Transportation Cmte: July 2026
Miami-Dade County
OFF-SYSTEM AGREEMENT FOR LOCAL ROADWAY IMPROVEMENTS
Miami-Dade County Board of County Commissioners (BCC) is set to approve an Off-System Construction and Maintenance Agreement with the Florida Department of Transportation (FDOT) for local roadway improvements along SR 934/NW 74th Street Connector from west of NW 77th Court to east of Red Road. The project, with an estimated cost of $5,900,000, will be funded and built by FDOT, with an anticipated construction start date of March 2027. Improvements include reconstruction of sidewalks, curb ramps, milling and resurfacing, widening, striping, traffic separators, and signage. The County will be responsible for maintenance operations upon project completion. The Transportation Committee forwarded the item to the BCC with a favorable recommendation.
- Board:
- Transportation Cmte
- Date:
- 2026-07-14
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation by Transportation Committee; awaiting BCC approval
- Address:
- SR 934/NW 74th Street Connector from west of NW 77th Court to east of Red Road, including work on NW 74th Street Connector and NW 72nd Avenue
- Applicant:
- Florida Department of Transportation (FDOT) and Miami-Dade County
OFF-SYSTEM AGREEMENT FOR LOCAL ROADWAY IMPROVEMENTS
Miami-Dade County Board of County Commissioners resolution approving an Off-System Construction and Maintenance Agreement with the Florida Department of Transportation for local roadway improvements on SR 934/NW 74th Street Connector from west of NW 77th Court to east of Red Road, including work on NW 74th Street Connector and NW 72nd Avenue. The project is estimated to cost $5,900,000, funded and built by FDOT, with an anticipated construction start date of March 2027. The Transportation Committee forwarded the item to the BCC with a favorable recommendation on 7/14/2026. The BCC agenda date is 9/1/2026. The County is required to provide maintenance operations within the County's right-of-way upon completion. Improvements include curb ramps, sidewalk, curb and gutter, milling and resurfacing, widening, striping, traffic separator, loops, and signage. The project is in Districts 6 and 12. The County Mayor or designee is authorized to execute the agreement.
- Board:
- Transportation Cmte
- Date:
- 2026-07-14
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation by Transportation Committee on 7/14/2026; pending BCC action on 9/1/2026
- Address:
- SR 934/NW 74th Street Connector from west of NW 77th Court to east of Red Road; a portion includes work on NW 74th Street Connector and NW 72nd Avenue
- Applicant:
- Miami-Dade County and Florida Department of Transportation
OFF-SYSTEM AGREEMENT FOR LOCAL ROADWAY IMPROVEMENTS
Miami-Dade County Board of County Commissioners is considering an Off-System Construction and Maintenance Agreement with the Florida Department of Transportation (FDOT) for roadway improvements on SR 934/NW 74th Street Connector from west of NW 77th Court to east of Red Road. The project includes work on NW 74th Street Connector and NW 72nd Avenue. Specific improvements include reconstruction of sidewalks, curb ramps, curb and gutter, milling and resurfacing, widening, striping, traffic separators, loops, and signage. The project is estimated to cost $5,900,000, funded and built by FDOT, with an anticipated construction start date of March 2027. Miami-Dade County will be responsible for maintenance operations upon project completion, funded through DTPW's General Fund allocation. The Transportation Committee forwarded the item to the Board with a favorable recommendation.
- Board:
- Transportation Cmte
- Date:
- 2026-07-14
- Type:
- Resolution
- Decision:
- Pending BCC Assignment, Forwarded to BCC with a favorable recommendation by Transportation Cmte
- Address:
- SR 934/NW 74th Street Connector from west of NW 77th Court to east of Red Road, including work on NW 74th Street Connector and NW 72nd Avenue
- Applicant:
- Miami-Dade County and Florida Department of Transportation
OFF-SYSTEM AGREEMENT FOR LOCAL ROADWAY IMPROVEMENTS
Resolution approving an Off-System Construction and Maintenance Agreement between Miami-Dade County and the Florida Department of Transportation for local roadway improvements for SR 934/NW 74th Street Connector from west of NW 77th Court to east of Red Road, with a portion of the project including work on NW 74th Street Connector and NW 72nd Avenue. The project is estimated to cost $5,900,000, funded and built by FDOT, with an anticipated construction start date of March 2027. The Transportation Committee forwarded it to the BCC with a favorable recommendation on 7/14/2026, and the agenda date is 9/1/2026. The County is required to provide maintenance operations within the County's right-of-way upon completion. Improvements include curb ramps, sidewalk, curb and gutter, milling and resurfacing, widening, striping, traffic separator, loops, and signage. If additional right-of-way is required, FDOT shall acquire it at no cost to the County.
- Board:
- Transportation Cmte
- Date:
- 2026-07-14
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation by Transportation Cmte on 7/14/2026; pending BCC assignment
- Address:
- SR 934/NW 74th Street Connector from west of NW 77th Court to east of Red Road; a portion includes work on NW 74th Street Connector and NW 72nd Avenue, Miami-Dade County, Florida
- Applicant:
- Miami-Dade County and Florida Department of Transportation
OFF-SYSTEM AGREEMENT FOR LOCAL ROADWAY IMPROVEMENTS
Miami-Dade County Board of County Commissioners is considering an Off-System Construction and Maintenance Agreement between Miami-Dade County and the Florida Department of Transportation (FDOT) for local roadway improvements. The project, identified as Project No. FM452566-1-52-01, involves SR 934/NW 74th Street Connector from west of NW 77th Court to east of Red Road, including work on NW 74th Street Connector and NW 72nd Avenue. Specific improvements include reconstruction of sidewalks, curb ramps, curb and gutter, milling and resurfacing, widening, striping, traffic separators, loops, and signage. The project is estimated to cost $5,900,000 and will be funded and built by FDOT. The anticipated construction start date is March 2027. The Transportation Committee forwarded the item to the Board with a favorable recommendation.
- Board:
- Transportation Cmte
- Date:
- 2026-07-14
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation by Transportation Committee; pending Board of County Commissioners approval
- Address:
- SR 934/NW 74th Street Connector from west of NW 77th Court to east of Red Road, including work on NW 74th Street Connector and NW 72nd Avenue
- Applicant:
- Florida Department of Transportation (FDOT) and Miami-Dade County
OFF-SYSTEM AGREEMENT FOR LOCAL ROADWAY IMPROVEMENTS
Miami-Dade County Board of County Commissioners is considering an Off-System Construction and Maintenance Agreement with the Florida Department of Transportation (FDOT) for roadway improvements on SR 934/NW 74th Street Connector from west of NW 77th Court to east of Red Road. The project includes work on NW 74th Street Connector and NW 72nd Avenue. Specific improvements include reconstruction of sidewalks, curb ramps, curb and gutter, milling and resurfacing, widening, striping, traffic separators, loops, and signage. The project is estimated to cost $5,900,000 and will be funded and built by FDOT. The anticipated construction start date is March 2027. The Transportation Committee forwarded the item to the Board with a favorable recommendation.
- Board:
- Transportation Cmte
- Date:
- 2026-07-14
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation by Transportation Committee; pending Board of County Commissioners approval
- Address:
- SR 934/NW 74th Street Connector from west of NW 77th Court to east of Red Road, including work on NW 74th Street Connector and NW 72nd Avenue
- Applicant:
- Florida Department of Transportation (FDOT) and Miami-Dade County
OFF-SYSTEM AGREEMENT FOR LOCAL ROADWAY IMPROVEMENTS
Miami-Dade County Board of County Commissioners is approving an Off-System Construction and Maintenance Agreement with the Florida Department of Transportation (FDOT) for roadway improvements. The project involves the reconstruction of sidewalks, curb ramps, and a traffic separator, along with milling, resurfacing, widening, striping, curb and gutter, loops, and signage. The project is estimated to cost $5,900,000, funded and built by FDOT, with an anticipated construction start date of March 2027. Miami-Dade County will be responsible for maintenance operations upon project completion.
- Board:
- Transportation Cmte
- Date:
- 2026-07-14
- Type:
- Resolution
- Decision:
- Approved (Resolution)
- Address:
- SR 934/NW 74th Street Connector from west of NW 77th Court to east of Red Road, including work on NW 74th Street Connector and NW 72nd Avenue
- Applicant:
- Florida Department of Transportation (FDOT) and Miami-Dade County
OFF-SYSTEM AGREEMENT FOR LOCAL ROADWAY IMPROVEMENTS
Miami-Dade County Board of County Commissioners is considering an Off-System Construction and Maintenance Agreement with the Florida Department of Transportation (FDOT) for roadway improvements on SR 934/NW 74th Street Connector from west of NW 77th Court to east of Red Road. The project includes work on NW 74th Street Connector and NW 72nd Avenue. Specific improvements include reconstruction of sidewalks, curb ramps, milling and resurfacing, widening, striping, traffic separators, loops, and signage. The project is estimated to cost $5,900,000, funded and built by FDOT, with an anticipated construction start date of March 2027. Miami-Dade County will be responsible for maintenance operations upon completion.
