Infrastructure, Innovation & Technology Committee: July 2026
Miami-Dade County
AWARD TO ITG COMMUNICATIONS FOR S-20298
Miami-Dade County is awarding Contract No. S-20298 for the Venetian Causeway Water Main and Sewer Force Main Relocation to ITG Communications LLC for $3,096,425.02. The project involves relocating existing water and sewer facilities to accommodate the replacement of Bridge No. 2 on the Venetian Causeway. The work includes approximately 1,500 linear feet of HDPE water main and 2,100 linear feet of HDPE force main to be installed via horizontal direction drill under Biscayne Bay. The contract period is 231 calendar days. The project is necessary due to the age and deterioration of the existing bridge structures and infrastructure, which no longer meet current safety requirements. The relocation must be completed before March 2027 to avoid impacting the bridge replacement schedule. ITG Communications LLC was the lowest responsive and responsible bidder, with a bid approximately 44.43% below the Engineer of Record's estimate. No public comment or stakeholder sentiment is stated in the document.
- Board:
- Infrastructure, Innovation & Technology Committee
- Date:
- 2026-07-15
- Type:
- Resolution
- Decision:
- Awarded
- Address:
- 1225 Venetian Causeway, Miami Beach, Florida 33139
- Applicant:
- ITG Communications LLC
AWARD TO ITG COMMUNICATIONS FOR S-20298
Miami-Dade County is awarding Contract No. S-20298 for the Venetian Causeway Water Main and Sewer Force Main Relocation to ITG Communications LLC for $3,096,425.02. The project involves relocating existing water and sewer facilities to accommodate the replacement of Bridge No. 2 on the Venetian Causeway. The work includes approximately 1,500 linear feet of HDPE water main and 2,100 linear feet of HDPE force main to be installed via horizontal direction drill under Biscayne Bay. The contract period is 231 calendar days. The project is necessary due to the age and deterioration of the Venetian Causeway, originally constructed in 1926, and to meet current structural and safety requirements. The relocation must be completed before March 2027 to avoid impacting the bridge replacement schedule. ITG Communications LLC was the lowest responsive and responsible bidder, with their bid being approximately 44.43% below the Engineer of Record's estimate. No public comment or stakeholder sentiment is stated in the document.
- Board:
- Infrastructure, Innovation & Technology Committee
- Date:
- 2026-07-15
- Type:
- Resolution
- Decision:
- Awarded
- Address:
- 1225 Venetian Causeway, Miami Beach, Florida 33139
- Applicant:
- ITG Communications LLC
AWARD TO ITG COMMUNICATIONS FOR S-20298
Miami-Dade County Board of County Commissioners (BCC) is set to award Contract No. S-20298 for the Venetian Causeway Water Main and Sewer Force Main Relocation to ITG Communications LLC. The project involves relocating existing water and sewer facilities to accommodate the replacement of Bridge No. 2 on the Venetian Causeway. The work includes approximately 1,500 linear feet of HDPE water main and 2,100 linear feet of HDPE force main to be installed via horizontal direction drill under Biscayne Bay. The contract amount is $3,096,425.02 with a period of 231 calendar days. The project is funded through WASD Revenue Bonds and other WASD funds, with an estimated annual operations and maintenance cost of $50,000 each. ITG Communications LLC was the lowest responsive and responsible bidder, with no prior county contracts. No public comment or stakeholder sentiment is stated in the document.
- Board:
- Infrastructure, Innovation & Technology Committee
- Date:
- 2026-07-15
- Type:
- Resolution
- Decision:
- Awarded (Resolution)
- Address:
- 1225 Venetian Causeway, Miami Beach, Florida 33139
- Applicant:
- ITG Communications LLC
AWARD TO ITG COMMUNICATIONS FOR S-20298
Miami-Dade County Board of County Commissioners is awarding Contract No. S-20298 for Venetian Causeway Water Main and Sewer Force Main Relocation to ITG Communications LLC. The project involves relocating existing water and sewer facilities to accommodate the replacement of Bridge No. 2 on the Venetian Causeway. The work includes installing approximately 1,500 linear feet of HDPE water main and 2,100 linear feet of HDPE force main via horizontal direction drill under Biscayne Bay. The contract amount is $3,096,425.02 with a contract period of 231 calendar days. The project is funded by WASD Revenue Bonds, Future WASD Revenue Bonds, and Wastewater Renewal and Replacement Fund. ITG Communications LLC was the lowest responsive and responsible bidder, with their bid being approximately 44.43% below the Engineer of Record's estimate. No public comment or stakeholder sentiment was recorded in this document.
- Board:
- Infrastructure, Innovation & Technology Committee
- Date:
- 2026-07-15
- Type:
- Resolution
- Decision:
- Awarded
- Address:
- 1225 Venetian Causeway, Miami Beach, Florida 33139
- Applicant:
- ITG Communications LLC
AWARD TO ITG COMMUNICATIONS FOR S-20298
Miami-Dade County Board of County Commissioners is set to award Contract No. S-20298 for Venetian Causeway Water Main and Sewer Force Main Relocation to ITG Communications LLC. The project involves relocating existing water and sewer facilities to accommodate the replacement of Bridge No. 2 on the Venetian Causeway. The contract amount is $3,096,425.02, with a contract period of 231 calendar days. The work includes approximately 1,500 linear feet of HDPE water main and 2,100 linear feet of HDPE force main to be installed via horizontal direction drill under Biscayne Bay. This project is crucial to avoid impacts on the bridge replacement schedule, which must be completed before March 2027. ITG Communications LLC was the lowest responsive and responsible bidder, with their bid being approximately 44.43% below the Engineer of Record's estimate. The project supports the restoration of the Venetian Causeway, enhancing transportation safety and mobility, while ensuring uninterrupted utility service.
- Board:
- Infrastructure, Innovation & Technology Committee
- Date:
- 2026-07-15
- Type:
- Resolution
- Decision:
- Awarded (Resolution)
- Address:
- 1225 Venetian Causeway, Miami Beach, Florida 33139
- Applicant:
- ITG Communications LLC
AWARD TO ITG COMMUNICATIONS FOR S-20298
Miami-Dade County Board of County Commissioners is set to award Contract No. S-20298 for the Venetian Causeway Water Main and Sewer Force Main Relocation to ITG Communications LLC. The project involves relocating existing water and sewer facilities to accommodate the replacement of Bridge No. 2 on the Venetian Causeway. The work includes approximately 1,500 linear feet of high-density polyethylene (HDPE) water main and 2,100 linear feet of HDPE force main to be installed via horizontal direction drill under Biscayne Bay. The contract amount is $3,096,425.02 with a contract period of 231 calendar days. ITG Communications LLC was the lowest responsive and responsible bidder, with their bid being approximately 44.43% below the Engineer of Record's estimate. No public comment or stakeholder sentiment was noted in the document.
- Board:
- Infrastructure, Innovation & Technology Committee
- Date:
- 2026-07-15
- Type:
- Resolution
- Decision:
- Awarded
- Address:
- 1225 Venetian Causeway, Miami Beach, Florida 33139
- Applicant:
- ITG Communications LLC
AWARD TO ITG COMMUNICATIONS FOR S-20298
Miami-Dade County Board of County Commissioners is awarding Contract No. S-20298 for Venetian Causeway Water Main and Sewer Force Main Relocation to ITG Communications LLC. The project involves relocating existing water and sewer facilities to accommodate the replacement of Bridge No. 2 on the Venetian Causeway. The contract amount is $3,096,425.02, with a contract period of 231 calendar days. The work includes approximately 1,500 linear feet of HDPE water main and 2,100 linear feet of HDPE force main to be installed via horizontal direction drill under Biscayne Bay. The project is funded by WASD Revenue Bonds, Future WASD Revenue Bonds, and Wastewater Renewal and Replacement Fund. ITG Communications LLC was the lowest responsive and responsible bidder, with their bid being approximately 44.3% below the Engineer of Record's estimate. The project supports the restoration of the historic Venetian Causeway and ensures continued utility service to Miami and Miami Beach.
