2050 Planning Horizon Integrated Master Plan - Wastewater, Small Diameter Replacement NE 203 Terr, 54-in PCCP Watermain SW 56th St & SW 67th Av, 36-in Crossing Normandy Isle along 79th St via HDD, Replacement of 36-in Forcemain NE 163rd St, PS-0415 to PS-0422 Transmission Force Main Replacement, Aventura (Biscayne Blvd) Force Main Replacement, Replacement of 36-in Forcemain Snake Creek Canal, Pump Station 49, 425 Upgrade, Pump Station 0300 Upgrade, Pump Station 0613, 616 Relocation, Pump Station No. 0618 Upgrade, Pump Station No. 455, 812, 831, 856, 867, 882, 894 Upgrade, Pump Station No. 2, 345, 347 and 348 Generator / Upgrade, Pump Station 374, 404, 408, 409, 410 Upgrade, Pump Station 18, 33, 34, 41, and 315, 413, 443, 1163, Pump Station 0703 Upgrade, Pump Station 0339 Upgrade, Pump Station 63, 382, 549, 704, 803, 815, 865, 1034, Regulatory Lab & Operator Control Room Replacement, East and West Pump Room Upgrades, Holding Tanks and Contact Basins Improvement (Orr), Lime Plant Fire and HVAC (Orr), Electrical Replacement and Upgrade (Orr), Electrical Distribution Building Upgrade (Orr), Pumping Facility Upgrade (Orr), New Hypochlorite Facility (Preston), Filter Backwash Tank (Hialeah), East and West Pump Room Upgrades (Hialeah), Electrical Distribution Building Upgrade, Operator's Control Room Upgrade (Hialeah), Building Access Safety and Code Compliance (WTPs), Plantwide Structural Assessment - Hialeah, Pumping Facility Upgrade (Preston), Electrical Upgrades Medium Voltage, Lime Plant Holding Tanks Upgrade (Hialeah), Filter Overhaul and Automation (Hialeah), Watermain Upgrade: Green Tech Corridor S-4, Watermain Upgrade: Green Tech Corridor D2, Watermain Upgrade: SW 87th AVE and Caribbean Blvd, Watermain Upgrade: NW 1st St and NW 11th Ave, Watermain Upgrade: NE 6 & 7 Ct and Snapper Creek, Watermain Upgrade: Atlas W32 Quadrant A&B, Watermain Upgrade: SW 9th & 5th Ave, Valves and Access Manholes Replacement, Watermain Upgrade: SW 5th, and E Palm Dr, Watermain Upgrade: Atlas P16 Quadrant C, Watermain Upgrade: Atlas Q16, Watermain Upgrade: Atlas V31, Watermain Upgrade: Atlas K3 Quadrant C, Watermain Upgrade: Atlas F13, Watermain Upgrade: Atlas R26, Watermain Upgrade: Atlas K17, and 2050 Planning Horizon Integrated Master Plan - Water. The total proposed allocation for these cancelled projects is $434,744,289. The report also states that without the requested increase, work under Professional Service Agreements with Jacobs Engineering, AECOM, and Hazen and Sawyer would be terminated. The report notes that the proposed adjustment would increase the monthly bill for low-usage households by approximately $0.82 and for the typical residential customer by approximately $3.77. The report states that even with the proposed adjustment, the average combined water and sewer bill will continue to remain below 1% of the median household income. The report does not state any public comment or stakeholder sentiment.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Report
Decision:
Accepted
Applicant:
Mayor Daniella Levine Cava

WATER AND WASTEWATER RETAIL RATE ADJUSTMENT REPORT

The document is a report to the Board of County Commissioners regarding a proposed 6% water and wastewater retail rate adjustment for the Miami-Dade Water and Sewer Department, effective October 1, 2026. The adjustment is projected to generate approximately $65.6 million in recurring annual revenue to support approximately $435 million in bond financing. The report was introduced on 7/9/2026 and accepted on 7/21/2026. The document does not state a specific project site, address, parcel, or acreage. It lists numerous projects and professional service agreements that would be cancelled if the rate adjustment is not approved, including the Ocean Outfall Program, Consent Decree Program, Advanced Metering Infrastructure, and various watermain, pump station, and treatment plant upgrades. The document does not state any public comment or stakeholder sentiment.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Report
Decision:
Accepted
Applicant:
Miami-Dade County Mayor Daniella Levine Cava

WATER AND WASTEWATER RETAIL RATE ADJUSTMENT REPORT

This is a legislative report regarding a proposed 6% water and wastewater retail rate adjustment for the Miami-Dade Water and Sewer Department, effective October 1, 2026. The report was introduced on 7/9/2026, and the final action was on 7/21/2026, where it was accepted. The proposed adjustment is necessary to fund the Capital Improvement Program and meet regulatory obligations, including the Consent Decree, Ocean Outfall Legislation Program, and Advanced Metering Infrastructure implementation. The adjustment is projected to generate approximately $65.6 million in recurring annual revenue to support approximately $435 million in bond financing. The report includes a list of projects and professional service agreements that would be immediately cancelled if the rate adjustment is not approved. The report does not state a specific street address, parcel, or acreage. The applicant/developer/owner is not stated; the report is from the Mayor to the Board of County Commissioners. The case/file number is 261269. The decision was 'Accepted' on 7/21/2026. The report does not state any public comment or stakeholder sentiment.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Report
Decision:
Accepted