- Board:
- Transportation Cmte
- Date:
- 2026-07-14
- Type:
- Resolution
- Decision:
- In Committee
- Address:
- SR 934/NW 74th Street Connector from west of NW 77th Court to east of Red Road, including work on NW 74th Street Connector and NW 72nd Avenue
- Applicant:
- Miami-Dade County and Florida Department of Transportation (FDOT)
OFF-SYSTEM AGREEMENT FOR LOCAL ROADWAY IMPROVEMENTS
Resolution approving an Off-System Construction and Maintenance Agreement between Miami-Dade County and the Florida Department of Transportation for local roadway improvements for SR 934/NW 74th Street Connector from west of NW 77th Court to east of Red Road, with a portion of the project including work on NW 74th Street Connector and NW 72nd Avenue. The project is estimated to cost $5,900,000, funded and built by FDOT, with an anticipated construction start date of March 2027. The Transportation Committee forwarded it to the BCC with a favorable recommendation on 7/14/2026, and the agenda date is 9/1/2026. The County is required to provide maintenance operations within the County's right-of-way upon completion. Improvements include curb ramps, sidewalk, curb and gutter, milling and resurfacing, widening, striping, traffic separator, loops, and signage. The project is in Districts 6 and 12, represented by Commissioner Natalie Milian Orbis and Commissioner Juan Carlos Bermudez, respectively. The person responsible for monitoring is Maria D. Molina P.E., Chief, Right-of-Way and Stormwater Planning and Design Division. No public comment sentiment is stated.
- Board:
- Transportation Cmte
- Date:
- 2026-07-14
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation by Transportation Cmte on 7/14/2026; pending BCC assignment
- Address:
- SR 934/NW 74th Street Connector from west of NW 77th Court to east of Red Road; a portion includes work on NW 74th Street Connector and NW 72nd Avenue
- Applicant:
- Miami-Dade County and Florida Department of Transportation
OFF-SYSTEM AGREEMENT FOR LOCAL ROADWAY IMPROVEMENTS
Miami-Dade County Board of County Commissioners is considering an Off-System Construction and Maintenance Agreement with the Florida Department of Transportation (FDOT) for local roadway improvements along SR 934/NW 74th Street Connector from west of NW 77th Court to east of Red Road. The project, identified as Project No. FM452566-1-52-01, also includes work on NW 74th Street Connector and NW 72nd Avenue. Specific improvements include reconstruction of sidewalks, curb ramps, curb and gutter, milling and resurfacing, widening, striping, traffic separators, loops, and signage. The estimated project cost is $5,900,000, which will be funded and built by FDOT. The anticipated construction start date is March 2027. The County will be responsible for maintenance operations upon project completion, funded through DTPW's General Fund. The Transportation Committee forwarded the item to the Board of County Commissioners with a favorable recommendation.
- Board:
- Transportation Cmte
- Date:
- 2026-07-14
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation
- Address:
- SR 934/NW 74th Street Connector from west of NW 77th Court to east of Red Road, including work on NW 74th Street Connector and NW 72nd Avenue
- Applicant:
- Florida Department of Transportation (FDOT) and Miami-Dade County
OFF-SYSTEM AGREEMENT FOR LOCAL ROADWAY IMPROVEMENTS
Resolution approving an Off-System Construction and Maintenance Agreement between Miami-Dade County and the Florida Department of Transportation for local roadway improvements for SR 934/NW 74th Street Connector from west of NW 77th Court to east of Red Road, with a portion of the project including work on NW 74th Street Connector and NW 72nd Avenue. The project is estimated to cost $5,900,000 and will be funded and built by FDOT. The anticipated construction start date is March 2027. The Transportation Committee forwarded the item to the BCC with a favorable recommendation on 7/14/2026. The agenda date is 9/1/2026. The file number is 261136.
- Board:
- Transportation Cmte
- Date:
- 2026-07-14
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation
- Address:
- SR 934/NW 74th Street Connector from west of NW 77th Court to east of Red Road; a portion of the project includes work on NW 74th Street Connector and NW 72nd Avenue
- Applicant:
- Miami-Dade County and Florida Department of Transportation
OFF-SYSTEM AGREEMENT FOR LOCAL ROADWAY IMPROVEMENTS
Miami-Dade County Board of County Commissioners (BCC) is set to approve an Off-System Construction and Maintenance Agreement between Miami-Dade County and the Florida Department of Transportation (FDOT) for local roadway improvements. The project, identified as Project No. FM452566-1-52-01, involves improvements to SR 934/NW 74th Street Connector from west of NW 77th Court to east of Red Road, including work on NW 74th Street Connector and NW 72nd Avenue. Specific improvements include reconstruction of sidewalks, curb ramps, curb and gutter, milling and resurfacing, widening, striping, traffic separators, loops, and signage. The project is estimated to cost $5,900,000 and will be funded and built by FDOT. The anticipated construction start date is March 2027. Miami-Dade County will be responsible for maintenance operations upon project completion, funded through DTPW's General Fund allocation. The Transportation Committee forwarded the item to the BCC with a favorable recommendation.
- Board:
- Transportation Cmte
- Date:
- 2026-07-14
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation (Transportation Committee); Pending BCC Assignment
- Address:
- SR 934/NW 74th Street Connector from west of NW 77th Court to east of Red Road, including work on NW 74th Street Connector and NW 72nd Avenue
- Applicant:
- Miami-Dade County and Florida Department of Transportation (FDOT)
PTP AMENDMENT FOR REIMBURSEMENT TO DTPW
Resolution approving an amendment to the FY 2026-30 Five-Year Implementation Plan Update of the People's Transportation Plan (PTP) to retroactively include the Purchase of 40-Foot Buses for I-95 Phase I and II project (CIP145), funded in part by Charter County Transportation Surtax Funds. The project involves the purchase of fifteen (15) 40-foot diesel and compressed Natural Gas (CNG) buses for I-95 Express Bus Service routes between Broward and Miami-Dade Counties. The buses previously served routes 195/295 from Broward Boulevard to Downtown Miami and 196/296 connecting Sheridan Street to the Civic Center. The fiscal impact is $3,896,702. The item was forwarded to the BCC with a favorable recommendation following a public hearing. The resolution was introduced on 6/22/2026, with a Transportation Committee hearing on 7/14/2026 and a Board agenda date of 9/1/2026. The request was made to advance the item to the July 21, 2026, Board meeting. The routes were discontinued in March 2020 due to COVID-19 ridership decline and bus operator shortages. FDOT requested reimbursement on September 9, 2024, and DTPW issued a reimbursement payment of $3,896,702 to FDOT on January 12, 2026, using DTPW's Operating Fund. The retroactive inclusion authorizes the use of PTP capital funds to restore DTPW's operating fund resources.
- Board:
- Transportation Cmte
- Date:
- 2026-07-14
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation following a public hearing
- Applicant:
- Citizens' Independent Transportation Trust (CITT), requested by Javier Betancourt, Executive Director; Department of Transportation and Public Works (DTPW)
PTP AMENDMENT FOR REIMBURSEMENT TO DTPW
Miami-Dade County is considering an amendment to the FY 2026-30 Five-Year Implementation Plan of the People's Transportation Plan (PTP). The amendment seeks to retroactively include the purchase of fifteen (15) 40-foot diesel and compressed natural gas (CNG) buses for the I-95 Phase I and II project. These buses were purchased in January 2017 for I-95 Express Bus Service routes between Broward and Miami-Dade Counties, funded in part by Charter County Transportation Surtax Funds and FDOT grants. The routes were discontinued in March 2020. The county issued a reimbursement payment of $3,896,702 to FDOT on January 12, 2026, for the depreciated value and unauthorized mileage. Retroactive inclusion in the PTP is required to authorize the use of PTP capital funds to restore DTPW's operating fund. The project is monitored by the Miami-Dade County Department of Transportation and Public Works (DTPW).