- Board:
- Infrastructure, Innovation & Technology Committee
- Date:
- 2026-07-15
- Type:
- Resolution
- Decision:
- Awarded
- Address:
- 1225 Venetian Causeway, Miami Beach, Florida 33139
- Applicant:
- ITG Communications LLC
AWARD TO ITG COMMUNICATIONS FOR S-20298
Miami-Dade County Board of County Commissioners is awarding Contract No. S-20298 for Venetian Causeway Water Main and Sewer Force Main Relocation to ITG Communications LLC. The project involves relocating existing water and sewer facilities to accommodate the replacement of Bridge No. 2 on the Venetian Causeway. The contract amount is $3,096,425.02, with a contract period of 231 calendar days. The work includes installing approximately 1,500 linear feet of HDPE water main and 2,100 linear feet of HDPE force main via horizontal direction drill under Biscayne Bay. This project is critical to avoid impacts on the bridge replacement schedule, which must be completed before March 2027. ITG Communications LLC was the lowest responsive and responsible bidder, with their bid being approximately 44.43% below the Engineer of Record's estimate. No public comment or stakeholder sentiment is mentioned in the document.
- Board:
- Infrastructure, Innovation & Technology Committee
- Date:
- 2026-07-15
- Type:
- Resolution
- Decision:
- Awarded
- Address:
- 1225 Venetian Causeway, Miami Beach, Florida 33139
- Applicant:
- ITG Communications LLC
AWARD TO ITG COMMUNICATIONS FOR S-20298
Miami-Dade County Board of County Commissioners is set to award Contract No. S-20298 for the Venetian Causeway Water Main and Sewer Force Main Relocation to ITG Communications LLC. The project involves relocating existing water and sewer facilities to accommodate the replacement of Bridge No. 2 on the Venetian Causeway. The work includes approximately 1,500 linear feet of HDPE water main and 2,100 linear feet of HDPE force main to be installed via horizontal direction drill under Biscayne Bay. The contract amount is $3,096,425.02 with a period of 231 calendar days. This project is critical to avoid impacts on the bridge replacement schedule, which must be completed before March 2027. ITG Communications LLC was the lowest responsive and responsible bidder, with their bid being approximately 44.43% below the Engineer of Record's estimate. No public comment or stakeholder sentiment is mentioned in this document.
- Board:
- Infrastructure, Innovation & Technology Committee
- Date:
- 2026-07-15
- Type:
- Resolution
- Decision:
- Awarded (Resolution)
- Address:
- 1225 Venetian Causeway, Miami Beach, Florida 33139
- Applicant:
- ITG Communications LLC
DEWATERING PREQUAL POOL - MOD
Miami-Dade County Board of County Commissioners is considering a resolution to authorize an additional expenditure of $12,879,707.00 for Prequalification Pool No. EVN0000187, which provides dewatering and tank cleaning services for the Water and Sewer Department (WASD). This would bring the total modified cumulative pool amount to $18,896,707.00. The additional funds are needed to maintain operational reliability, regulatory compliance, and environmental protection of water and wastewater treatment facilities, including planned maintenance, emergency repairs, and increased system demand. The pool was initially established on October 3, 2023, and modified on a previous date not specified. The Infrastructure, Innovation & Technology Committee forwarded this item to the BCC with a favorable recommendation on July 15, 2026. The pool expires on November 30, 2028. Prequalified vendors include Envirowaste Services Group, Inc., Flotech Environmental, LLC, Merrell Bros., Inc., Synagro South, LLC, and U.S. Submergent Technologies, LLC.
- Board:
- Infrastructure, Innovation & Technology Committee
- Date:
- 2026-07-15
- Type:
- Resolution
- Decision:
- Pending BCC Assignment
- Applicant:
- Miami-Dade Water and Sewer Department (WASD)
DEWATERING PREQUAL POOL - MOD
Miami-Dade County's Board of County Commissioners is considering a resolution to authorize an additional expenditure of $12,879,707.00 for Prequalification Pool No. EVN0000187, which provides dewatering and tank cleaning services for the Water and Sewer Department (WASD). This would bring the total modified cumulative pool amount to $18,896,707.00. The additional funds are needed to address increased utilization of the pool due to enhanced preventative maintenance, emergency repairs, and regulatory compliance requirements. The pool supports essential services for water and wastewater treatment plant structures, tanks, clarifiers, containment units, and pipelines. The Infrastructure, Innovation & Technology Committee forwarded this item to the Board with a favorable recommendation. The pool was initially established on October 3, 2023, and has been modified previously. The pool expires on November 30, 2028. Prequalified vendors include Envirowaste Services Group, Inc., Flotech Environmental, LLC, Merrell Bros., Inc., Synagro South, LLC, and U.S. Submergent Technologies, LLC.
- Board:
- Infrastructure, Innovation & Technology Committee
- Date:
- 2026-07-15
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation by Infrastructure, Innovation & Technology Committee; pending Board of County Commissioners (BCC) action
- Applicant:
- Miami-Dade Water and Sewer Department (WASD)
DEWATERING PREQUAL POOL - MOD
This legislative item concerns a resolution authorizing additional expenditure authority for Prequalification Pool No. EVN0000187, which provides dewatering and tank cleaning services for the Miami-Dade Water and Sewer Department (WASD). The request is for an additional $12,879,707.00, bringing the total modified cumulative pool amount to $18,896,707.00. These services are critical for maintaining water and wastewater treatment plant structures, tanks, and facilities, ensuring operational reliability, regulatory compliance, and environmental protection. The increased utilization is attributed to enhanced preventative maintenance, response to operational emergencies (such as a temporary dewatering system installation at North District Wastewater Treatment Plant costing over $2 million), and the need to maintain full production during cleaning activities. The pool was initially established on October 3, 2023, and modified on May 15, 2025. The pool expires on November 30, 2028. The item is currently 'In Committee' with an Agenda Date of 9/1/2026.
- Board:
- Infrastructure, Innovation & Technology Committee
- Date:
- 2026-07-15
- Type:
- Resolution
- Decision:
- In Committee
- Applicant:
- Miami-Dade Water and Sewer Department (WASD)
DEWATERING PREQUAL POOL - MOD
Miami-Dade County is seeking to authorize an additional expenditure of $12,879,707.00 for Prequalification Pool No. EVN0000187, which provides dewatering and tank cleaning services for the Water and Sewer Department (WASD). This brings the total modified cumulative pool amount to $18,896,707.00. The services are critical for maintaining water and wastewater treatment plant structures, tanks, and pipelines, ensuring operational reliability, regulatory compliance, and environmental protection. The increased need is attributed to enhanced preventative maintenance, emergency repairs for aging infrastructure, increased system demand, and specific events like the temporary dewatering system installation at the North District Wastewater Treatment Plant. The pool was initially established on October 3, 2023, and modified on an unspecified date in 2025, with a five-year term expiring November 30, 2028. The Infrastructure, Innovation & Technology Committee forwarded the item to the Board of County Commissioners (BCC) with a favorable recommendation on July 15, 2026. The BCC agenda date is September 1, 2026. Any contract award under the pool exceeding $5,000,000.00 requires ratification by the Board.
