HORIZON CONTRACTORS TO EXTEND CONTRACT BY 421 DAYS
Transportation Cmte · 2026-09-09 · resolution
Resolution approving Supplemental Agreement No. 1 with Horizon Contractors, Inc. for design-build services for roadway improvements to NW 84 Avenue from NW 58 Street to NW 74 Street, extending contract duration by 421 non-compensable calendar days. The project involves widening NW 84 Avenue from two to four lanes, including two dedicated transit lanes, drainage, roadway reconstruction, sidewalks, lighting, and related infrastructure. The extension is due to delays from third-party utility conflicts. The adjusted contract duration is 1,201 calendar days. No fiscal impact; contract amount remains $7,730,537.60. Status: In Committee. Agenda date 10/6/2026. Introduced 8/19/2026. No public comment sentiment stated.