WATER AND WASTEWATER RETAIL RATE ADJUSTMENT REPORT

The document is a legislative report regarding a proposed 6% water and wastewater retail rate adjustment for the Miami-Dade Water and Sewer Department, effective October 1, 2026. The report was introduced on 7/9/2026, and the final action was on 7/21/2026, where it was accepted. The adjustment is projected to generate approximately $65.6 million in recurring annual revenue to support approximately $435 million in bond financing. The report lists projects and professional services agreements that would be immediately cancelled if the rate adjustment is not approved, including specific project names, OMB numbers, proposed allocations, and contractors. The report states that the proposed adjustment would increase the monthly bill for low-usage households by approximately $0.82 and for the typical residential customer by approximately $3.77. The report also states that the average combined water and sewer bill will remain below 1% of the median household income. The report mentions that the rate adjustment would require an amendment to Implementing Order 4-110. The report does not state a specific street address, parcel, or acreage. The report does not state a specific applicant or developer name. The report does not state a zoning or use change. The report does not state any public comment or stakeholder sentiment. The report does not state a specific business opportunity for contractors or trades beyond the list of projects that would be cancelled if the rate adjustment is not approved.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Report
Decision:
Accepted

WATER AND WASTEWATER RETAIL RATE ADJUSTMENT REPORT

The document is a report regarding a proposed 6% water and wastewater retail rate adjustment for the Miami-Dade Water and Sewer Department, effective October 1, 2026. The adjustment is countywide and would generate approximately $65.6 million in recurring annual revenue to support approximately $435 million in bond financing. The report was accepted by the Board of County Commissioners on July 21, 2026. The document lists projects that would be cancelled if the rate adjustment is not approved, including specific projects and professional service agreements. No public comment or stakeholder sentiment is stated in the document.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Report
Decision:
Accepted
Applicant:
Mayor Daniella Levine Cava

WATER AND WASTEWATER RETAIL RATE ADJUSTMENT REPORT

This is a legislative report regarding a proposed 6% water and wastewater retail rate adjustment for the Miami-Dade Water and Sewer Department (WASD), effective October 1, 2026. The adjustment is proposed to generate approximately $65.6 million in recurring annual revenue to support approximately $435 million in bond financing. The report details that without the increase, approximately $435 million in projects would be cancelled, including specific projects and Professional Service Agreements (PSAs) listed in Figure 1. The report is scheduled for the Board of County Commissioners agenda on July 21, 2026, as item 14B1. The report was introduced on July 9, 2026, and is currently in draft status. The proposed rate adjustment would require an amendment to Implementing Order 4-110, WASD's Schedule of Rates, Fees, and Charges. The report states the adjustment will have a countywide impact on retail customers in WASD's service areas. The report notes that the next planned bond issuance is anticipated in Fiscal Year 2026-27 and is dependent upon the revenues generated by the proposed rate adjustment. The report also states that the proposed adjustment applies only to retail customers, and wholesale customer rates will be evaluated separately. The report includes a list of projects and PSAs that would be immediately cancelled if the rate adjustment is not approved, including projects related to the Ocean Outfall Program, Consent Decree Program, Advanced Metering Infrastructure (AMI), and various water and sewer infrastructure upgrades. The report mentions that the Consent Decree compliance deadline is June 2028 and the program is approximately 89% complete. The report states that the proposed rate adjustment would increase the monthly bill for low-usage households by approximately $0.82 and for the typical residential customer by approximately $3.77, or 12 cents per day. The report also states that even with the proposed adjustment, the average combined water and sewer bill will continue to remain below 1% of the median household income. The report does not state a specific street address, parcel, or acreage for a project, as it is a countywide rate adjustment report. The report does not state a final decision, as it is a report to the Board. The report does not include any public comment or stakeholder sentiment.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Report
Decision:
not stated; report is in draft status and scheduled for Board agenda
Applicant:
Mayor Daniella Levine Cava

WATER AND WASTEWATER RETAIL RATE ADJUSTMENT REPORT

Miami-Dade County is proposing a 6% water and wastewater retail rate adjustment for the Miami-Dade Water and Sewer Department (WASD), effective October 1, 2026. This adjustment is necessary to fund infrastructure improvements required by a Consent Decree with the United States and the State of Florida, the State-mandated Ocean Outfall Legislation Program, Advanced Metering Infrastructure implementation, and other critical regulatory requirements. The proposed adjustment is projected to generate approximately $65.6 million in annual revenue, supporting approximately $435 million in bond financing for projects. Failure to implement the rate increase could lead to the suspension of critical projects, potential violations of federal orders, financial penalties, and increased future rate hikes. The document lists numerous Professional Service Agreements (PSAs) and construction projects that would be cancelled or significantly reduced if the rate adjustment is not approved, impacting contractors such as Jacobs Engineering, AECOM, Hazen and Sawyer, Black and Veatch, and others. The report indicates that even with the proposed adjustment, average combined water and sewer bills will remain below 1% of the median household income and below the average of comparable utilities.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Report
Decision:
Report presented to the Board of County Commissioners for consideration; final action not stated in this document.
Address:
Countywide
Applicant:
Miami-Dade Water and Sewer Department (WASD)

WATER AND WASTEWATER RETAIL RATE ADJUSTMENT REPORT

The document is a report to the Board of County Commissioners regarding a proposed 6% water and wastewater retail rate adjustment for the Miami-Dade Water and Sewer Department, effective October 1, 2026. The adjustment is projected to generate approximately $65.6 million in recurring annual revenue to support approximately $435 million in bond financing. The report was accepted by the Board of County Commissioners on 7/21/2026. The report lists projects and professional services agreements that would be immediately cancelled if the rate adjustment is not approved, including specific projects and contractors. The document does not state a specific street address, parcel, or acreage for a construction project. The document does not state any public comment or stakeholder sentiment.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Report
Decision:
Accepted
Applicant:
Miami-Dade County Mayor Daniella Levine Cava