- Board:
- Infrastructure, Innovation & Technology Committee
- Date:
- 2026-07-15
- Type:
- Resolution
- Decision:
- Pending BCC Assignment / Forwarded to BCC with a favorable recommendation
- Applicant:
- Miami-Dade Water and Sewer Department (WASD)
DEWATERING PREQUAL POOL - MOD
This legislative item concerns a resolution authorizing additional expenditure authority for Prequalification Pool No. EVN0000187, which provides dewatering and tank cleaning services for the Miami-Dade Water and Sewer Department (WASD). The request is for an additional $12,879,707.00, bringing the total modified cumulative pool amount to $18,896,707.00. These services are critical for maintaining water and wastewater treatment plant structures, tanks, and facilities, ensuring operational reliability, regulatory compliance, and environmental protection. The increased utilization is attributed to enhanced preventative maintenance efforts, response to operational emergencies like the Central District Wastewater Treatment Plant's oxygen production system failures, and the need to maintain full production during cleaning activities. The pool was initially established on October 3, 2023, and modified on a later date not specified, with a five-year term. The pool expires on November 30, 2028. The item is currently 'In Committee' with an Agenda Date of 9/1/2026.
- Board:
- Infrastructure, Innovation & Technology Committee
- Date:
- 2026-07-15
- Type:
- Resolution
- Decision:
- In Committee
- Applicant:
- Miami-Dade Water and Sewer Department (WASD)
DEWATERING PREQUAL POOL - MOD
Miami-Dade County's Infrastructure, Innovation & Technology Committee is considering a resolution (File Number: 261158) to authorize an additional expenditure of $12,879,707.00 for Prequalification Pool No. EVN0000187, which provides dewatering and tank cleaning services for the Water and Sewer Department (WASD). This would bring the total modified cumulative pool amount to $18,896,707.00. The additional funds are needed to continue essential services for maintaining water and wastewater treatment plant structures, tanks, clarifiers, containment units, and pipelines, addressing aging infrastructure, increased system demand, and regulatory compliance. A specific instance cited is the temporary dewatering system installed at the North District Wastewater Treatment Plant due to failures at the Central District Wastewater Treatment Plant, which incurred expenditures exceeding $2 million. The pool was initially established on October 3, 2023, and modified on a previous date not specified, with a current value of $6,017,000 and an expiration date of November 30, 2028. The services include tank cleaning, sludge removal, dewatering, vacuum truck services, and hydro-excavation. The request is for WASD, the largest user of the pool. The resolution requires that any contract award under the pool exceeding $5,000,000.00 be ratified by the Board. Prequalified vendors include Envirowaste Services Group, Inc., Flotech Environmental, LLC, Merrell Bros., Inc., Synagro South, LLC, and U.S. Submergent Technologies, LLC. Due diligence was conducted, with a past litigation settlement noted for Synagro South, LLC. The scope of this item is countywide. Public comment is not stated in this document.
- Board:
- Infrastructure, Innovation & Technology Committee
- Date:
- 2026-07-15
- Type:
- Resolution
- Decision:
- In Committee
- Applicant:
- Miami-Dade Water and Sewer Department (WASD)
DEWATERING PREQUAL POOL - MOD
This legislative item concerns a resolution authorizing additional expenditure authority for Prequalification Pool No. EVN0000187, which provides dewatering and tank cleaning services for the Miami-Dade Water and Sewer Department (WASD). The request is for an additional $12,879,707.00, bringing the total modified cumulative pool amount to $18,896,707.00. These services are critical for maintaining water and wastewater treatment plant structures, tanks, and facilities, ensuring operational reliability, regulatory compliance, and environmental protection. The increased utilization is attributed to enhanced preventative maintenance, emergency repairs, and increased system demand, including a specific instance at the North District Wastewater Treatment Plant requiring a temporary dewatering system. The pool was initially established on October 3, 2023, and modified on a previous date not specified, with a five-year term. The pool expires on November 30, 2028. The item is currently 'In Committee' with an Agenda Date of 9/1/2026.
- Board:
- Infrastructure, Innovation & Technology Committee
- Date:
- 2026-07-15
- Type:
- Resolution
- Decision:
- In Committee
- Applicant:
- Miami-Dade Water and Sewer Department (WASD)
DEWATERING PREQUAL POOL - MOD
Miami-Dade County Board of County Commissioners (BCC) is considering a resolution to authorize additional expenditure authority for Prequalification Pool No. EVN0000187, Dewatering and Tank Cleaning Services, for the Water and Sewer Department (WASD). The request is for an additional $12,879,707.00, bringing the total modified cumulative pool amount to $18,896,707.00. This funding is needed to continue essential services for water and wastewater treatment plant maintenance, including tank cleaning, sludge removal, and dewatering, which are critical for operational reliability, regulatory compliance, and environmental protection. The increased utilization is attributed to enhanced preventative maintenance efforts and emergency repairs, such as a temporary dewatering system installed at the North District Wastewater Treatment Plant. The pool was initially established on October 3, 2023, and modified on June 24, 2026. The Infrastructure, Innovation & Technology Committee forwarded this item to the BCC with a favorable recommendation on July 15, 2026. The pool expires on November 30, 2028. Prequalified vendors include Envirowaste Services Group, Inc., Flotech Environmental, LLC, Merrell Bros., Inc., Synagro South, LLC, and U.S. Submergent Technologies, LLC.
- Board:
- Infrastructure, Innovation & Technology Committee
- Date:
- 2026-07-15
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation
- Applicant:
- Miami-Dade Water and Sewer Department (WASD)
DEWATERING PREQUAL POOL - MOD
Miami-Dade County Board of County Commissioners (BCC) is considering a resolution to authorize additional expenditure authority for Prequalification Pool No. EVN0000187, which provides dewatering and tank cleaning services for the Water and Sewer Department (WASD). The request is for an additional $12,879,707.00, bringing the total modified cumulative pool amount to $18,896,707.00. This is needed to continue essential services for water and wastewater treatment facilities, including tank cleaning, sludge removal, and dewatering, due to increased utilization for preventative maintenance and emergency repairs, such as a recent incident at the Central District Wastewater Treatment Plant. The pool was initially established on October 3, 2023, and modified on May 6, 2025. The Infrastructure, Innovation & Technology Committee forwarded the item to the BCC with a favorable recommendation on July 15, 2026. The pool expires on November 30, 2028. Prequalified vendors include Envirowaste Services Group, Inc., Flotech Environmental, LLC, Merrell Bros., Inc., Synagro South, LLC, and U.S. Submergent Technologies, LLC. Public comment is not stated in this document.
- Board:
- Infrastructure, Innovation & Technology Committee
- Date:
- 2026-07-15
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation by Infrastructure, Innovation & Technology Committee; pending BCC Assignment
- Applicant:
- Miami-Dade Water and Sewer Department (WASD)
DEWATERING PREQUAL POOL - MOD
Miami-Dade County Board of County Commissioners is considering a resolution to authorize an additional expenditure of $12,879,707.00 for Prequalification Pool No. EVN0000187, which provides dewatering and tank cleaning services for the Water and Sewer Department (WASD). This would bring the total modified cumulative pool amount to $18,896,707.00. The additional funds are needed to maintain operational reliability, regulatory compliance, and environmental protection of water and wastewater treatment facilities, including planned maintenance, emergency repairs, and increased system demand. The pool was initially established on October 3, 2023, and modified on a previous date not specified. The Infrastructure, Innovation & Technology Committee forwarded this item to the Board with a favorable recommendation on July 15, 2026. The pool expires on November 30, 2028. Prequalified vendors include Envirowaste Services Group, Inc., Flotech Environmental, LLC, Merrell Bros., Inc., Synagro South, LLC, and U.S. Submergent Technologies, LLC.
