CHANGE ORDER #2 TGSV ENTERPRISES (W-949)
Board of County Commissioners · 2026-09-01 · resolution
Resolution R-752-26 (File Number 261438) ratifies Change Order No. 2 to Contract No. W-949 between Miami-Dade County and TGSV Enterprises Inc. for High Service Pump Station Room Electrical Upgrades at the John E. Preston Water Treatment Plant. The change order is a net-zero monetary reallocation of $2,754,126.76 and grants a 12-calendar-day non-compensable time extension, extending the Final Completion Date from September 28, 2025 to October 10, 2025. The project is completed. The change order funds modifications to motors, VFDs, switchgear, and related components, and includes a phased approach with a future Phase II contract. Adopted on 9/1/2026.