9. BALANCE TO FINISH, PLUS RETAINAGE
City Commission Special Meeting · 2026-05-18 · agenda_item
The City of Wildwood is moving forward with the North Old Wire Road Waterline Replacement project. This project involves replacing existing waterlines and associated components. The project is currently in the payment and approval phase, with progress estimates and change orders being reviewed. This work will likely involve site clearing, underground utility work, pipe installation, and road and sidewalk repair. Contractors, suppliers, and service providers interested in future phases or related work should reach out to the City of Wildwood or its representatives early in the process. Early engagement can provide an advantage before final bid packages and permits are issued.
- Additions
- 38,073.37 $
- Total Contract Amount
- 496,041.16 $
- Net Change by Change Orders
- 38,073.37 $
- Total
- 534,114.53 $
- Retainage
- 20,233.21 $
- Balance to Finish
- 384,430.99 $
Industries that could win this work
- General Contractor
- Site Prep, Grading & Hardscape
- Concrete & Masonry
- Plumbing
- Utilities (Sub)
- Building & Industrial Supply
Follow this across meetings
Applicants and firms
Locations
See the actual businesses behind these numbers
Get the real filings, with addresses and officers, backed by a 14-day money-back guarantee.
Create your account