WATER AND WASTEWATER RETAIL RATE ADJUSTMENT REPORT

This is a report to the Board of County Commissioners regarding a proposed 6% water and wastewater retail rate adjustment for the Miami-Dade Water and Sewer Department, effective October 1, 2026. The adjustment is projected to generate approximately $65.6 million in recurring annual revenue to support approximately $435 million in bond financing. The report was accepted by the Board on 7/21/2026. The report lists projects and professional services agreements that would be immediately cancelled if the rate adjustment is not approved, including specific projects and contractors. No public comment or stakeholder sentiment is stated in the document.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Report
Decision:
Accepted
Applicant:
Mayor Daniella Levine Cava

WATER AND WASTEWATER RETAIL RATE ADJUSTMENT REPORT

The document is a report regarding a proposed 6% water and wastewater retail rate adjustment for the Miami-Dade Water and Sewer Department, effective October 1, 2026. The adjustment is countywide and would generate approximately $65.6 million in recurring annual revenue to support approximately $435 million in bond financing. The report was accepted by the Board of County Commissioners on 7/21/2026. The report lists projects and professional services agreements that would be immediately cancelled if the rate adjustment is not approved, including specific projects with associated costs and contractors. The report does not state a specific street address, parcel, or acreage for a construction project. The report does not state any public comment or stakeholder sentiment.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Report
Decision:
Accepted
Applicant:
Miami-Dade County Mayor Daniella Levine Cava

WATER AND WASTEWATER RETAIL RATE ADJUSTMENT REPORT

The document is a report regarding a proposed 6% water and wastewater retail rate adjustment for the Miami-Dade Water and Sewer Department, effective October 1, 2026. The adjustment is countywide for retail customers in WASD's service areas. It is projected to generate approximately $65.6 million in recurring annual revenue to support approximately $435 million in bond financing. The report was accepted by the Board of County Commissioners on 7/21/2026. The report details that without the increase, approximately $435 million in projects would be cancelled, including specific projects and professional service agreements listed in Figure 1. The report also states that the adjustment would increase the monthly bill for low-usage households by approximately $0.82 and for the typical residential customer by approximately $3.77. The report does not state any public comment or stakeholder sentiment.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Report
Decision:
Accepted
Applicant:
Miami-Dade County Mayor Daniella Levine Cava

WATER AND WASTEWATER RETAIL RATE ADJUSTMENT REPORT

The document is a report regarding a proposed 6% water and wastewater retail rate adjustment for the Miami-Dade Water and Sewer Department, effective October 1, 2026. The adjustment is countywide and would generate approximately $65.6 million in recurring annual revenue to support approximately $435 million in bond financing. The report was accepted by the Board of County Commissioners on 7/21/2026. The document lists projects and professional services agreements that would be immediately cancelled if the rate adjustment is not approved, including specific projects with proposed allocations and contractors. No public comment or stakeholder sentiment is stated in the document.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Report
Decision:
Accepted
Applicant:
Miami-Dade County Mayor Daniella Levine Cava

WATER AND WASTEWATER RETAIL RATE ADJUSTMENT REPORT

The document is a report regarding a proposed 6% water and wastewater retail rate adjustment for the Miami-Dade Water and Sewer Department, effective October 1, 2026. The adjustment is countywide for retail customers in WASD's service areas. It is projected to generate approximately $65.6 million in recurring annual revenue to support approximately $435 million in bond financing. The report was accepted by the Board of County Commissioners on 7/21/2026. The report states that without the increase, approximately $435 million in projects would be cancelled, including specific projects and professional service agreements. The report also states that the adjustment would increase the monthly bill for low-usage households by approximately $0.82 and for the typical residential customer by approximately $3.77. The report notes that the rate adjustment would require an amendment to Implementing Order 4-110. The document does not state a specific street address, parcel, or acreage for a construction project. The document does not contain public comment or stakeholder sentiment.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Report
Decision:
Accepted
Applicant:
Mayor Daniella Levine Cava (Requester: Mayor)

WATER AND WASTEWATER RETAIL RATE ADJUSTMENT REPORT

This is a report to the Board of County Commissioners regarding a proposed 6% water and wastewater retail rate adjustment for the Miami-Dade Water and Sewer Department (WASD), effective October 1, 2026. The adjustment is needed to fund the Capital Improvement Program (CIP) and meet regulatory obligations, including the Consent Decree, Ocean Outfall Legislation Program, and Advanced Metering Infrastructure (AMI) implementation. The proposed adjustment would generate approximately $65.6 million in recurring annual revenue to support approximately $435 million in bond financing. Without the increase, approximately $435 million in projects would be cancelled, and certain Professional Service Agreements (PSAs) with Jacobs Engineering, AECOM, and Hazen and Sawyer would be terminated. The report was accepted by the Board of County Commissioners on 7/21/2026. The document does not state a specific project site, address, or parcel, and does not include any public comment or stakeholder sentiment.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Report
Decision:
Accepted
Applicant:
Mayor Daniella Levine Cava

