JVA ENGINEERING CONTRACTORS, INC. FOR ROADWAY IMPROVEMENTS
Transportation Cmte · 2026-09-09 · resolution
Resolution authorizing Supplemental Agreement No. 1 with JVA Engineering Contractors, Inc. for design-build services for roadway improvements to NE 2nd Avenue from NE 20th Street to NE 36th Street, extending contract duration by 380 non-compensable calendar days from 420 to 800 calendar days. No additional compensation. The extension addresses schedule impacts from conflicts between existing electrical utility facilities and proposed storm drainage improvements. Original contract amount was $13,974,652. The project is in Commission District 3. The item was introduced on 8/19/2026 and is scheduled for the 10/6/2026 agenda. Status is In Committee. No public comment sentiment is stated.