- Board:
- Transportation Cmte
- Date:
- 2026-07-14
- Type:
- Resolution
- Decision:
- In Committee
- Applicant:
- Citizens' Independent Transportation Trust (CITT)
PTP AMENDMENT FOR REIMBURSEMENT TO DTPW
Miami-Dade County Board of County Commissioners (BCC) is considering a resolution to amend the FY 2026-30 Five-Year Implementation Plan Update of the People's Transportation Plan (PTP). The amendment retroactively includes the purchase of fifteen (15) 40-foot diesel and compressed natural gas (CNG) buses for the I-95 Phase I and II project. These buses were purchased in January 2017 for $3,896,702 using FDOT grant funds but were later redeployed from I-95 Express Bus Service routes due to declining ridership and operator shortages during the COVID-19 pandemic. This redeployment was inconsistent with FDOT's requirements, leading to a reimbursement request from FDOT. Miami-Dade County's Department of Transportation and Public Works (DTPW) issued the reimbursement payment on January 12, 2026, using DTPW's Operating Fund. The PTP amendment is needed to authorize the use of PTP capital funds to restore DTPW's operating fund resources and ensure compliance with PTP funding eligibility. The Transportation Committee forwarded the item to the BCC with a favorable recommendation following a public hearing.
- Board:
- Transportation Cmte
- Date:
- 2026-07-14
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation following a public hearing (Transportation Committee); Pending BCC Assignment (Legislative Item)
- Applicant:
- Citizens' Independent Transportation Trust (CITT)
PTP AMENDMENT FOR REIMBURSEMENT TO DTPW
Miami-Dade County Board of County Commissioners (BCC) is considering a resolution to amend the FY 2026-30 Five-Year Implementation Plan of the People's Transportation Plan (PTP). The amendment retroactively includes the purchase of fifteen (15) 40-foot diesel and compressed natural gas (CNG) buses for the I-95 Phase I and II project. These buses were purchased in January 2017 for $3,896,702 using FDOT grant funds but were redeployed from I-95 Express Bus Service routes due to declining ridership and operator shortages during the COVID-19 pandemic. This redeployment violated FDOT's contractual requirement for exclusive use on I-95 Express Service. Miami-Dade County's Department of Transportation and Public Works (DTPW) reimbursed FDOT $3,896,702 on January 12, 2026, from its Operating Fund. The PTP amendment is needed to authorize the use of PTP capital funds to restore DTPW's operating resources and ensure compliance with PTP funding eligibility. The Transportation Committee forwarded the item to the BCC with a favorable recommendation following a public hearing.
- Board:
- Transportation Cmte
- Date:
- 2026-07-14
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation by Transportation Committee; pending BCC Assignment
- Applicant:
- Citizens' Independent Transportation Trust (CITT)
PTP AMENDMENT FOR REIMBURSEMENT TO DTPW
Resolution approving an amendment to the FY 2026-30 Five-Year Implementation Plan of the People's Transportation Plan (PTP) to retroactively include the purchase of fifteen (15) 40-foot diesel and compressed Natural Gas (CNG) buses for the I-95 Phase I and II project (CIP145), funded in part by Charter County Transportation Surtax Funds. The buses previously served routes 195/295 and 196/296, connecting Broward Boulevard and Sheridan Street to Downtown Miami and the Civic Center. The project cost is $3,896,702. The amendment is needed because DTPW issued a reimbursement payment of $3,896,702 to FDOT on January 12, 2026, using DTPW's Operating Fund, after FDOT requested reimbursement on September 9, 2024, for depreciated value and unauthorized mileage. The Transportation Committee forwarded the item to the BCC with a favorable recommendation following a public hearing on 7/14/2026. The Board agenda date is 9/1/2026. The request was made to advance the item to the July 21, 2026, Board meeting. The discontinued bus routes primarily served District 3 and District 5, represented by Commissioner Keon Hardemon and Commissioner Vicki L. Lopez, respectively. The project is included in the County's FY 2025-26 Adopted Budget and Multi-Year Capital Plan under Program No. 6730101, Site No. 300908. FDOT provided $15 million in State toll revenues through grants G0350 and G1C16 for the purchase of 28 buses. The fifteen buses were purchased with these grant funds and placed into service in January 2017. The routes were discontinued in March 2020. The project will be monitored by the Miami-Dade County Department of Transportation and Public Works (DTPW).
- Board:
- Transportation Cmte
- Date:
- 2026-07-14
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation following a public hearing by the Transportation Committee on 7/14/2026; pending BCC assignment; agenda date 9/1/2026
- Applicant:
- Citizens' Independent Transportation Trust (CITT), requested by Javier Betancourt, Executive Director; Mayor Daniella Levine Cava; Deputy Mayor Roy Coley
PTP AMENDMENT FOR REIMBURSEMENT TO DTPW
Resolution approving an amendment to the FY 2026-30 Five-Year Implementation Plan Update of the People's Transportation Plan (PTP) to retroactively include the Purchase of 40-Foot Buses for I-95 Phase I and II project (CIP145), funded in part by Charter County Transportation Surtax Funds. The project involves the purchase of fifteen (15) 40-foot diesel and compressed Natural Gas (CNG) buses to support I-95 Express Bus Service routes in managed toll lanes between Broward and Miami-Dade Counties. The buses previously served routes 195/295 from Broward Boulevard to Downtown Miami and 196/296 connecting Sheridan Street to the Civic Center. The routes were discontinued in March 2020. FDOT requested reimbursement on September 9, 2024, and DTPW issued a reimbursement payment of $3,896,702 to FDOT on January 12, 2026, using DTPW's Operating Fund. The amendment authorizes the use of PTP capital funds to restore DTPW's operating fund resources. The Transportation Committee forwarded the item to the BCC with a favorable recommendation following a public hearing on July 14, 2026. The Board agenda date is September 1, 2026. The fiscal impact is $3,896,702. The project is included in the County's FY 2025-26 Adopted Budget and Multi-Year Capital Plan under Program No. 6730101, Site No. 300908. The discontinued bus routes primarily served District 3 and District 5, represented by Commissioner Keon Hardemon and Commissioner Vicki L. Lopez, respectively. The request was made to advance the item to the July 21, 2026, Board meeting. The requester is the Citizens' Independent Transportation Trust. The file number is 261138. The resolution was introduced on June 22, 2026. The staff recommendation is approval. The final action is not stated.
- Board:
- Transportation Cmte
- Date:
- 2026-07-14
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation following a public hearing by the Transportation Committee on July 14, 2026; final Board action not stated
- Applicant:
- Citizens' Independent Transportation Trust (CITT), requested by Javier Betancourt, Executive Director; Department of Transportation and Public Works (DTPW); Mayor Daniella Levine Cava; Deputy Mayor Roy Coley
PTP AMENDMENT FOR REIMBURSEMENT TO DTPW
Miami-Dade County Board of County Commissioners is considering a resolution to amend the FY 2026-30 Five-Year Implementation Plan of the People's Transportation Plan (PTP). The amendment retroactively includes the purchase of fifteen (15) 40-foot diesel and compressed natural gas (CNG) buses for the I-95 Phase I and II project. These buses were purchased in January 2017 for $3,896,702 using FDOT grant funds but were later redeployed from I-95 Express Bus Service routes due to declining ridership and operator shortages during the COVID-19 pandemic. FDOT requested reimbursement for the depreciated value and unauthorized mileage, which DTPW paid on January 12, 2026, from its operating fund. The PTP amendment is required to authorize the use of PTP capital funds to restore DTPW's operating resources and ensure compliance with PTP funding eligibility. The project is funded in part by Charter County Transportation Surtax Funds and is included in the County's FY 2025-26 Adopted Budget and Multi-Year Capital Plan.
- Board:
- Transportation Cmte
- Date:
- 2026-07-14
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation following a public hearing by the Transportation Committee. Pending Board of County Commissioners (BCC) Assignment.
- Applicant:
- Citizens' Independent Transportation Trust (CITT)
PTP AMENDMENT FOR REIMBURSEMENT TO DTPW
The document is a legislative matter for a resolution approving an amendment to the FY 2026-30 Five-Year Implementation Plan Update of the People's Transportation Plan (PTP) to retroactively include the Purchase of 40-Foot Buses for I-95 Phase I and II project (CIP145). The project involves the purchase of fifteen (15) 40-foot diesel and compressed Natural Gas (CNG) buses intended to support I-95 Express Bus Service routes operating within the managed toll lanes between Broward and Miami-Dade Counties. These buses previously served routes 195/295 from Broward Boulevard to Downtown Miami and 196/296 connecting Sheridan Street to the Civic Center. The fiscal impact is $3,896,702. The project is included in the County's FY 2025-26 Adopted Budget and Multi-Year Capital Plan under Program No. 6730101, Site No. 300908. The buses were purchased with FDOT grant funds and placed into service in January 2017. The routes were discontinued in March 2020. On September 9, 2024, FDOT requested reimbursement for the depreciated value and unauthorized mileage. DTPW issued a reimbursement payment of $3,896,702 to FDOT on January 12, 2026, using DTPW's Operating Fund. The amendment authorizes the use of PTP capital funds to restore DTPW's operating fund resources. The Transportation Committee forwarded the item to the BCC with a favorable recommendation following a public hearing on 7/14/2026. The agenda date is 9/1/2026. The requester is the Citizens' Independent Transportation Trust. The staff recommendation is to approve the resolution.