WATER AND WASTEWATER RETAIL RATE ADJUSTMENT REPORT

Miami-Dade County legislative item File Number 261269 is a report regarding a proposed 6% water and wastewater retail rate adjustment for the Miami-Dade Water and Sewer Department (WASD), effective October 1, 2026. The report was introduced on 7/9/2026, and the final action was 'Accepted' on 7/21/2026. The adjustment is projected to generate approximately $65.6 million in recurring annual revenue to support approximately $435 million in bond financing. The report details that without the increase, approximately $435 million in projects would be cancelled, including specific projects and Professional Services Agreements (PSAs) listed in Figure 1. The report states the adjustment would increase the monthly bill for low-usage households by approximately $0.82 and for the typical residential customer by approximately $3.77. The report recommends the adjustment to fulfill obligations under the Consent Decree, Ocean Outfall Legislation Program, Advanced Metering Infrastructure (AMI) Implementation, and other regulatory requirements. The report notes that the rate adjustment would require an amendment to Implementing Order 4-110, WASD's Schedule of Rates, Fees, and Charges. The report states that the proposed adjustment applies only to retail customers, and wholesale customer rates will be evaluated separately. The report also states that even with the proposed adjustment, the average combined water and sewer bill will remain below 1% of the median household income. The report lists numerous projects that would be cancelled if the rate adjustment is not approved, including but not limited to: Ocean Outfall Program ($12,788,783), Consent Decree Program and Construction Management ($183,464), Water and Sewer Design Services ($1,900,000), Wastewater Design Services ($4,400,000 each for Hazen and Sawyer, Black and Veatch, Brown and Caldwell), Capacity, Management, Operations and Maintenance ($2,200,000), Building Access Safety ($41,032,387), 48-in PCCP Forcemain Replacement - Opa Locka (Phase 2) ($4,500,000), Pump Station Upgrades (Regional) ($826,450), Industrial Reuse System (South) ($4,390,120), Treatment Filters Upgrade (Orr Plant) ($30,250,000), Effluent Pump Station Upgrade ($7,170,731), Hypochlorite Building Hardening ($27,893,326), Monitoring Well Installation ($2,970,784), Co-Generation Facility HVAC Improvements (South) ($13,578,864), Transmission Main Replacement ($3,076,322), FED Required - Inflow and Infiltration Inspection & Repairs ($15,605,946), JPA with City of Miami - Auburndale Neighborhood ($5,500,000), Compliance Upgrade: Lab and Control Room ($11,734,255), Control Room Facility Upgrade (Hialeah) ($5,050,950), Supply Wells Upgrade ($16,797,319), Sludge Line Replacement (Orr) ($2,125,304), Connect 2 Protect - Lateral Expansion ($8,975,000), 2050 Planning Horizon Integrated Master Plan - Wastewater ($3,091,050), Small Diameter Replacement NE 203 Terr ($25,836,782), Replacement of 36-in Forcemain NE 163rd St ($20,147,250), Pump Station 49, 425 Upgrade ($45,408,826), Regulatory Lab & Operator Control Room Replacement ($39,976,612), New Hypochlorite Facility (Preston) ($40,981,155), Watermain Upgrade: Green Tech Corridor S-4 ($27,552,609). The total for the listed projects is $434,744,289. The report also lists specific contractors for some projects, including Allied Contractors, Maestre Construction, Poole & Kent, Comtech Engineering, All Webbs Enterprises, David Mancini and Sons, Central Civil, Roadway Construction, RF Environmental, and NV5 Inc. The report states that without the increase, work under PSAs with Jacobs Engineering, AECOM, and Hazen and Sawyer would be terminated. The report notes that the next planned bond issuance is anticipated in Fiscal Year 2026-27 and is dependent upon the revenues generated by the proposed rate adjustment. The report also states that maintaining flat rates would hinder the Department's ability to meet minimum annual investment thresholds required under the County's 1993 Master Bond Ordinance and required debt service coverage ratios (1.10 for senior obligations and 1.00 for subordinate obligations).

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Report
Decision:
Accepted
Applicant:
Mayor Daniella Levine Cava

WATER AND WASTEWATER RETAIL RATE ADJUSTMENT REPORT

The document is a report regarding a proposed 6% water and wastewater retail rate adjustment for the Miami-Dade Water and Sewer Department, effective October 1, 2026. The adjustment is countywide in scope, impacting retail customers in WASD's service areas. It is projected to generate approximately $65.6 million in recurring annual revenue to support approximately $435 million in bond financing. The report was accepted by the Board of County Commissioners on July 21, 2026. The report includes a list of projects and professional service agreements that would be immediately cancelled if the rate adjustment is not approved, totaling $434,744,289. The report does not state a specific street address, parcel, or acreage. The report does not state any public comment or stakeholder sentiment.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Report
Decision:
Accepted
Applicant:
Miami-Dade County Mayor Daniella Levine Cava

WATER AND WASTEWATER RETAIL RATE ADJUSTMENT REPORT

The document is a legislative report regarding a proposed 6% water and wastewater retail rate adjustment for the Miami-Dade Water and Sewer Department (WASD), effective October 1, 2026. The adjustment is countywide and would generate approximately $65.6 million in recurring annual revenue to support approximately $435 million in bond financing. The report was introduced on 7/9/2026 and accepted by the Board of County Commissioners on 7/21/2026. The report lists numerous projects and professional services agreements that would be cancelled if the rate adjustment is not approved, including projects related to Consent Decree compliance, Ocean Outfall Legislation, Advanced Metering Infrastructure (AMI), and other infrastructure improvements. The report does not state a specific street address, parcel, or acreage for a project, as this is a countywide rate adjustment, not a specific construction project. The report does not state any public comment or stakeholder sentiment.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Report
Decision:
Accepted
Applicant:
Mayor Daniella Levine Cava (requester)

WATER AND WASTEWATER RETAIL RATE ADJUSTMENT REPORT

The document is a legislative item report regarding a proposed 6% water and wastewater retail rate adjustment for the Miami-Dade Water and Sewer Department, effective October 1, 2026. The report was introduced on 7/9/2026, and the final action was on 7/21/2026, with the Board of County Commissioners accepting the item. The adjustment is projected to generate approximately $65.6 million in recurring annual revenue to support approximately $435 million in bond financing. The report lists projects and professional services agreements that would be immediately cancelled if the rate adjustment is not approved, with a total proposed allocation of $434,744,289. The report does not state a specific street address, parcel, or acreage. The applicant/developer/owner is not stated; the report is from the Mayor to the Board of County Commissioners. The case/file number is 261269. The decision is 'Accepted' as of 7/21/2026. The report does not include public comment or stakeholder sentiment. The business opportunity for contractors and trades is the potential for work on the listed projects if the rate adjustment is approved, and the cancellation of those projects if it is not.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Report
Decision:
Accepted