- Board:
- Infrastructure, Innovation & Technology Committee
- Date:
- 2026-07-15
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation
- Applicant:
- Miami-Dade Water and Sewer Department (WASD)
DEWATERING PREQUAL POOL - MOD
Miami-Dade County is seeking to authorize additional expenditure authority for Prequalification Pool No. EVN0000187, which provides dewatering and tank cleaning services for the Water and Sewer Department (WASD). The request is for an additional $12,879,707.00, bringing the total modified cumulative pool amount to $18,896,707.00. These services are critical for maintaining water and wastewater treatment plant structures, tanks, pipelines, and other facilities, ensuring operational reliability, regulatory compliance, and environmental protection. The increased utilization is attributed to enhanced preventative maintenance efforts, emergency repairs for aging infrastructure, and increased system demand. Specific examples include addressing failures at the Central District Wastewater Treatment Plant (CDWWTP) and supporting cleaning of contact basins at Alexander Orr, Hialeah, and Preston Water Treatment Plants. The pool was initially established on October 3, 2023, and modified on May 6, 2025. Any contract award under the pool exceeding $5,000,000.00 requires ratification by the Board. The Infrastructure, Innovation & Technology Committee forwarded this item to the Board of County Commissioners (BCC) with a favorable recommendation on July 15, 2026. The pool expires on November 30, 2028. Prequalified vendors include Envirowaste Services Group, Inc., Flotech Environmental, LLC, Merrell Bros., Inc., Synagro South, LLC, and U.S. Submergent Technologies, LLC.
- Board:
- Infrastructure, Innovation & Technology Committee
- Date:
- 2026-07-15
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation
- Applicant:
- Miami-Dade Water and Sewer Department (WASD)
DEWATERING PREQUAL POOL - MOD
Miami-Dade County Board of County Commissioners is considering authorizing an additional expenditure of $12,879,707.00 for Prequalification Pool No. EVN0000187, which provides dewatering and tank cleaning services for the Water and Sewer Department (WASD). This would bring the total modified cumulative pool amount to $18,896,707.00. The additional funds are needed to maintain operational reliability, regulatory compliance, and environmental protection for water and wastewater treatment facilities, including cleaning of contact basins at Alexander Orr, Hialeah, and Preston Water Treatment Plants. The pool was initially established on October 3, 2023, and modified on a previous date not specified. The pool expires on November 30, 2028. The Infrastructure, Innovation & Technology Committee forwarded this item to the Board with a favorable recommendation on July 15, 2026. The request is for WASD, the largest user of these services, which are critical for maintaining water and wastewater treatment plant structures, tanks, clarifiers, containment units, pipelines, and other processing facilities. Services include tank cleaning, sludge removal, dewatering, vacuum truck services, and hydro-excavation. The increased utilization is due to enhanced preventative maintenance efforts and response to operational emergencies, such as a temporary dewatering system installed at the North District Wastewater Treatment Plant following failures at the Central District Wastewater Treatment Plant.
- Board:
- Infrastructure, Innovation & Technology Committee
- Date:
- 2026-07-15
- Type:
- Resolution
- Decision:
- Pending BCC Assignment (Before the Board)
- Applicant:
- Miami-Dade Water and Sewer Department (WASD)
DEWATERING PREQUAL POOL - MOD
Miami-Dade County Board of County Commissioners (BCC) is considering authorizing an additional $12,879,707.00 in expenditure authority for Prequalification Pool No. EVN0000187, which provides dewatering and tank cleaning services for the Water and Sewer Department (WASD). This would bring the total modified cumulative pool amount to $18,896,707.00. The additional funds are needed to address WASD's current and anticipated operational needs, including planned maintenance, emergency repairs, increased system demand, and regulatory compliance. The pool was established on October 3, 2023, and modified on a previous date, with a five-year term. The Infrastructure, Innovation & Technology Committee forwarded this item to the BCC with a favorable recommendation on July 15, 2026. The pool is currently valued at $6,017,000.00. The services are critical for maintaining water and wastewater treatment plant structures, tanks, clarifiers, containment units, pipelines, and other facilities. The increased utilization is due to enhanced preventative maintenance efforts and responding to operational emergencies, such as a temporary dewatering system installed at the North District Wastewater Treatment Plant due to failures at the Central District Wastewater Treatment Plant. The funding will also support cleaning of contact basins at the Alexander Orr, Hialeah, and Preston Water Treatment Plants. Prequalified vendors include Envirowaste Services Group, Inc., Flotech Environmental, LLC, Merrell Bros., Inc., Synagro South, LLC, and U.S. Submergent Technologies, LLC. Due diligence was conducted, with a past litigation settlement noted for Synagro South, LLC. The User Access Program and Small Business Enterprise measures may apply to future spot market competitions.
- Board:
- Infrastructure, Innovation & Technology Committee
- Date:
- 2026-07-15
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation
- Applicant:
- Miami-Dade Water and Sewer Department (WASD)
DEWATERING PREQUAL POOL - MOD
This legislative item concerns a resolution authorizing additional expenditure authority for Prequalification Pool No. EVN0000187, which provides dewatering and tank cleaning services for the Miami-Dade Water and Sewer Department (WASD). The request is for an additional $12,879,707.00, bringing the total modified cumulative pool amount to $18,896,707.00. These services are critical for maintaining water and wastewater treatment plant structures, tanks, and facilities, ensuring operational reliability, regulatory compliance, and environmental protection. The increased utilization is attributed to enhanced preventative maintenance, response to operational emergencies like the one at the Central District Wastewater Treatment Plant, and the need to maintain production levels during cleaning activities. The pool was initially established on October 3, 2023, and modified on a previous date not specified, with a five-year term. The pool expires on November 30, 2028. The item is currently 'In Committee' with an Agenda Date of 9/1/2026. The resolution requires that any contract award under the pool exceeding $5,000,000.00 must be ratified by the Board. The scope of this item is countywide.
- Board:
- Infrastructure, Innovation & Technology Committee
- Date:
- 2026-07-15
- Type:
- Resolution
- Decision:
- In Committee
- Applicant:
- Miami-Dade Water and Sewer Department (WASD)
DEWATERING PREQUAL POOL - MOD
Miami-Dade County Board of County Commissioners (BCC) is considering a resolution to authorize additional expenditure authority for Prequalification Pool No. EVN0000187, which provides dewatering and tank cleaning services for the Water and Sewer Department (WASD). The request is for an additional $12,879,707.00, bringing the total modified cumulative pool amount to $18,896,707.00. This is needed to continue essential services for water and wastewater treatment plants, including tank cleaning, sludge removal, and dewatering, due to increased utilization for preventative maintenance and emergency repairs, such as those at the Central District Wastewater Treatment Plant. The pool was initially established on October 3, 2023, and modified on a previous date not specified. The Infrastructure, Innovation & Technology Committee forwarded this item to the BCC with a favorable recommendation on July 15, 2026. The pool expires on November 30, 2028. Prequalified vendors include Envirowaste Services Group, Inc., Flotech Environmental, LLC, Merrell Bros., Inc., Synagro South, LLC, and U.S. Submergent Technologies, LLC. Due diligence was conducted, with a past litigation settlement noted for Synagro South, LLC. The scope of this item is countywide.