- Board:
- Transportation Cmte
- Date:
- 2026-07-14
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation following a public hearing
- Applicant:
- Citizens' Independent Transportation Trust
PTP AMENDMENT FOR REIMBURSEMENT TO DTPW
Miami-Dade County is considering an amendment to the FY 2026-30 Five-Year Implementation Plan Update of the People's Transportation Plan (PTP). The amendment seeks to retroactively include the purchase of fifteen (15) 40-foot diesel and compressed natural gas (CNG) buses for the I-95 Phase I and II project. These buses were purchased in January 2017 for $3,896,702 using FDOT grant funds for I-95 Express Bus Service routes. The routes were discontinued in March 2020, and the buses were redeployed to other services, which was inconsistent with FDOT's requirements. FDOT requested reimbursement, and Miami-Dade County paid $3,896,702 to FDOT on January 12, 2026, from DTPW's Operating Fund. The PTP amendment is needed to authorize the use of PTP capital funds to restore DTPW's operating fund resources and ensure compliance with PTP funding eligibility. The project is monitored by the Miami-Dade County Department of Transportation and Public Works (DTPW).
- Board:
- Transportation Cmte
- Date:
- 2026-07-14
- Type:
- Resolution
- Decision:
- In Committee
- Applicant:
- Citizens' Independent Transportation Trust (CITT)
PTP AMENDMENT FOR REIMBURSEMENT TO DTPW
Miami-Dade County Board of County Commissioners is considering a resolution to approve an amendment to the FY 2026-30 Five-Year Implementation Plan Update of the People's Transportation Plan (PTP). The amendment retroactively includes the purchase of fifteen (15) 40-foot diesel and compressed Natural Gas (CNG) buses for the I-95 Phase I and II project. These buses were purchased in January 2017 for $3,896,702 using FDOT grant funds for I-95 Express Bus Service routes. The routes were discontinued in March 2020, and the buses were redeployed, which was inconsistent with FDOT's requirements. FDOT requested reimbursement, and Miami-Dade County paid $3,896,702 to FDOT on January 12, 2026, from DTPW's Operating Fund. The PTP amendment is needed to authorize the use of PTP capital funds to restore DTPW's operating fund resources and ensure compliance with PTP funding eligibility. The project is monitored by the Miami-Dade County Department of Transportation and Public Works (DTPW).
- Board:
- Transportation Cmte
- Date:
- 2026-07-14
- Type:
- Resolution
- Decision:
- In Committee
- Applicant:
- Citizens' Independent Transportation Trust (CITT)
PTP AMENDMENT FOR REIMBURSEMENT TO DTPW
Resolution approving an amendment to the FY 2026-30 Five-Year Implementation Plan of the People's Transportation Plan (PTP) to retroactively include the Purchase of 40-Foot Buses for I-95 Phase I and II project (CIP145), funded in part by Charter County Transportation Surtax Funds. The project involves the purchase of fifteen (15) 40-foot diesel and compressed Natural Gas (CNG) buses for I-95 Express Bus Service routes between Broward and Miami-Dade Counties. The buses previously served routes 195/295 and 196/296. The fiscal impact is $3,896,702. The Transportation Committee forwarded the item to the Board with a favorable recommendation following a public hearing on 7/14/2026. The Board agenda date is 9/1/2026. The resolution was introduced on 6/22/2026. The request was made to advance the item to the July 21, 2026, Board meeting. The routes were discontinued in March 2020. FDOT requested reimbursement on September 9, 2024. DTPW issued a reimbursement payment of $3,896,702 to FDOT on January 12, 2026. The project is included in the County's FY 2025-26 Adopted Budget and Multi-Year Capital Plan under Program No. 6730101, Site No. 300908. The discontinued bus routes primarily served District 3 and District 5. The requester is the Citizens' Independent Transportation Trust. The sponsor is none. The registered lobbyist is none listed. The County Attorney assigned is Bruce Libhaber. The Deputy Mayor is Roy Coley. The Mayor is Daniella Levine Cava. The Chairman is Anthony Rodriguez. The Executive Director of CITT is Javier Betancourt. The project is monitored by the Miami-Dade County Department of Transportation and Public Works (DTPW). The buses were purchased with FDOT grant funds and placed into service in January 2017. The buses were redeployed to other routes, which was inconsistent with FDOT's contractual requirement. The retroactive inclusion authorizes the use of PTP capital funds to restore DTPW's operating fund resources. The document does not state a specific street address, parcel, or acreage. The document does not state any public comment or stakeholder sentiment beyond the fact that a public hearing was held.
- Board:
- Transportation Cmte
- Date:
- 2026-07-14
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation following a public hearing
- Applicant:
- Citizens' Independent Transportation Trust
PTP AMENDMENT FOR REIMBURSEMENT TO DTPW
Miami-Dade County is considering an amendment to the FY 2026-30 Five-Year Implementation Plan of the People's Transportation Plan (PTP). The amendment seeks to retroactively include the purchase of fifteen (15) 40-foot diesel and compressed natural gas (CNG) buses for the I-95 Phase I and II project. These buses were purchased in January 2017 for I-95 Express Bus Service routes connecting Broward and Miami-Dade Counties, funded in part by Charter County Transportation Surtax Funds and FDOT grants. The routes were discontinued in March 2020 due to declining ridership and operator shortages. Miami-Dade Department of Transportation and Public Works (DTPW) deployed the buses to other routes, which was inconsistent with FDOT's contractual requirements. FDOT requested reimbursement for the depreciated value and unauthorized mileage, totaling $3,896,702, which DTPW paid on January 12, 2026, from its Operating Fund. The amendment is required to authorize the use of PTP capital funds to restore DTPW's operating fund resources and ensure compliance with PTP funding eligibility. The project is identified as CIP145 and is included in the County's FY 2025-26 Adopted Budget and Multi-Year Capital Plan under Program No. 6730101, Site No. 300908. The matter is currently In Committee.
- Board:
- Transportation Cmte
- Date:
- 2026-07-14
- Type:
- Resolution
- Decision:
- In Committee
- Address:
- I-95 Phase I and II project
- Applicant:
- Citizens' Independent Transportation Trust (CITT)
PTP AMENDMENT FOR REIMBURSEMENT TO DTPW
Resolution approving an amendment to the FY 2026-30 Five-Year Implementation Plan Update of the People's Transportation Plan (PTP) to retroactively include the Purchase of 40-Foot Buses for I-95 Phase I and II project (CIP145), funded in part by Charter County Transportation Surtax Funds. The project involves the purchase of fifteen (15) 40-foot diesel and compressed Natural Gas (CNG) buses for I-95 Express Bus Service routes between Broward and Miami-Dade Counties. The fiscal impact is $3,896,702. The Transportation Committee forwarded it to the BCC with a favorable recommendation following a public hearing on 7/14/2026. The Board agenda date is 9/1/2026. The buses were purchased with FDOT grant funds and placed into service in January 2017, routes were discontinued in March 2020, and DTPW issued a reimbursement payment of $3,896,702 to FDOT on January 12, 2026, using DTPW's Operating Fund. Retroactive inclusion authorizes the use of PTP capital funds to restore DTPW's operating fund resources.