WATER AND WASTEWATER RETAIL RATE ADJUSTMENT REPORT

The document is a report regarding a proposed 6% water and wastewater retail rate adjustment for the Miami-Dade Water and Sewer Department (WASD), effective October 1, 2026. The adjustment is countywide in scope, affecting retail customers in WASD's service areas. It is projected to generate approximately $65.6 million in recurring annual revenue to support approximately $435 million in bond financing. The report was accepted by the Board of County Commissioners on July 21, 2026. The report details that without the increase, approximately $435 million in projects would be cancelled, including specific projects and professional service agreements listed in Figure 1. The report also states that the adjustment would increase the monthly bill for low-usage households by approximately $0.82 and for the typical residential customer by approximately $3.77. The report notes that the rate adjustment would require an amendment to Implementing Order 4-110, WASD's Schedule of Rates, Fees, and Charges. The document does not state any public comment or stakeholder sentiment.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Report
Decision:
Accepted
Applicant:
Mayor Daniella Levine Cava

WATER AND WASTEWATER RETAIL RATE ADJUSTMENT REPORT

The document is a legislative report regarding a proposed 6% water and wastewater retail rate adjustment for the Miami-Dade Water and Sewer Department, effective October 1, 2026. The report was introduced on 7/9/2026, and the final action was on 7/21/2026, where it was accepted by the Board of County Commissioners. The adjustment is projected to generate approximately $65.6 million in recurring annual revenue to support approximately $435 million in bond financing. The report states that without the increase, approximately $435 million in projects would be cancelled, including specific projects and professional service agreements listed in Figure 1. The report does not state a specific street address, parcel, or acreage for a construction project; it is a countywide rate adjustment affecting retail customers in WASD's service areas. The document does not include any public comment or stakeholder sentiment.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Report
Decision:
Accepted
Applicant:
Miami-Dade County Mayor Daniella Levine Cava (requester: Mayor)

ZOO MIAMI ANIMAL HOSPITAL

Resolution granting a non-exclusive underground utility easement to Florida Power and Light Company for installation of underground facilities within Zoo Miami in support of the Zoo Miami Hospital. The easement is for a 15' by 15' wide utility easement. The County receives $10.00. Adopted by the Board of County Commissioners on 7/21/2026. The Infrastructure, Innovation & Technology Committee forwarded it with a favorable recommendation on 6/10/2026. Introduced 5/14/2026. Prime Sponsor: Kionne L. McGhee. Requester: Parks, Recreation and Open Spaces. No public comment sentiment is stated in the document.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Adopted
Address:
124000 SW 152 Street, Miami, Florida
Applicant:
Parks, Recreation and Open Spaces (PROS) Department

ZOO MIAMI ANIMAL HOSPITAL

Miami-Dade County Board of County Commissioners is considering a resolution to grant a non-exclusive underground utility easement to Florida Power and Light Company (FPL). This easement is for the installation of underground electrical facilities to support the new Zoo Miami Animal Hospital. The easement will be located within Zoo Miami. The Infrastructure, Innovation & Technology Committee forwarded this item to the Board with a favorable recommendation. FPL will be responsible for the installation, operation, and maintenance of the utilities and will pay a nominal sum of $10.00 for the easement. The easement area is described as a 15-foot by 15-foot wide utility easement.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Forwarded to BCC with a favorable recommendation by the Infrastructure, Innovation & Technology Committee; pending final action by the Board of County Commissioners.
Address:
124000 SW 152 Street, Miami, Florida
Applicant:
Florida Power and Light Company (FPL)

ZOO MIAMI ANIMAL HOSPITAL

Miami-Dade County Board of County Commissioners is considering a resolution to grant a non-exclusive underground utility easement to Florida Power and Light Company (FPL). This easement is for the installation of underground electrical facilities to support the new Zoo Miami Animal Hospital. The easement will be located within Zoo Miami, a county-owned property. FPL will be responsible for the installation, operation, and maintenance of these facilities. The Infrastructure, Innovation & Technology Committee forwarded this item to the Board with a favorable recommendation. The resolution authorizes the County Mayor or designee to execute the easement and exercise all related provisions. The project involves a 15-foot by 15-foot utility easement area.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Forwarded to BCC with a favorable recommendation by the Infrastructure, Innovation & Technology Committee. Status is 'Before the Board'.
Address:
124000 SW 152 Street, Miami, Florida
Applicant:
Florida Power and Light Company (FPL)

ZOO MIAMI ANIMAL HOSPITAL

Resolution granting a non-exclusive underground utility easement to Florida Power and Light Company for installation of underground facilities within Zoo Miami in support of the Zoo Miami Hospital. The easement is on a portion of County-owned land within Zoo Miami, located at 124000 SW 152 Street, Miami, Florida, Folio No. 30-5936-000-0050. The easement is 15 feet by 15 feet wide. FPL will pay $10.00 for the easement. The resolution was adopted by the Board of County Commissioners on 7/21/2026. The Infrastructure, Innovation & Technology Committee forwarded it to the BCC with a favorable recommendation on 6/10/2026. The file number is 260864, reference R-629-26. The applicant is Miami-Dade County Parks, Recreation and Open Spaces Department. The prime sponsor is Kionne L. McGhee. The property is in County Commission District 9. The easement is for installation, operation, and maintenance of underground electrical utility facilities, including cables, conduits, and appurtenant equipment, with the right to reconstruct, improve, add to, enlarge, change voltage and size, and remove such facilities. The resolution authorizes the County Mayor or designee to execute the easement and record it. No public comment or stakeholder sentiment is stated in the document.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Adopted
Address:
124000 SW 152 Street, Miami, Florida
Applicant:
Miami-Dade County Parks, Recreation and Open Spaces Department

