CHANGE ORDER #2 TGSV ENTERPRISES (W-949)
Board of County Commissioners · 2026-09-01 · resolution
Resolution R-752-26, File Number 261438, adopted 9/1/2026, ratifies Change Order No. 2 to Contract W-949 between Miami-Dade County and TGSV Enterprises Inc. for High Service Pump Station Room Electrical Upgrades at the John E. Preston Water Treatment Plant. Change Order No. 2 is a net-zero monetary reallocation of $2,754,126.76 and grants a 12-calendar-day non-compensable time extension, extending the Final Completion Date from September 28, 2025 to October 10, 2025. The Project has been completed. Work includes upsizing motors and VFDs to 1,750 horsepower, switchgear manufacturer modifications, extended guarantees, and water infiltration corrective work. A future Phase II contract will complete remaining electrical installation work.