- Board:
- Transportation Cmte
- Date:
- 2026-07-14
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation following a public hearing (Transportation Committee, 7/14/2026); pending BCC approval on 9/1/2026
- Applicant:
- Citizens' Independent Transportation Trust (CITT); Department of Transportation and Public Works (DTPW); Javier Betancourt, Executive Director of CITT
PTP AMENDMENT FOR REIMBURSEMENT TO DTPW
Resolution approving an amendment to the FY 2026-30 Five-Year Implementation Plan Update of the People's Transportation Plan (PTP) to retroactively include the Purchase of 40-Foot Buses for I-95 Phase I and II project (CIP145), funded in part by Charter County Transportation Surtax Funds. The project involves the purchase of fifteen (15) 40-foot diesel and compressed Natural Gas (CNG) buses for I-95 Express Bus Service routes between Broward and Miami-Dade Counties. The buses previously served routes 195/295 from Broward Boulevard to Downtown Miami and 196/296 connecting Sheridan Street to the Civic Center. The fiscal impact is $3,896,702. The Transportation Committee forwarded the item to the BCC with a favorable recommendation following a public hearing on 7/14/2026. The Board agenda date is 9/1/2026. The item was introduced on 6/22/2026. The requester is the Citizens' Independent Transportation Trust. The applicant is the Department of Transportation and Public Works (DTPW). The resolution was recommended by the Mayor. The buses were purchased with FDOT grant funds and placed into service in January 2017. The routes were discontinued in March 2020. On September 9, 2024, FDOT requested reimbursement. DTPW issued a reimbursement payment of $3,896,702 to FDOT on January 12, 2026. The amendment authorizes the use of PTP capital funds to restore DTPW's operating fund resources. The discontinued routes primarily served District 3 and District 5. The project is included in the County's FY 2025-26 Adopted Budget and Multi-Year Capital Plan under Program No. 6730101, Site No. 300908. A public hearing was held. A request was made to advance the item to the July 21, 2026, Board meeting. The County Attorney assigned was Bruce Libhaber. The item has 13 pages. The final action is not stated. The effective date is not stated. The expiration date is not stated. The cost is not stated. The sponsors are none. The registered lobbyist is none listed.
- Board:
- Transportation Cmte
- Date:
- 2026-07-14
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation following a public hearing (Transportation Committee, 7/14/2026); final Board action not stated
- Applicant:
- Department of Transportation and Public Works (DTPW); requester: Citizens' Independent Transportation Trust
PTP AMENDMENT FOR REIMBURSEMENT TO DTPW
Miami-Dade Board of County Commissioners is considering a resolution to approve an amendment to the FY 2026-30 Five-Year Implementation Plan Update of the People's Transportation Plan (PTP). The amendment retroactively adds the 'Purchase of 40-Foot Buses for I-95 Phase I and II project (CIP145)' to allow the use of PTP capital funds to reimburse the Department of Transportation and Public Works (DTPW) Operating Fund. This reimbursement of $3,896,702 was made to FDOT on January 12, 2026, for fifteen (15) 40-foot diesel and compressed natural gas (CNG) buses. These buses were purchased with FDOT grant funds for I-95 Express Bus Service but were redeployed to other routes due to declining ridership and operator shortages during the COVID-19 pandemic, which violated FDOT's contractual requirements. The Transportation Committee forwarded the item to the Board with a favorable recommendation following a public hearing. The Board is expected to make a decision on September 1, 2026.
- Board:
- Transportation Cmte
- Date:
- 2026-07-14
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation by Transportation Committee; Pending Board of County Commissioners decision
- Applicant:
- Citizens' Independent Transportation Trust (CITT)
PTP AMENDMENT FOR REIMBURSEMENT TO DTPW
Resolution approving an amendment to the FY 2026-30 Five-Year Implementation Plan Update of the People's Transportation Plan (PTP) to retroactively include the Purchase of 40-Foot Buses for I-95 Phase I and II project (CIP145), funded in part by Charter County Transportation Surtax Funds. The project involves the purchase of fifteen (15) 40-foot diesel and compressed Natural Gas (CNG) buses for I-95 Express Bus Service routes between Broward and Miami-Dade Counties. The buses previously served routes 195/295 from Broward Boulevard to Downtown Miami and 196/296 connecting Sheridan Street to the Civic Center. The fiscal impact is $3,896,702. The Transportation Committee forwarded the item to the BCC with a favorable recommendation following a public hearing on 7/14/2026. The Board agenda date is 9/1/2026. The item was introduced on 6/22/2026. The requester is the Citizens' Independent Transportation Trust. The applicant/developer/owner is not stated; the Department of Transportation and Public Works (DTPW) is the department seeking the amendment. The decision is pending before the Board. The document does not state a street address, parcel/folio, acreage, or number of units/lots. The project is for the purchase of buses, not a construction project. Public comment sentiment is not stated beyond the fact that a public hearing was held.
- Board:
- Transportation Cmte
- Date:
- 2026-07-14
- Type:
- Resolution
- Decision:
- Pending before the Board; Transportation Committee forwarded to BCC with favorable recommendation on 7/14/2026
- Applicant:
- Citizens' Independent Transportation Trust (requester); Department of Transportation and Public Works (DTPW) seeking the amendment
PTP AMENDMENT FOR REIMBURSEMENT TO DTPW
Miami-Dade County Board of County Commissioners (BCC) is considering a resolution to amend the FY 2026-30 Five-Year Implementation Plan of the People's Transportation Plan (PTP). The amendment retroactively includes the purchase of fifteen (15) 40-foot diesel and compressed natural gas (CNG) buses for the I-95 Phase I and II project. These buses were purchased in January 2017 for $3,896,702 using FDOT grant funds but were later redeployed from discontinued routes (195/295 and 196/296) inconsistent with grant requirements. Miami-Dade County's Department of Transportation and Public Works (DTPW) reimbursed FDOT $3,896,702 on January 12, 2026, from its Operating Fund. The PTP amendment is needed to authorize the use of PTP capital funds to restore DTPW's operating fund resources and ensure compliance with PTP funding eligibility. The Transportation Committee forwarded the item to the BCC with a favorable recommendation following a public hearing. The project is funded in part by Charter County Transportation Surtax Funds and is included in the County's FY 2025-26 Adopted Budget and Multi-Year Capital Plan under Program No. 6730101, Site No. 300908.
- Board:
- Transportation Cmte
- Date:
- 2026-07-14
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation following a public hearing by the Transportation Committee. Pending BCC Assignment.
- Applicant:
- Citizens' Independent Transportation Trust (CITT)
PTP AMENDMENT FOR REIMBURSEMENT TO DTPW
The document is a legislative item for a resolution approving an amendment to the FY 2026-30 Five-Year Implementation Plan of the People's Transportation Plan (PTP) to retroactively include the purchase of 40-foot buses for the I-95 Phase I and II project, funded in part by Charter County Transportation Surtax Funds. The project (CIP145) involves the purchase of fifteen (15) 40-foot diesel and compressed Natural Gas (CNG) buses for I-95 Express Bus Service routes between Broward and Miami-Dade Counties. The fiscal impact is $3,896,702. The item was forwarded to the Board of County Commissioners with a favorable recommendation following a public hearing. The buses were previously purchased with FDOT grant funds and placed into service in January 2017, but routes were discontinued in March 2020. FDOT requested reimbursement on September 9, 2024, and DTPW issued a reimbursement payment of $3,896,702 on January 12, 2026. The amendment is required to authorize the use of PTP capital funds to restore DTPW's operating fund resources.
- Board:
- Transportation Cmte
- Date:
- 2026-07-14
- Type:
- Resolution
- Decision:
- Forwarded to the Board of County Commissioners with a favorable recommendation following a public hearing; pending Board action
- Applicant:
- Citizens' Independent Transportation Trust (CITT), requested by Javier Betancourt, Executive Director; Mayor Daniella Levine Cava; Department of Transportation and Public Works (DTPW)
PTP AMENDMENT FOR REIMBURSEMENT TO DTPW
Miami-Dade County Board of County Commissioners (BCC) is considering a resolution to amend the FY 2026-30 Five-Year Implementation Plan of the People's Transportation Plan (PTP). The amendment retroactively includes the purchase of fifteen (15) 40-foot diesel and compressed natural gas (CNG) buses for the I-95 Phase I and II Project (CIP145). These buses were purchased in January 2017 for $3,896,702 using FDOT grant funds for I-95 Express Bus Service routes connecting Broward and Miami-Dade Counties. The routes were discontinued in March 2020 due to declining ridership and operator shortages. The buses were redeployed to other routes, which was inconsistent with FDOT's contractual requirements. FDOT requested reimbursement for the depreciated value and unauthorized mileage, which DTPW paid on January 12, 2026. The PTP amendment is needed to authorize the use of PTP capital funds to restore DTPW's operating fund. The Transportation Committee forwarded the item to the BCC with a favorable recommendation following a public hearing.
- Board:
- Transportation Cmte
- Date:
- 2026-07-14
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation following a public hearing (Transportation Cmte); Recommendation for Approval (Staff)
- Applicant:
- Citizens' Independent Transportation Trust (CITT)
PTP AMENDMENT FOR REIMBURSEMENT TO DTPW
Miami-Dade County Board of County Commissioners (BCC) is considering a resolution to amend the FY 2026-30 Five-Year Implementation Plan of the People's Transportation Plan (PTP). The amendment retroactively includes the purchase of fifteen (15) 40-foot diesel and Compressed Natural Gas (CNG) buses for the I-95 Phase I and II project. These buses were purchased in January 2017 for $3,896,702 using FDOT grant funds but were later redeployed from discontinued routes (195/295 and 196/296) inconsistent with grant requirements. FDOT requested reimbursement, which DTPW paid on January 12, 2026, from its Operating Fund. The PTP amendment is needed to authorize the use of PTP capital funds to restore DTPW's operating resources and ensure compliance with PTP funding eligibility. The Transportation Committee forwarded the item to the BCC with a favorable recommendation following a public hearing.