ZOO MIAMI ANIMAL HOSPITAL

The Board of County Commissioners adopted Resolution R-629-26, granting a non-exclusive underground utility easement to Florida Power and Light Company for the installation of underground facilities within Zoo Miami in support of the Zoo Miami Hospital. The easement is for a 15'-0

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution

ZOO MIAMI ANIMAL HOSPITAL

Resolution granting a non-exclusive underground utility easement to Florida Power and Light Company for installation of underground facilities within Zoo Miami in support of the Zoo Miami Hospital. The easement is for a 15'-0" by 15'-0" wide utility easement. The County approved and authorized the County Mayor or designee to execute the easement in exchange for $10.00. The resolution was adopted by the Board of County Commissioners on 7/21/2026, after being forwarded with a favorable recommendation by the Infrastructure, Innovation & Technology Committee on 6/10/2026. The applicant is not stated; the requester is Parks, Recreation and Open Spaces. The case file number is 260864, reference R-629-26. The property is located at 124000 SW 152 Street, Miami, Florida, Folio No. 30-5936-000-0050. The size is not stated beyond the easement dimensions. The zoning or use change is not stated; the document grants an easement, not a zoning change. Public comment sentiment is not stated.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Adopted
Address:
124000 SW 152 Street, Miami, Florida

ZOO MIAMI ANIMAL HOSPITAL

Resolution granting a non-exclusive underground utility easement to Florida Power and Light Company for installation of underground facilities within Zoo Miami in support of the Zoo Miami Hospital. The easement is located at 124000 SW 152 Street, Miami, Florida, Folio No. 30-5936-000-0050. The easement is 15 feet by 15 feet. The resolution was adopted by the Board of County Commissioners on 7/21/2026. The applicant is not stated; the requester is Parks, Recreation and Open Spaces. The case file number is 260864. The decision was adopted. Key dates include introduced 5/14/2026, committee forwarded 6/10/2026, and final action 7/21/2026. The business opportunity is the installation of underground electrical utilities for the new Zoo Miami Animal Hospital. Public comment sentiment is not stated.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Adopted
Address:
124000 SW 152 Street, Miami, Florida

ZOO MIAMI ANIMAL HOSPITAL

Miami-Dade County Board of County Commissioners is considering a resolution to grant a non-exclusive underground utility easement to Florida Power and Light Company (FPL). This easement is for the installation of underground electrical facilities to support the new Zoo Miami Animal Hospital. FPL will be responsible for the installation, operation, and maintenance of these facilities. The easement is on a portion of County-owned land within Zoo Miami. The Infrastructure, Innovation & Technology Committee forwarded this item with a favorable recommendation to the Board of County Commissioners.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Forwarded to BCC with a favorable recommendation by the Infrastructure, Innovation & Technology Committee. Status is 'Before the Board'.
Address:
124000 SW 152 Street, Miami, Florida
Applicant:
Florida Power and Light Company (FPL)

ZOO MIAMI ANIMAL HOSPITAL

Miami-Dade County Commission adopted a resolution granting Florida Power and Light Company (FPL) a non-exclusive underground utility easement within Zoo Miami to support the construction of a new Zoo Miami Animal Hospital. The easement allows for the installation, operation, and maintenance of underground electrical facilities. FPL will pay $10.00 for the easement and is responsible for all costs associated with the utility installation and maintenance. The easement area is a portion of County-owned land managed by the Parks, Recreation and Open Spaces (PROS) Department.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Adopted
Address:
124000 SW 152 Street, Miami, Florida
Applicant:
Florida Power and Light Company (FPL)

ZOO MIAMI ANIMAL HOSPITAL

Miami-Dade County Board of County Commissioners is considering a resolution to grant a non-exclusive underground utility easement to Florida Power and Light Company (FPL). This easement is for the installation of underground electrical facilities to support the new Zoo Miami Animal Hospital. The easement will be located within Zoo Miami. The Infrastructure, Innovation & Technology Committee forwarded this item to the Board with a favorable recommendation. FPL will be responsible for the installation, operation, and maintenance of the utilities and will pay a nominal fee of $10.00 for the easement. The easement area is described as a portion of County-owned land within Zoo Miami.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Forwarded to BCC with a favorable recommendation by the Infrastructure, Innovation & Technology Committee. Resolution is before the Board for final action.
Address:
124000 SW 152 Street, Miami, Florida
Applicant:
Florida Power and Light Company (FPL)

ZOO MIAMI ANIMAL HOSPITAL

Miami-Dade County Board of County Commissioners is considering a resolution to grant a non-exclusive underground utility easement to Florida Power and Light Company (FPL). This easement is for the installation of underground electrical facilities to support the new Zoo Miami Animal Hospital. The easement will be located within Zoo Miami. The Infrastructure, Innovation & Technology Committee forwarded the item with a favorable recommendation to the Board of County Commissioners. No public comment is stated in the document.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Forwarded to BCC with a favorable recommendation by the Infrastructure, Innovation & Technology Committee. Status is 'Before the Board'.
Address:
124000 SW 152 Street, Miami, Florida
Applicant:
Florida Power and Light Company (FPL)