- Board:
- Infrastructure, Innovation & Technology Committee
- Date:
- 2026-07-15
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation
- Applicant:
- Miami-Dade Water and Sewer Department (WASD)
DEWATERING PREQUAL POOL - MOD
Miami-Dade County Board of County Commissioners (BCC) is considering a resolution to authorize additional expenditure authority for Prequalification Pool No. EVN0000187, Dewatering and Tank Cleaning Services, for the Water and Sewer Department (WASD). The request is for an additional $12,879,707.00, bringing the total modified cumulative pool amount to $18,896,707.00. This increase is needed to address WASD's current and anticipated operational needs, including planned maintenance, emergency repairs for aging infrastructure, increased system demand, and regulatory compliance. The pool is utilized for essential services such as tank cleaning, sludge removal, dewatering, vacuum truck services, and hydro-excavation to maintain water and wastewater treatment plant structures and facilities. The Infrastructure, Innovation & Technology Committee forwarded this item to the BCC with a favorable recommendation on July 15, 2026. The pool was initially established on October 3, 2023, and modified on a previous date, with a current value of $6,017,000 and an expiration date of November 30, 2028. The increased utilization is attributed to enhanced preventative maintenance efforts and responding to operational emergencies, such as a temporary dewatering system installed at the North District Wastewater Treatment Plant due to failures at the Central District Wastewater Treatment Plant. The scope of this item is countywide. Prequalified vendors include Envirowaste Services Group, Inc., Flotech Environmental, LLC, Merrell Bros., Inc., Synagro South, LLC, and U.S. Submergent Technologies, LLC. Due diligence was conducted, with a past litigation involving Synagro South, LLC resolved through a settlement agreement.
- Board:
- Infrastructure, Innovation & Technology Committee
- Date:
- 2026-07-15
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation
- Applicant:
- Miami-Dade Water and Sewer Department
DEWATERING PREQUAL POOL - MOD
This legislative item concerns a resolution authorizing an additional expenditure of $12,879,707.00 for Prequalification Pool No. EVN0000187, which provides Dewatering and Tank Cleaning Services for the Miami-Dade Water and Sewer Department (WASD). The total modified cumulative pool amount will be $18,896,707.00. The additional funds are needed to maintain operational reliability, regulatory compliance, and environmental protection for water and wastewater treatment facilities, including addressing needs at the Central District Wastewater Treatment Plant and cleaning contact basins at Alexander Orr, Hialeah, and Preston Water Treatment Plants. The pool was initially established on October 3, 2023, and modified on a previous date not specified, with a five-year term expiring November 30, 2028. Any contract award under the pool exceeding $5,000,000.00 requires ratification by the Board. The Infrastructure, Innovation & Technology Committee forwarded this item to the Board of County Commissioners (BCC) with a favorable recommendation on July 15, 2026. The final action date is pending BCC assignment.
- Board:
- Infrastructure, Innovation & Technology Committee
- Date:
- 2026-07-15
- Type:
- Resolution
- Decision:
- Pending BCC Assignment (Forwarded to BCC with a favorable recommendation by committee)
- Applicant:
- Miami-Dade Water and Sewer Department (WASD)
DEWATERING PREQUAL POOL - MOD
Miami-Dade County's Infrastructure, Innovation & Technology Committee is considering a resolution to authorize an additional $12,879,707.00 in expenditure authority for Prequalification Pool No. EVN0000187, which provides dewatering and tank cleaning services for the Water and Sewer Department (WASD). This would bring the total modified cumulative pool amount to $18,896,707.00. The additional funds are needed to address current and anticipated operational needs, including planned maintenance, emergency repairs for aging infrastructure, increased system demand, and regulatory compliance. The pool is utilized by multiple county departments, but this request is specifically for WASD, the largest user. The services are critical for maintaining water and wastewater treatment plant structures, tanks, clarifiers, containment units, pipelines, and other processing facilities. A specific example cited is the need for a temporary dewatering system at the North District Wastewater Treatment Plant due to failures at the Central District Wastewater Treatment Plant, which incurred expenditures exceeding $2 million. The pool was established on October 3, 2023, and modified on a previous date, with a five-year term expiring November 30, 2028. Any contract award under the pool exceeding $5,000,000.00 requires ratification by the Board. The document lists five prequalified vendors: Envirowaste Services Group, Inc., Flotech Environmental, LLC, Merrell Bros., Inc., Synagro South, LLC, and U.S. Submergent Technologies, LLC. Due diligence was conducted, with one vendor, Synagro South, LLC, having a past litigation resolved through a settlement agreement.
- Board:
- Infrastructure, Innovation & Technology Committee
- Date:
- 2026-07-15
- Type:
- Resolution
- Decision:
- In Committee
- Applicant:
- Miami-Dade Water and Sewer Department (WASD)
DEWATERING PREQUAL POOL - MOD
Miami-Dade County Board of County Commissioners is considering a resolution to authorize an additional expenditure of $12,879,707.00 for Prequalification Pool No. EVN0000187, which provides dewatering and tank cleaning services for the Water and Sewer Department (WASD). This brings the total modified cumulative pool amount to $18,896,707.00. The additional funds are needed to maintain operational reliability, regulatory compliance, and environmental protection of water and wastewater treatment facilities, including addressing needs at the Central District Wastewater Treatment Plant and cleaning contact basins at Alexander Orr, Hialeah, and Preston Water Treatment Plants. The Infrastructure, Innovation & Technology Committee forwarded this item to the Board with a favorable recommendation. The pool was originally established on October 3, 2023, and modified on a previous date not specified, with a current value of $6,017,000 and an expiration date of November 30, 2028. Any contract award under the pool exceeding $5,000,000.00 requires ratification by the Board. Prequalified vendors include Envirowaste Services Group, Inc., Flotech Environmental, LLC, Merrell Bros., Inc., Synagro South, LLC, and U.S. Submergent Technologies, LLC.
- Board:
- Infrastructure, Innovation & Technology Committee
- Date:
- 2026-07-15
- Type:
- Resolution
- Decision:
- Pending BCC Assignment (Before the Board)
- Applicant:
- Miami-Dade Water and Sewer Department (WASD)
DEWATERING PREQUAL POOL - MOD
This legislative item concerns a resolution authorizing additional expenditure authority for Prequalification Pool No. EVN0000187, which provides dewatering and tank cleaning services for the Miami-Dade Water and Sewer Department (WASD). The request is for an additional $12,879,707.00, bringing the total modified cumulative pool amount to $18,896,707.00. These services are critical for maintaining water and wastewater treatment plant structures, tanks, and facilities, ensuring operational reliability, regulatory compliance, and environmental protection. The increased utilization is attributed to enhanced preventative maintenance, response to operational emergencies (such as a temporary dewatering system at the North District Wastewater Treatment Plant costing over $2 million), and the need to maintain production levels during cleaning activities. The pool was initially established on October 3, 2023, and modified on June 24, 2026. The item is currently 'In Committee' with an Agenda Date of September 1, 2026. The pool expires on November 30, 2028. Prequalified vendors include Envirowaste Services Group, Inc., Flotech Environmental, LLC, Merrell Bros., Inc., Synagro South, LLC, and U.S. Submergent Technologies, LLC.