- Board:
- Transportation Cmte
- Date:
- 2026-07-14
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation
- Applicant:
- Citizens' Independent Transportation Trust (CITT)
PTP AMENDMENT FOR REIMBURSEMENT TO DTPW
Miami-Dade County Board of County Commissioners (BCC) is considering a resolution to amend the FY 2026-30 Five-Year Implementation Plan Update of the People's Transportation Plan (PTP). The amendment retroactively includes the purchase of fifteen (15) 40-foot diesel and Compressed Natural Gas (CNG) buses for the I-95 Phase I and II project. These buses were purchased in January 2017 for I-95 Express Bus Service routes connecting Broward and Miami-Dade Counties, but were discontinued in March 2020 due to declining ridership and operator shortages during the COVID-19 pandemic. The buses were redeployed to other routes, which was inconsistent with FDOT's contractual requirement for their use solely on I-95 Express Service. FDOT requested reimbursement for the depreciated value and unauthorized mileage, totaling $3,896,702, which DTPW paid on January 12, 2026, from its Operating Fund. The PTP amendment is required to authorize the use of PTP capital funds to restore DTPW's operating fund resources and ensure compliance with PTP funding eligibility. The Transportation Committee forwarded the item to the BCC with a favorable recommendation following a public hearing.
- Board:
- Transportation Cmte
- Date:
- 2026-07-14
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation by Transportation Committee; pending BCC Assignment
- Applicant:
- Citizens' Independent Transportation Trust (CITT)
PTP AMENDMENT FOR REIMBURSEMENT TO DTPW
Miami-Dade County Board of County Commissioners is considering a resolution to approve an amendment to the FY 2026-30 Five-Year Implementation Plan Update of the People's Transportation Plan (PTP). This amendment retroactively includes the purchase of fifteen (15) 40-foot diesel and compressed natural gas (CNG) buses for the I-95 Phase I and II Project (CIP145). These buses were initially purchased in January 2017 with FDOT grant funds for I-95 Express Bus Service routes connecting Broward and Miami-Dade Counties. The routes were discontinued in March 2020 due to declining ridership and operator shortages. To comply with FDOT requirements, Miami-Dade County's Department of Transportation and Public Works (DTPW) issued a reimbursement payment of $3,896,702 to FDOT on January 12, 2026, using DTPW's Operating Fund. The PTP amendment is needed to authorize the use of PTP capital funds to restore DTPW's operating fund resources and ensure compliance with PTP funding eligibility. The Transportation Committee forwarded the item to the Board with a favorable recommendation following a public hearing.
- Board:
- Transportation Cmte
- Date:
- 2026-07-14
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation (Transportation Committee); Recommendation for Approval (Staff)
- Applicant:
- Citizens' Independent Transportation Trust (CITT)
PTP AMENDMENT FOR REIMBURSEMENT TO DTPW
Resolution approving an amendment to the FY 2026-30 Five-Year Implementation Plan of the People's Transportation Plan (PTP) to retroactively include the Purchase of 40-Foot Buses for I-95 Phase I and II project (CIP145), funded in part by Charter County Transportation Surtax Funds. The project involves the purchase of fifteen (15) 40-foot diesel and compressed Natural Gas (CNG) buses for I-95 Express Bus Service routes between Broward and Miami-Dade Counties. The buses previously served routes 195/295 from Broward Boulevard to Downtown Miami and 196/296 connecting Sheridan Street to the Civic Center. The fiscal impact is $3,896,702. The item was forwarded to the Board with a favorable recommendation following a public hearing. The Board agenda date is 9/1/2026. The request was made to advance the item to the July 21, 2026, Board meeting. The routes were discontinued in March 2020 due to COVID-19 ridership decline and bus operator shortages. FDOT requested reimbursement on September 9, 2024, and DTPW issued a reimbursement payment of $3,896,702 to FDOT on January 12, 2026, using DTPW's Operating Fund. The amendment authorizes the use of PTP capital funds to restore DTPW's operating fund resources. The discontinued bus routes primarily served District 3 and District 5. The project is included in the County's FY 2025-26 Adopted Budget and Multi-Year Capital Plan under Program No. 6730101, Site No. 300908. FDOT provided $15 million in State toll revenues through grants G0350 and G1C16 for the purchase of 28 buses. The fifteen buses were purchased with these grant funds and placed into service in January 2017.
- Board:
- Transportation Cmte
- Date:
- 2026-07-14
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation following a public hearing (Transportation Committee, 7/14/2026); pending Board action on 9/1/2026
- Applicant:
- Citizens' Independent Transportation Trust (CITT), requested by Javier Betancourt, Executive Director; Department of Transportation and Public Works (DTPW); Mayor Daniella Levine Cava; Deputy Mayor Roy Coley
PTP AMENDMENT FOR REIMBURSEMENT TO DTPW
Miami-Dade County Board of County Commissioners is considering a resolution to approve an amendment to the FY 2026-30 Five-Year Implementation Plan Update of the People's Transportation Plan (PTP). This amendment retroactively includes the purchase of fifteen (15) 40-foot diesel and compressed natural gas (CNG) buses for the I-95 Phase I and II Project (CIP145). These buses were purchased in January 2017 for $3,896,702 using FDOT grant funds for I-95 Express Bus Service routes. The routes were discontinued in March 2020. The amendment is needed to authorize the use of PTP capital funds to reimburse DTPW's operating fund, which was used to pay FDOT $3,896,702 on January 12, 2026, for the depreciated value and unauthorized mileage of these buses, as their use deviated from the original FDOT grant requirements. The project is funded in part by Charter County Transportation Surtax Funds and is included in the County's FY 2025-26 Adopted Budget.
- Board:
- Transportation Cmte
- Date:
- 2026-07-14
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation following a public hearing by the Transportation Committee. Recommendation for Approval by Staff.
- Applicant:
- Citizens' Independent Transportation Trust (CITT)
PTP AMENDMENT FOR REIMBURSEMENT TO DTPW
Miami-Dade Board of County Commissioners (BCC) is considering a resolution to approve an amendment to the FY 2026-30 Five-Year Implementation Plan Update of the People's Transportation Plan (PTP). This amendment retroactively includes the purchase of fifteen (15) 40-foot diesel and compressed Natural Gas (CNG) buses for the I-95 Phase I and II project. These buses were purchased in January 2017 for $3,896,702 using FDOT grant funds for I-95 Express Bus Service routes. The routes were discontinued in March 2020 due to declining ridership and operator shortages. The buses were redeployed to other routes, which was inconsistent with FDOT's grant requirements. On September 9, 2024, FDOT requested reimbursement for the depreciated value and unauthorized mileage. Miami-Dade Department of Transportation and Public Works (DTPW) issued a reimbursement payment of $3,896,702 to FDOT on January 12, 2026, from DTPW's Operating Fund. The amendment is required to authorize the use of PTP capital funds to restore DTPW's operating fund resources and ensure compliance with PTP funding eligibility. The project is funded in part by Charter County Transportation Surtax Funds and is included in the County's FY 2025-26 Adopted Budget and Multi-Year Capital Plan under Program No. 6730101, Site No. 300908.
- Board:
- Transportation Cmte
- Date:
- 2026-07-14
- Type:
- Resolution
- Decision:
- Pending BCC Assignment
- Applicant:
- Citizens' Independent Transportation Trust (CITT)
PTP AMENDMENT FOR REIMBURSEMENT TO DTPW
Resolution approving an amendment to the FY 2026-30 Five-Year Implementation Plan Update of the People's Transportation Plan (PTP) to retroactively include the Purchase of 40-Foot Buses for I-95 Phase I and II project (CIP145), funded in part by Charter County Transportation Surtax Funds. The project involves the purchase of fifteen (15) 40-foot diesel and compressed Natural Gas (CNG) buses to support I-95 Express Bus Service routes between Broward and Miami-Dade Counties. The buses previously served routes 195/295 and 196/296. The fiscal impact is $3,896,702. The item was forwarded to the Board with a favorable recommendation following a public hearing. The resolution is before the Board with an agenda date of 9/1/2026. The request was made to advance the item to the July 21, 2026, Board meeting. The buses were purchased with FDOT grant funds and placed into service in January 2017. Routes were discontinued in March 2020. On September 9, 2024, FDOT requested reimbursement. DTPW issued a reimbursement payment of $3,896,702 to FDOT on January 12, 2026, using DTPW's Operating Fund. Retroactive inclusion is required to authorize the use of PTP capital funds to restore DTPW's operating fund resources.