ZOO MIAMI ANIMAL HOSPITAL

Miami-Dade County is granting a non-exclusive underground utility easement to Florida Power and Light Company (FPL) for the installation of underground facilities within Zoo Miami. This easement supports the construction of the new Zoo Miami Animal Hospital. FPL will be responsible for the installation, operation, and maintenance of these facilities, paying a nominal $10.00 for the easement. The easement area is a 15-foot by 15-foot portion of county-owned land within Zoo Miami. The Infrastructure, Innovation & Technology Committee forwarded this item to the Board of County Commissioners (BCC) with a favorable recommendation.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Forwarded to BCC with a favorable recommendation
Address:
124000 SW 152 Street, Miami, Florida
Applicant:
Florida Power and Light Company (FPL)

ZOO MIAMI ANIMAL HOSPITAL

Miami-Dade County Board of County Commissioners is considering a resolution to grant a non-exclusive underground utility easement to Florida Power and Light Company (FPL). This easement is for the installation of underground electrical facilities to support the new Zoo Miami Animal Hospital. The easement will be located within Zoo Miami at 124000 SW 152 Street. The Infrastructure, Innovation & Technology Committee forwarded the item to the Board with a favorable recommendation. FPL will be responsible for the installation, operation, and maintenance of the utilities and will pay a nominal $10.00 for the easement. The project involves a 15-foot by 15-foot utility easement area.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Forwarded to BCC with a favorable recommendation by the Infrastructure, Innovation & Technology Committee; pending final action by the Board of County Commissioners.
Address:
124000 SW 152 Street, Miami, Florida
Applicant:
Florida Power and Light Company (FPL)

ZOO MIAMI ANIMAL HOSPITAL

Resolution granting a non-exclusive underground utility easement to Florida Power and Light Company for installation of underground facilities within Zoo Miami in support of the Zoo Miami Hospital. The easement is on a portion of County-owned land within Zoo Miami, located at 124000 SW 152 Street, Miami, Florida, Folio No. 30-5936-000-0050. The easement is 15 feet by 15 feet. The resolution was adopted by the Board of County Commissioners on 7/21/2026. The applicant is not stated; the requester is Parks, Recreation and Open Spaces. The case file number is 260864. The resolution authorizes the County Mayor or designee to execute the easement in exchange for $10.00. The easement is in support of a new Veterinary Animal Hospital to be constructed by PROS within Zoo Miami. The property is in County Commission District 9. The Infrastructure, Innovation & Technology Committee forwarded the item to the BCC with a favorable recommendation on 6/10/2026. The item was introduced on 5/14/2026. No public comment sentiment is stated in the document.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Adopted
Address:
124000 SW 152 Street, Miami, Florida
Applicant:
Not stated; requester is Parks, Recreation and Open Spaces

ZOO MIAMI ANIMAL HOSPITAL

Resolution granting a non-exclusive underground utility easement to Florida Power and Light Company for installation of underground facilities within Zoo Miami in support of the Zoo Miami Hospital. The easement is on a portion of County-owned land within Zoo Miami, located at 124000 SW 152 Street, Miami, Florida, Folio No. 30-5936-000-0050. The easement area is 15 feet by 15 feet. The resolution was adopted by the Board of County Commissioners on 7/21/2026. The applicant is not stated; the requester is Parks, Recreation and Open Spaces. The case file number is 260864, reference R-629-26. The resolution authorizes the County Mayor or designee to execute the easement in exchange for $10.00. The easement is in support of a new Veterinary Animal Hospital to be constructed by PROS within Zoo Miami. The property is in County Commission District 9, represented by Vice Chairman Kionne L. McGhee. The Infrastructure, Innovation & Technology Committee forwarded the item to the BCC with a favorable recommendation on 6/10/2026. No public comment or stakeholder sentiment is stated.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Adopted
Address:
124000 SW 152 Street, Miami, Florida

ZOO MIAMI ANIMAL HOSPITAL

Miami-Dade County Board of County Commissioners is considering a resolution to grant a non-exclusive underground utility easement to Florida Power and Light Company (FPL). This easement is for the installation of underground facilities within Zoo Miami to support the new Zoo Miami Animal Hospital. The Infrastructure, Innovation & Technology Committee recommended forwarding this to the Board of County Commissioners with a favorable recommendation. FPL will be responsible for the installation, operation, and maintenance of the utilities, paying a nominal $10.00 for the easement. The easement area is a portion of county-owned land within Zoo Miami.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Forwarded to BCC with a favorable recommendation
Address:
124000 SW 152 Street, Miami, Florida
Applicant:
Florida Power and Light Company (FPL)

ZOO MIAMI ANIMAL HOSPITAL

Resolution granting a non-exclusive underground utility easement to Florida Power and Light Company for installation of underground facilities within Zoo Miami in support of the Zoo Miami Hospital. The easement is for a 15' by 15' utility easement on a portion of County-owned land. FPL will pay $10.00. The resolution was adopted by the Board of County Commissioners on 7/21/2026. The Infrastructure, Innovation & Technology Committee forwarded it with a favorable recommendation on 6/10/2026. The item was introduced on 5/14/2026. The applicant/requester is Parks, Recreation and Open Spaces. The prime sponsor is Kionne L. McGhee. The County Mayor is Daniella Levine Cava. The resolution authorizes the County Mayor or designee to execute the easement and record it. The easement is in support of a new Veterinary Animal Hospital to be constructed by PROS within Zoo Miami. No public comment or stakeholder sentiment is stated in the document.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Adopted
Address:
124000 SW 152 Street, Miami, Florida
Applicant:
Parks, Recreation and Open Spaces (PROS)