- Board:
- Infrastructure, Innovation & Technology Committee
- Date:
- 2026-07-15
- Type:
- Resolution
- Decision:
- In Committee
- Applicant:
- Miami-Dade Water and Sewer Department (WASD)
DEWATERING PREQUAL POOL - MOD
Miami-Dade County is seeking to authorize additional expenditure authority for Prequalification Pool No. EVN0000187, which provides dewatering and tank cleaning services for the Water and Sewer Department (WASD). The request is for an additional $12,879,707.00, bringing the total modified cumulative pool amount to $18,896,707.00. This is to address WASD's current and anticipated operational needs, including planned maintenance, emergency repairs for aging infrastructure, increased system demand, and regulatory compliance. The pool was established on October 3, 2023, and modified on a previous date, with a current value of $6,017,000. The pool expires on November 30, 2028. The Infrastructure, Innovation & Technology Committee forwarded this item to the Board of County Commissioners (BCC) with a favorable recommendation on July 15, 2026. The BCC is scheduled to consider this on September 1, 2026. Prequalified vendors include Envirowaste Services Group, Inc., Flotech Environmental, LLC, Merrell Bros., Inc., Synagro South, LLC, and U.S. Submergent Technologies, LLC. Due diligence was conducted, with one exception noted regarding Synagro South, LLC's prior litigation which was resolved via settlement.
- Board:
- Infrastructure, Innovation & Technology Committee
- Date:
- 2026-07-15
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation by the Infrastructure, Innovation & Technology Committee; pending BCC decision
- Applicant:
- Miami-Dade Water and Sewer Department (WASD)
DEWATERING PREQUAL POOL - MOD
Miami-Dade County's Infrastructure, Innovation & Technology Committee is considering a resolution to authorize an additional expenditure of $12,879,707.00 for Prequalification Pool No. EVN0000187, which provides dewatering and tank cleaning services for the Water and Sewer Department (WASD). This would bring the total modified cumulative pool amount to $18,896,707.00. The additional funds are needed to cover current and anticipated operational needs, including planned maintenance, emergency repairs for aging infrastructure, increased system demand, and regulatory compliance. A specific example cited is the need for a temporary dewatering system at the North District Wastewater Treatment Plant due to failures at the Central District Wastewater Treatment Plant, which incurred expenditures exceeding $2 million. The pool was initially established on October 3, 2023, and modified on a later date not specified, with a current value of $6,017,000. The pool expires on November 30, 2028. Contract awards under the pool exceeding $5,000,000.00 require ratification by the Board. Prequalified vendors include Envirowaste Services Group, Inc., Flotech Environmental, LLC, Merrell Bros., Inc., Synagro South, LLC, and U.S. Submergent Technologies, LLC. Due diligence was conducted, with one exception noted regarding a resolved litigation with Synagro South, LLC. The User Access Program and Small Business Enterprise measures apply where permitted, and Local Preference will be applied at the time of spot market competition. The Living Wage Ordinance does not apply.
- Board:
- Infrastructure, Innovation & Technology Committee
- Date:
- 2026-07-15
- Type:
- Resolution
- Decision:
- In Committee
- Applicant:
- Miami-Dade Water and Sewer Department (WASD)
DEWATERING PREQUAL POOL - MOD
This legislative item concerns a resolution authorizing additional expenditure authority for Prequalification Pool No. EVN0000187, which provides dewatering and tank cleaning services for the Miami-Dade Water and Sewer Department (WASD). The request is for an additional $12,879,707.00, bringing the total modified cumulative pool amount to $18,896,707.00. These services are critical for maintaining water and wastewater treatment plant structures, tanks, and facilities, ensuring operational reliability, regulatory compliance, and environmental protection. The increased utilization is attributed to enhanced preventative maintenance, response to operational emergencies like the one at the Central District Wastewater Treatment Plant, and the need to maintain full production during cleaning activities. The pool was initially established on October 3, 2023, and modified on a previous date. The pool expires on November 30, 2028. The item is currently 'In Committee' with an Agenda Date of 9/1/2026.
- Board:
- Infrastructure, Innovation & Technology Committee
- Date:
- 2026-07-15
- Type:
- Resolution
- Decision:
- In Committee
- Applicant:
- Miami-Dade Water and Sewer Department (WASD)
DEWATERING PREQUAL POOL - MOD
This legislative item concerns a resolution authorizing an additional expenditure of $12,879,707.00 for Prequalification Pool No. EVN0000187, which provides dewatering and tank cleaning services for the Miami-Dade Water and Sewer Department (WASD). The total modified cumulative pool amount will be $18,896,707.00. The additional funds are needed to maintain operational reliability, regulatory compliance, and environmental protection of water and wastewater treatment facilities, including addressing emergency repairs and increased system demand. The pool was initially established on October 3, 2023, and modified on a previous date. The Infrastructure, Innovation & Technology Committee forwarded this item to the Board of County Commissioners (BCC) with a favorable recommendation on July 15, 2026. The BCC agenda date is September 1, 2026. The services include tank cleaning, sludge removal, dewatering, and vacuum truck services. Specific cleaning of 10 contact basins at the Alexander Orr, Hialeah, and Preston Water Treatment Plants is also supported by this funding. The pool expires on November 30, 2028. Prequalified vendors include Envirowaste Services Group, Inc., Flotech Environmental, LLC, Merrell Bros., Inc., Synagro South, LLC, and U.S. Submergent Technologies, LLC.
- Board:
- Infrastructure, Innovation & Technology Committee
- Date:
- 2026-07-15
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation
- Applicant:
- Miami-Dade Water and Sewer Department (WASD)
DEWATERING PREQUAL POOL - MOD
This legislative item concerns a resolution authorizing additional expenditure authority for Prequalification Pool No. EVN0000187, which provides dewatering and tank cleaning services for the Miami-Dade Water and Sewer Department (WASD). The request is for an additional $12,879,707.00, bringing the total modified cumulative pool amount to $18,896,707.00. These services are critical for maintaining water and wastewater treatment plant structures, tanks, and facilities, ensuring operational reliability, regulatory compliance, and environmental protection. The increased utilization is attributed to enhanced preventative maintenance, emergency repairs, and increased system demand. The pool was initially established on October 3, 2023, and modified on a previous date not specified in this document. The pool expires on November 30, 2028. The item is currently 'In Committee' with an Agenda Date of 9/1/2026.
- Board:
- Infrastructure, Innovation & Technology Committee
- Date:
- 2026-07-15
- Type:
- Resolution
- Decision:
- In Committee
- Applicant:
- Miami-Dade Water and Sewer Department (WASD)
DEWATERING PREQUAL POOL - MOD
Miami-Dade County Board of County Commissioners is considering a resolution to authorize an additional expenditure of $12,879,707.00 for Prequalification Pool No. EVN0000187, which provides dewatering and tank cleaning services for the Water and Sewer Department (WASD). This would bring the total modified cumulative pool amount to $18,896,707.00. The additional funds are needed to maintain operational reliability, regulatory compliance, and environmental protection of water and wastewater treatment facilities, including cleaning of contact basins at Alexander Orr, Hialeah, and Preston Water Treatment Plants. The pool was initially established on October 3, 2023, and modified on a previous date not specified. The Infrastructure, Innovation & Technology Committee forwarded this item to the Board with a favorable recommendation on July 15, 2026. The pool expires on November 30, 2028. Prequalified vendors include Envirowaste Services Group, Inc., Flotech Environmental, LLC, Merrell Bros., Inc., Synagro South, LLC, and U.S. Submergent Technologies, LLC.