- Board:
- Transportation Cmte
- Date:
- 2026-07-14
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation following a public hearing; before the Board
- Applicant:
- Citizens' Independent Transportation Trust (CITT), requested by Javier Betancourt, Executive Director; Department of Transportation and Public Works (DTPW)
PTP AMENDMENT FOR REIMBURSEMENT TO DTPW
Miami-Dade Board of County Commissioners (BCC) is considering a resolution to approve an amendment to the FY 2026-30 Five-Year Implementation Plan Update of the People's Transportation Plan (PTP). This amendment retroactively includes the purchase of fifteen (15) 40-foot diesel and compressed natural gas (CNG) buses for the I-95 Phase I and II project. These buses were purchased in January 2017 for $3,896,702 using FDOT grant funds for I-95 Express Bus Service. Due to decreased ridership and operator shortages during the COVID-19 pandemic, the buses were redeployed to other routes, which was inconsistent with FDOT's grant requirements. FDOT requested reimbursement for the depreciated value and unauthorized mileage, which DTPW paid on January 12, 2026, from its Operating Fund. The PTP amendment is needed to authorize the use of PTP capital funds to restore DTPW's operating fund resources and ensure compliance with PTP funding eligibility. The project is monitored by the Miami-Dade County Department of Transportation and Public Works (DTPW).
- Board:
- Transportation Cmte
- Date:
- 2026-07-14
- Type:
- Resolution
- Decision:
- Pending BCC Assignment (Resolution before the Board)
- Applicant:
- Citizens' Independent Transportation Trust (CITT)
PTP AMENDMENT FOR REIMBURSEMENT TO DTPW
Miami-Dade County Board of County Commissioners is considering a resolution to approve an amendment to the FY 2026-30 Five-Year Implementation Plan Update of the People's Transportation Plan (PTP). This amendment retroactively includes the purchase of fifteen (15) 40-foot diesel and compressed natural gas (CNG) buses for the I-95 Phase I and II Project (CIP145). These buses were purchased in January 2017 for $3,896,702 using FDOT grant funds but were later redeployed from I-95 Express Bus Service routes due to declining ridership and operator shortages during the COVID-19 pandemic. This redeployment was inconsistent with FDOT's requirements, leading to a request for reimbursement from FDOT on September 9, 2024. Miami-Dade County's Department of Transportation and Public Works (DTPW) issued a reimbursement payment of $3,896,702 to FDOT on January 12, 2026, from DTPW's Operating Fund. The PTP amendment is needed to authorize the use of PTP capital funds to restore DTPW's operating fund resources and ensure compliance with PTP funding eligibility. The project is funded in part by Charter County Transportation Surtax Funds and is included in the County's FY 2025-26 Adopted Budget.
- Board:
- Transportation Cmte
- Date:
- 2026-07-14
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation following a public hearing by the Transportation Committee.
- Applicant:
- Citizens' Independent Transportation Trust (CITT)
PTP AMENDMENT FOR REIMBURSEMENT TO DTPW
Miami-Dade County Board of County Commissioners (BCC) is considering a resolution to amend the FY 2026-30 Five-Year Implementation Plan of the People's Transportation Plan (PTP). The amendment retroactively includes the purchase of fifteen (15) 40-foot diesel and compressed natural gas (CNG) buses for the I-95 Phase I and II Project (CIP145). These buses were purchased in January 2017 for $3,896,702 using FDOT grant funds for I-95 Express Bus Service. The project was discontinued in March 2020 due to declining ridership and operator shortages during the COVID-19 pandemic. The buses were redeployed to other routes, which was inconsistent with FDOT's contractual requirements. FDOT requested reimbursement, and Miami-Dade County's Department of Transportation and Public Works (DTPW) issued a payment of $3,896,702 on January 12, 2026, from DTPW's Operating Fund. The PTP amendment is needed to authorize the use of PTP capital funds to restore DTPW's operating fund resources and ensure compliance with PTP funding eligibility. The Transportation Committee forwarded the item to the BCC with a favorable recommendation following a public hearing.
- Board:
- Transportation Cmte
- Date:
- 2026-07-14
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation by Transportation Committee; pending BCC Assignment.
- Applicant:
- Citizens' Independent Transportation Trust (CITT)
PTP AMENDMENT FOR REIMBURSEMENT TO DTPW
The document is a resolution approving an amendment to the FY 2026-30 Five-Year Implementation Plan of the People's Transportation Plan (PTP) to retroactively include the purchase of fifteen 40-foot buses for the I-95 Phase I and II project, funded in part by Charter County Transportation Surtax Funds. The project is identified as CIP145. The buses were previously used on routes 195/295 and 196/296, which were discontinued in March 2020. The fiscal impact is $3,896,702. The Transportation Committee forwarded the item to the Board of County Commissioners with a favorable recommendation following a public hearing on July 14, 2026. The Board agenda date is September 1, 2026. The applicant is the Citizens' Independent Transportation Trust, requested by Javier Betancourt, Executive Director. The file number is 261138. The decision is pending before the Board. The document does not state a specific street address, parcel, or acreage. The project involves the purchase of buses, not a construction project, so no zoning or use change is stated. The business opportunity is the retroactive inclusion of a capital project for the purchase of fifteen 40-foot diesel and compressed natural gas buses to support I-95 Express Bus Service routes between Broward and Miami-Dade Counties. The document states a public hearing was held, but does not state any specific public comment or stakeholder sentiment.
- Board:
- Transportation Cmte
- Date:
- 2026-07-14
- Type:
- Resolution
- Decision:
- Pending before the Board; Transportation Committee forwarded with favorable recommendation
- Applicant:
- Citizens' Independent Transportation Trust (CITT), requested by Javier Betancourt, Executive Director
PTP AMENDMENT FOR REIMBURSEMENT TO DTPW
Miami-Dade County is considering an amendment to the FY 2026-30 Five-Year Implementation Plan of the People's Transportation Plan (PTP). The amendment seeks to retroactively include the purchase of fifteen (15) 40-foot diesel and compressed natural gas (CNG) buses for the I-95 Phase I and II project. These buses were purchased in January 2017 for I-95 Express Bus Service routes connecting Broward and Miami-Dade Counties, funded in part by Charter County Transportation Surtax Funds and FDOT grants. The routes were discontinued in March 2020 due to declining ridership and operator shortages. Miami-Dade Department of Transportation and Public Works (DTPW) deployed the buses to other routes, which was inconsistent with FDOT's contractual requirements. FDOT requested reimbursement for the depreciated value and unauthorized mileage, totaling $3,896,702, which DTPW paid on January 12, 2026, using its Operating Fund. The PTP amendment is required to authorize the use of PTP capital funds to restore DTPW's operating fund resources and ensure compliance with PTP funding eligibility. The project is identified as CIP145 and is included in the County's FY 2025-26 Adopted Budget and Multi-Year Capital Plan under Program No. 6730101, Site No. 300908. The Citizens' Independent Transportation Trust (CITT) recommends approval, and the Board of County Commissioners is expected to consider this at an upcoming agenda meeting.
- Board:
- Transportation Cmte
- Date:
- 2026-07-14
- Type:
- Resolution
- Decision:
- In Committee
- Applicant:
- Citizens' Independent Transportation Trust (CITT)
PTP AMENDMENT FOR REIMBURSEMENT TO DTPW
Resolution approving an amendment to the FY 2026-30 Five-Year Implementation Plan of the People's Transportation Plan (PTP) to retroactively include the purchase of fifteen (15) 40-foot diesel and compressed Natural Gas (CNG) buses for the I-95 Phase I and II project (CIP145), funded in part by Charter County Transportation Surtax Funds. The buses previously served routes 195/295 and 196/296, connecting Broward Boulevard and Sheridan Street to Downtown Miami and the Civic Center. The project cost is $3,896,702. The buses were purchased with FDOT grant funds and placed into service in January 2017; routes were discontinued in March 2020; FDOT requested reimbursement on September 9, 2024; DTPW issued reimbursement on January 12, 2026. The Transportation Committee forwarded to the BCC with a favorable recommendation on 7/14/2026. Agenda date 9/1/2026. No street address, parcel, or acreage is stated.