ZOO MIAMI ANIMAL HOSPITAL

Miami-Dade County Board of County Commissioners is considering a resolution to grant a non-exclusive underground utility easement to Florida Power and Light Company (FPL). This easement is for the installation of underground electrical facilities to support the new Zoo Miami Animal Hospital. The easement will be located within Zoo Miami. The Infrastructure, Innovation & Technology Committee forwarded this item to the Board with a favorable recommendation. FPL will be responsible for the installation, operation, and maintenance of the utilities and will pay a nominal sum of $10.00 for the easement. The easement area is described as a 15-foot by 15-foot utility easement.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Forwarded to BCC with a favorable recommendation by the Infrastructure, Innovation & Technology Committee; pending final action by the Board of County Commissioners.
Address:
124000 SW 152 Street, Miami, Florida
Applicant:
Florida Power and Light Company (FPL)

ZOO MIAMI ANIMAL HOSPITAL

Resolution granting a non-exclusive underground utility easement to Florida Power and Light Company for installation of underground facilities within Zoo Miami in support of the Zoo Miami Hospital. The easement is on a portion of County-owned land at 124000 SW 152 Street, Miami, Florida, Folio No. 30-5936-000-0050. The easement is 15 feet by 15 feet. FPL will pay $10.00. The resolution was adopted by the Board of County Commissioners on 7/21/2026. The Infrastructure, Innovation & Technology Committee forwarded it with a favorable recommendation on 6/10/2026. The file number is 260864, reference R-629-26. The applicant is Miami-Dade County Parks, Recreation and Open Spaces, with the County Mayor as the requester. The prime sponsor is Kionne L. McGhee. The property is in County Commission District 9. The easement is for underground electrical utilities, including cables, conduits, and appurtenant equipment, with rights to reconstruct, improve, add to, enlarge, change voltage and size, and remove facilities. The County Mayor or designee is authorized to execute the easement and record it within 30 days of execution. The staff recommendation is to approve. The document does not state any public comment or stakeholder sentiment.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Adopted
Address:
124000 SW 152 Street, Miami, Florida
Applicant:
Miami-Dade County Parks, Recreation and Open Spaces

ZOO MIAMI ANIMAL HOSPITAL

The Board of County Commissioners adopted Resolution R-629-26 granting a non-exclusive underground utility easement to Florida Power and Light Company for the installation of underground facilities within Zoo Miami in support of the Zoo Miami Hospital. The easement is on a portion of County-owned land at 124000 SW 152 Street, Miami, Florida, Folio No. 30-5936-000-0050. The easement is a 15' by 15' wide utility easement for underground electrical utilities. FPL will pay $10.00 for the easement. The resolution was introduced on 5/14/2026, forwarded to the BCC with a favorable recommendation by the Infrastructure, Innovation & Technology Committee on 6/10/2026, and adopted on 7/21/2026. The applicant is Miami-Dade County Parks, Recreation and Open Spaces Department, with the County Mayor as the requester. The case file number is 260864. The resolution authorizes the County Mayor or designee to execute the easement and record it. No public comment or stakeholder sentiment is stated in the document.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Adopted
Address:
124000 SW 152 Street, Miami, Florida
Applicant:
Miami-Dade County Parks, Recreation and Open Spaces Department

ZOO MIAMI ANIMAL HOSPITAL

Miami-Dade County is granting a non-exclusive underground utility easement to Florida Power and Light Company (FPL) for the installation of underground facilities within Zoo Miami. This easement supports the construction of a new Zoo Miami Animal Hospital. FPL will be responsible for the installation, operation, and maintenance of these facilities. The easement is for a 15-foot by 15-foot area. The Infrastructure, Innovation & Technology Committee forwarded this item to the Board of County Commissioners (BCC) with a favorable recommendation. No public comment is stated in the document.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Forwarded to BCC with a favorable recommendation by the Infrastructure, Innovation & Technology Committee. Resolution granting easement is pending BCC approval.
Address:
124000 SW 152 Street, Miami, Florida
Applicant:
Florida Power and Light Company (FPL)

ZOO MIAMI ANIMAL HOSPITAL

Resolution granting a non-exclusive underground utility easement to Florida Power and Light Company for installation of underground facilities within Zoo Miami in support of the Zoo Miami Hospital. The easement is on a portion of County-owned land at 124000 SW 152 Street, Miami, Florida, Folio No. 30-5936-000-0050. The easement is 15 feet by 15 feet. FPL will pay $10.00. The resolution was adopted by the Board of County Commissioners on 7/21/2026. The Infrastructure, Innovation & Technology Committee forwarded it with a favorable recommendation on 6/10/2026. The file number is 260864, reference R-629-26. The applicant/requester is Parks, Recreation and Open Spaces. Prime sponsor is Kionne L. McGhee. The property is in County Commission District 9. The easement is for installation, operation, and maintenance of underground electrical utility facilities, including cables, conduits, and appurtenant equipment, with rights to reconstruct, improve, add to, enlarge, change voltage and size, and remove facilities. The document does not state any public comment or stakeholder sentiment.

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution
Decision:
Adopted
Address:
124000 SW 152 Street, Miami, Florida
Applicant:
Parks, Recreation and Open Spaces (PROS)

ZOO MIAMI ANIMAL HOSPITAL

The Board of County Commissioners adopted Resolution R-629-26, granting a non-exclusive underground utility easement to Florida Power and Light Company for the installation of underground facilities within Zoo Miami in support of the Zoo Miami Hospital. The easement is for a 15'-0

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution

ZOO MIAMI ANIMAL HOSPITAL

Resolution granting a non-exclusive underground utility easement to Florida Power and Light Company for installation of underground facilities within Zoo Miami in support of the Zoo Miami Hospital. The easement is on a portion of County-owned land within Zoo Miami, located at 124000 SW 152 Street, Miami, Florida, Folio No. 30-5936-000-0050. The easement is a 15'-0

Board:
Board of County Commissioners
Date:
2026-07-21
Type:
Resolution

See the actual businesses behind these numbers

Get the real filings, with addresses and officers, backed by a 14-day money-back guarantee.

Create your account