- Board:
- Infrastructure, Innovation & Technology Committee
- Date:
- 2026-07-15
- Type:
- Resolution
- Decision:
- Pending BCC Assignment (Forwarded to BCC with a favorable recommendation by committee)
- Applicant:
- Water and Sewer Department (WASD)
DEWATERING PREQUAL POOL - MOD
Miami-Dade County's Infrastructure, Innovation & Technology Committee is considering a resolution (File Number: 261158) to authorize an additional $12,879,707.00 in expenditure authority for Prequalification Pool No. EVN0000187, which provides dewatering and tank cleaning services for the Water and Sewer Department (WASD). This increases the total modified cumulative pool amount to $18,896,707.00. The additional funds are needed to cover increased utilization of the pool for essential maintenance, emergency repairs, and regulatory compliance at water and wastewater treatment facilities, including specific cleaning of contact basins at Alexander Orr, Hialeah, and Preston Water Treatment Plants. A previous incident at the Central District Wastewater Treatment Plant required a temporary dewatering system, costing over $2 million. Any contract award under this pool exceeding $5,000,000.00 requires ratification by the Board. The pool was established on October 3, 2023, and modified on an unspecified date in 2025, with a current expiration date of November 30, 2028.
- Board:
- Infrastructure, Innovation & Technology Committee
- Date:
- 2026-07-15
- Type:
- Resolution
- Decision:
- In Committee
- Applicant:
- Miami-Dade Water and Sewer Department (WASD)
DEWATERING PREQUAL POOL - MOD
Miami-Dade County's Infrastructure, Innovation & Technology Committee is considering a resolution to authorize an additional $12,879,707.00 in expenditure authority for Prequalification Pool No. EVN0000187, which provides dewatering and tank cleaning services for the Water and Sewer Department (WASD). This would bring the total modified cumulative pool amount to $18,896,707.00. The additional funds are needed to address WASD's operational needs, including preventative maintenance, emergency repairs, and regulatory compliance, due to higher-than-anticipated utilization. A specific example cited is the need for a temporary dewatering system at the North District Wastewater Treatment Plant, which incurred costs exceeding $2 million. The pool was initially established on October 3, 2023, and modified on a previous date not specified, with a five-year term. Any contract award under this pool exceeding $5,000,000.00 requires ratification by the Board. The scope of this item is countywide. Prequalified vendors include Envirowaste Services Group, Inc., Flotech Environmental, LLC, Merrell Bros., Inc., Synagro South, LLC, and U.S. Submergent Technologies, LLC. Due diligence was conducted, with a past litigation settlement noted for Synagro South, LLC. The User Access Program applies where permitted, and Small Business Enterprise measures will be determined prior to advertising spot market competitions.
- Board:
- Infrastructure, Innovation & Technology Committee
- Date:
- 2026-07-15
- Type:
- Resolution
- Decision:
- In Committee
- Applicant:
- Miami-Dade Water and Sewer Department (WASD)
DEWATERING PREQUAL POOL - MOD
This legislative item concerns a resolution authorizing an additional expenditure of $12,879,707.00 for Prequalification Pool No. EVN0000187, which provides dewatering and tank cleaning services for the Miami-Dade Water and Sewer Department (WASD). The total modified cumulative pool amount will be $18,896,707.00. The additional funds are needed to address WASD's current and anticipated operational needs, including preventative maintenance, emergency repairs, and regulatory compliance for water and wastewater treatment facilities. The pool was initially established on October 3, 2023, and modified on May 15, 2025. The services include tank cleaning, sludge removal, dewatering, and vacuum truck services. The request was forwarded to the Board of County Commissioners (BCC) with a favorable recommendation from the Infrastructure, Innovation & Technology Committee on July 15, 2026. The pool expires on November 30, 2028. Prequalified vendors include Envirowaste Services Group, Inc., Flotech Environmental, LLC, Merrell Bros., Inc., Synagro South, LLC, and U.S. Submergent Technologies, LLC.
- Board:
- Infrastructure, Innovation & Technology Committee
- Date:
- 2026-07-15
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation
- Applicant:
- Miami-Dade Water and Sewer Department (WASD)
DEWATERING PREQUAL POOL - MOD
Miami-Dade County's Infrastructure, Innovation & Technology Committee is considering a resolution to authorize an additional expenditure of $12,879,707.00 for Prequalification Pool No. EVN0000187, which provides dewatering and tank cleaning services for the Water and Sewer Department (WASD). This would bring the total modified cumulative pool amount to $18,896,707.00. The additional funds are needed to cover increased utilization of the pool for essential maintenance, emergency repairs, and regulatory compliance at water and wastewater treatment facilities, including specific cleaning of contact basins at Alexander Orr, Hialeah, and Preston Water Treatment Plants. A past incident at the Central District Wastewater Treatment Plant involving a temporary dewatering system cost over $2 million. Any contract award under this pool exceeding $5,000,000.00 requires ratification by the Board. The pool was initially established on October 3, 2023, and is set to expire on November 30, 2028. Prequalified vendors include Envirowaste Services Group, Inc., Flotech Environmental, LLC, Merrell Bros., Inc., Synagro South, LLC, and U.S. Submergent Technologies, LLC.
- Board:
- Infrastructure, Innovation & Technology Committee
- Date:
- 2026-07-15
- Type:
- Resolution
- Decision:
- In Committee
- Applicant:
- Miami-Dade Water and Sewer Department (WASD)
DEWATERING PREQUAL POOL - MOD
This legislative item concerns a resolution authorizing an additional expenditure of $12,879,707.00 for Prequalification Pool No. EVN0000187, which provides dewatering and tank cleaning services for the Miami-Dade Water and Sewer Department (WASD). The total modified cumulative pool amount will be $18,896,707.00. The additional funds are needed to maintain operational reliability, regulatory compliance, and environmental protection for water and wastewater treatment facilities, including addressing needs at the Central District Wastewater Treatment Plant and cleaning contact basins at Alexander Orr, Hialeah, and Preston Water Treatment Plants. The pool was initially established on October 3, 2023, and modified on May 15, 2025. The Infrastructure, Innovation & Technology Committee forwarded this item to the Board of County Commissioners (BCC) with a favorable recommendation on July 15, 2026. The BCC is scheduled to consider this item on September 1, 2026.
- Board:
- Infrastructure, Innovation & Technology Committee
- Date:
- 2026-07-15
- Type:
- Resolution
- Decision:
- Pending BCC Assignment (Forwarded to BCC with a favorable recommendation by Infrastructure, Innovation & Technology Committee)
- Applicant:
- Miami-Dade Water and Sewer Department (WASD)
DEWATERING PREQUAL POOL - MOD
This legislative item concerns a resolution authorizing an additional expenditure of $12,879,707.00 for Prequalification Pool No. EVN0000187, which provides dewatering and tank cleaning services for the Miami-Dade Water and Sewer Department (WASD). The total modified cumulative pool amount will be $18,896,707.00. The additional funds are needed to maintain operational reliability, regulatory compliance, and environmental protection for water and wastewater treatment facilities, including addressing needs at the Central District Wastewater Treatment Plant and cleaning contact basins at Alexander Orr, Hialeah, and Preston Water Treatment Plants. The pool was initially established on October 3, 2023, and modified on a previous date, with a current value of $6,017,000. The pool expires on November 30, 2028. The Infrastructure, Innovation & Technology Committee forwarded this item to the Board of County Commissioners (BCC) with a favorable recommendation on July 15, 2026. The BCC is scheduled to consider this item on September 1, 2026.