- Board:
- Transportation Cmte
- Date:
- 2026-07-14
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation following a public hearing (Transportation Committee, 7/14/2026); pending BCC action on 9/1/2026
- Applicant:
- Citizens' Independent Transportation Trust (CITT), requested by Javier Betancourt, Executive Director; Department of Transportation and Public Works (DTPW)
PTP AMENDMENT FOR REIMBURSEMENT TO DTPW
Miami-Dade County Board of County Commissioners is considering a resolution to amend the FY 2026-30 Five-Year Implementation Plan Update of the People's Transportation Plan (PTP). The amendment retroactively includes the purchase of fifteen (15) 40-foot diesel and compressed natural gas (CNG) buses for the I-95 Phase I and II project. These buses were purchased in January 2017 for $3,896,702 using FDOT grant funds but were later redeployed from I-95 Express Bus Service routes due to declining ridership and operator shortages during the COVID-19 pandemic. This redeployment was inconsistent with FDOT's contractual requirements, leading to a reimbursement request from FDOT. Miami-Dade County's Department of Transportation and Public Works (DTPW) issued the reimbursement payment on January 12, 2026, using DTPW's Operating Fund. The PTP amendment is required to authorize the use of PTP capital funds to restore DTPW's operating fund resources and ensure compliance with PTP funding eligibility. The Transportation Committee forwarded the item to the Board of County Commissioners (BCC) with a favorable recommendation following a public hearing.
- Board:
- Transportation Cmte
- Date:
- 2026-07-14
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation by Transportation Committee; pending BCC Assignment.
- Applicant:
- Citizens' Independent Transportation Trust (CITT) / Miami-Dade County Department of Transportation and Public Works (DTPW)
PTP AMENDMENT FOR REIMBURSEMENT TO DTPW
Resolution approving an amendment to the FY 2026-30 Five-Year Implementation Plan of the People's Transportation Plan (PTP) to retroactively include the Purchase of 40-Foot Buses for I-95 Phase I and II project (CIP145), funded in part by Charter County Transportation Surtax Funds. The project involves the purchase of fifteen (15) 40-foot diesel and compressed Natural Gas (CNG) buses for I-95 Express Bus Service routes between Broward and Miami-Dade Counties. The buses previously served routes 195/295 and 196/296, which were discontinued in March 2020. DTPW issued a reimbursement payment of $3,896,702 to FDOT on January 12, 2026, using DTPW's Operating Fund, and this amendment authorizes the use of PTP capital funds to restore DTPW's operating fund resources. The Transportation Committee forwarded the item to the BCC with a favorable recommendation following a public hearing on 7/14/2026. The Board agenda date is 9/1/2026. The fiscal impact is $3,896,702. The project is included in the County's FY 2025-26 Adopted Budget and Multi-Year Capital Plan under Program No. 6730101, Site No. 300908. The discontinued bus routes primarily served District 3 and District 5. The request was made to advance the item to the July 21, 2026, Board meeting. The resolution was introduced on 6/22/2026 by the Citizens' Independent Transportation Trust. The staff recommendation is approval. The final action is not stated. The status is 'Before the Board'.
- Board:
- Transportation Cmte
- Date:
- 2026-07-14
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation following a public hearing (Transportation Committee, 7/14/2026); staff recommendation is approval; final action not stated
- Applicant:
- Citizens' Independent Transportation Trust (CITT), requested by Javier Betancourt, Executive Director; Department of Transportation and Public Works (DTPW)
PTP AMENDMENT FOR REIMBURSEMENT TO DTPW
Miami-Dade County Board of County Commissioners (BCC) is considering a resolution to amend the FY 2026-30 Five-Year Implementation Plan Update of the People's Transportation Plan (PTP). The amendment retroactively includes the purchase of fifteen (15) 40-foot diesel and compressed natural gas (CNG) buses for the I-95 Phase I and II Project (CIP145). These buses were purchased in January 2017 for $3,896,702 using FDOT grant funds for I-95 Express Bus Service routes. The routes were discontinued in March 2020 due to declining ridership and operator shortages. The buses were redeployed to other routes, which was inconsistent with FDOT's contractual requirements. FDOT requested reimbursement for the depreciated value and unauthorized mileage, and Miami-Dade County's Department of Transportation and Public Works (DTPW) issued a reimbursement payment of $3,896,702 on January 12, 2026. The PTP amendment is required to authorize the use of PTP capital funds to restore DTPW's operating fund resources and ensure compliance with PTP funding eligibility. The Transportation Committee forwarded the item to the BCC with a favorable recommendation following a public hearing.
- Board:
- Transportation Cmte
- Date:
- 2026-07-14
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation following a public hearing (Transportation Cmte); Pending BCC Assignment (Legislative Item)
- Applicant:
- Citizens' Independent Transportation Trust (CITT)
PTP AMENDMENT FOR REIMBURSEMENT TO DTPW
Resolution approving an amendment to the FY 2026-30 Five-Year Implementation Plan Update of the People's Transportation Plan (PTP) to retroactively include the Purchase of 40-Foot Buses for I-95 Phase I and II project (CIP145), funded in part by Charter County Transportation Surtax Funds. The project involves the purchase of fifteen (15) 40-foot diesel and compressed Natural Gas (CNG) buses for I-95 Express Bus Service routes between Broward and Miami-Dade Counties. The fiscal impact is $3,896,702. The buses were previously purchased with FDOT grant funds and placed into service in January 2017, but routes were discontinued in March 2020. FDOT requested reimbursement on September 9, 2024, and DTPW issued a reimbursement payment of $3,896,702 on January 12, 2026. The amendment authorizes use of PTP capital funds to restore DTPW's operating fund resources. The Transportation Committee forwarded the item to the BCC with a favorable recommendation following a public hearing on July 14, 2026. The Board agenda date is September 1, 2026. The item was introduced on June 22, 2026.
- Board:
- Transportation Cmte
- Date:
- 2026-07-14
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation following a public hearing (Transportation Committee, July 14, 2026); pending BCC approval
- Applicant:
- Citizens' Independent Transportation Trust (CITT), requested by Javier Betancourt, Executive Director; Department of Transportation and Public Works (DTPW)
PTP AMENDMENT FOR REIMBURSEMENT TO DTPW
Miami-Dade County Board of County Commissioners (BCC) is considering a resolution to amend the FY 2026-30 Five-Year Implementation Plan Update of the People's Transportation Plan (PTP). The amendment retroactively includes the purchase of fifteen (15) 40-foot diesel and compressed natural gas (CNG) buses for the I-95 Phase I and II project. These buses were purchased in January 2017 for $3,896,702 using State toll revenues and FDOT grants, intended for I-95 Express Bus Service routes. The routes were discontinued in March 2020 due to declining ridership and operator shortages. The buses were redeployed to other routes, which was inconsistent with FDOT's grant requirements. FDOT requested reimbursement, and Miami-Dade County's Department of Transportation and Public Works (DTPW) issued a payment of $3,896,702 on January 12, 2026, from DTPW's Operating Fund. The PTP amendment is required to authorize the use of PTP capital funds to restore DTPW's operating fund resources and ensure compliance with PTP funding eligibility. The Transportation Committee forwarded the item to the BCC with a favorable recommendation following a public hearing.
- Board:
- Transportation Cmte
- Date:
- 2026-07-14
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation by Transportation Committee; pending BCC Assignment.
- Applicant:
- Citizens' Independent Transportation Trust (CITT)
PTP AMENDMENT FOR REIMBURSEMENT TO DTPW
Resolution approving an amendment to the FY 2026-30 Five-Year Implementation Plan Update of the People's Transportation Plan (PTP) to retroactively include the Purchase of 40-Foot Buses for I-95 Phase I and II project (CIP145), funded in part by Charter County Transportation Surtax Funds. The project involves the purchase of fifteen (15) 40-foot diesel and compressed Natural Gas (CNG) buses for I-95 Express Bus Service routes between Broward and Miami-Dade Counties. The buses previously served routes 195/295 from Broward Boulevard to Downtown Miami and 196/296 connecting Sheridan Street to the Civic Center. The fiscal impact is $3,896,702. The item was forwarded to the Board of County Commissioners with a favorable recommendation following a public hearing. The Board agenda date is 9/1/2026. The request was made to advance the item to the July 21, 2026, Board meeting.
- Board:
- Transportation Cmte
- Date:
- 2026-07-14
- Type:
- Resolution
- Decision:
- Forwarded to BCC with a favorable recommendation following a public hearing
- Applicant:
- Citizens' Independent Transportation Trust (CITT), requested by Javier Betancourt, Executive Director; Department of Transportation and Public Works (DTPW)