- Board:
- Infrastructure, Innovation & Technology Committee
- Date:
- 2026-07-15
- Type:
- Resolution
- Decision:
- Pending BCC Assignment (Favorable recommendation from committee)
- Applicant:
- Miami-Dade Water and Sewer Department (WASD)
DEWATERING PREQUAL POOL - MOD
Miami-Dade County's Infrastructure, Innovation & Technology Committee is considering a resolution to authorize an additional $12,879,707.00 in expenditure authority for Prequalification Pool No. EVN0000187, which provides dewatering and tank cleaning services for the Water and Sewer Department (WASD). This would bring the total modified cumulative pool amount to $18,896,707.00. The additional funds are needed to continue essential services for maintaining water and wastewater treatment plant structures, tanks, clarifiers, containment units, and pipelines, addressing increased utilization due to enhanced preventative maintenance and emergency repairs, such as a temporary dewatering system installed at the North District Wastewater Treatment Plant. The pool was initially established on October 3, 2023, and modified on a previous date not specified. Any contract award under the pool exceeding $5,000,000.00 requires ratification by the Board. The pool expires on November 30, 2028. Prequalified vendors include Envirowaste Services Group, Inc., Flotech Environmental, LLC, Merrell Bros., Inc., Synagro South, LLC, and U.S. Submergent Technologies, LLC.
- Board:
- Infrastructure, Innovation & Technology Committee
- Date:
- 2026-07-15
- Type:
- Resolution
- Decision:
- In Committee
- Applicant:
- Miami-Dade Water and Sewer Department (WASD)
DEWATERING PREQUAL POOL - MOD
Miami-Dade County is seeking to authorize an additional expenditure of $12,879,707.00 for Prequalification Pool No. EVN0000187, which provides dewatering and tank cleaning services for the Water and Sewer Department (WASD). This brings the total modified cumulative pool amount to $18,896,707.00. The services are critical for maintaining water and wastewater treatment plant structures, tanks, clarifiers, containment units, and pipelines, ensuring operational reliability, regulatory compliance, and environmental protection. The increased need is attributed to enhanced preventative maintenance, emergency repairs for aging infrastructure, increased system demand, and regulatory compliance requirements, including cleaning of contact basins at Alexander Orr, Hialeah, and Preston Water Treatment Plants. The pool was initially established on October 3, 2023, and modified on June 24, 2025, with a five-year term. The Infrastructure, Innovation & Technology Committee forwarded this item to the Board of County Commissioners (BCC) with a favorable recommendation on July 15, 2026. The BCC agenda date is September 1, 2026.
- Board:
- Infrastructure, Innovation & Technology Committee
- Date:
- 2026-07-15
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation by Infrastructure, Innovation & Technology Committee; Pending BCC Assignment
- Applicant:
- Miami-Dade Water and Sewer Department (WASD)
DEWATERING PREQUAL POOL - MOD
This legislative item concerns a resolution authorizing an additional expenditure of $12,879,707.00 for Prequalification Pool No. EVN0000187, which provides dewatering and tank cleaning services for the Miami-Dade Water and Sewer Department (WASD). The total modified cumulative pool amount will be $18,896,707.00. The additional funds are needed to maintain operational reliability, regulatory compliance, and environmental protection for water and wastewater treatment facilities, including addressing needs at the Central District Wastewater Treatment Plant and cleaning contact basins at Alexander Orr, Hialeah, and Preston Water Treatment Plants. The pool was initially established on October 3, 2023, and modified on May 15, 2025. The Infrastructure, Innovation & Technology Committee forwarded this item to the Board of County Commissioners (BCC) with a favorable recommendation on July 15, 2026. The BCC is scheduled to consider this item on September 1, 2026.
- Board:
- Infrastructure, Innovation & Technology Committee
- Date:
- 2026-07-15
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation by Infrastructure, Innovation & Technology Committee; Pending BCC Assignment
- Applicant:
- Miami-Dade Water and Sewer Department (WASD)
DISCUSSION ITEM REGARDING THE PROPOSED FY 2026-27 BUDGET
This is a discussion item regarding the proposed FY 2026-27 Budget, with presentations from several departments including Communication, Information and Technology; Solid Waste Management; Miami-Dade Water and Sewer; People and Internal Operations; and Regulatory and Economic Resources. The item is currently in committee. No specific project details, applicant, or decision are stated.
- Board:
- Infrastructure, Innovation & Technology Committee
- Date:
- 2026-07-15
- Type:
- Legislation
- Decision:
- In Committee
DISCUSSION ITEM REGARDING THE PROPOSED FY 2026-27 BUDGET
This legislative item is a discussion regarding the proposed FY 2026-27 Budget, featuring presentations from several Miami-Dade County departments including Communication, Information and Technology; Solid Waste Management; Water and Sewer; People and Internal Operations; and Regulatory and Economic Resources. The item is currently in committee. No specific project details, addresses, or zoning changes are mentioned as it pertains to the overall budget discussion.
- Board:
- Infrastructure, Innovation & Technology Committee
- Date:
- 2026-07-15
- Type:
- Legislation
- Decision:
- In Committee
DISCUSSION ITEM REGARDING THE PROPOSED FY 2026-27 BUDGET
This is a discussion item regarding the proposed FY 2026-27 budget for Miami-Dade County. Presentations are scheduled from several departments, including Communication, Information and Technology; Solid Waste Management; Water and Sewer; People and Internal Operations; and Regulatory and Economic Resources. The item is currently in committee.
- Board:
- Infrastructure, Innovation & Technology Committee
- Date:
- 2026-07-15
- Type:
- Legislation
- Decision:
- In Committee
DISCUSSION ITEM REGARDING THE PROPOSED FY 2026-27 BUDGET
This is a discussion item regarding the proposed FY 2026-27 Budget. Presentations are scheduled from several departments, including Communication, Information and Technology; Solid Waste Management; Miami-Dade Water and Sewer; People and Internal Operations; and Regulatory and Economic Resources. The item is currently in committee.
- Board:
- Infrastructure, Innovation & Technology Committee
- Date:
- 2026-07-15
- Type:
- Legislation
- Decision:
- In Committee
DISCUSSION ITEM REGARDING THE PROPOSED FY 2026-27 BUDGET
This is a discussion item regarding the proposed FY 2026-27 Budget, with presentations from several departments including Communication, Information and Technology; Solid Waste Management; Miami-Dade Water and Sewer; People and Internal Operations; and Regulatory and Economic Resources. The item is currently in committee.
- Board:
- Infrastructure, Innovation & Technology Committee
- Date:
- 2026-07-15
- Type:
- Legislation
- Decision:
- In Committee
DISCUSSION ITEM REGARDING THE PROPOSED FY 2026-27 BUDGET
This legislative item is a discussion regarding the proposed FY 2026-27 budget, with presentations from multiple departments including Communication, Information and Technology; Solid Waste Management; Miami-Dade Water and Sewer; People and Internal Operations; and Regulatory and Economic Resources. The item is currently in committee.
- Board:
- Infrastructure, Innovation & Technology Committee
- Date:
- 2026-07-15
- Type:
- Legislation
- Decision:
- In Committee
See the actual businesses behind these numbers
Get the real filings, with addresses and officers, free for 7 days. No credit card required.
Start your free trial