4. The City agrees to repair any damage caused by the City to F.D.O.T. facilities
City Commission Meeting · 2026-04-21 · agenda_item
The City of Ormond Beach is addressing an unexpected issue discovered during utility adjustments along Williamson Boulevard, specifically concerning a water main under Hand Avenue. The project involved relocating a 16-inch potable water main, but a 12-inch main was found in place. To ensure consistent 16-inch diameter and optimal performance for this critical interconnection between Ormond Beach and Daytona Beach, a new 16-inch water main was installed under Hand Avenue. This work has already been completed as an emergency procurement. The project involved site work and underground utility installation, specifically the replacement of a water main. Local contractors, suppliers, and service providers involved in underground utility work, concrete, and paving could find opportunities by engaging with the city early on future infrastructure projects, as this situation highlights the need for proactive planning and potential for unforeseen work.
- additional project cost
- 69,611.77 $
- 16-inch water main
- 16 inch
- 12-inch main
- 12 inch
- Joint Project Agreement
- 2023-214 Res. No.
- funding for the project
- 497,095 $
- project funding
- 2024-183 Res. No.
- water main
- 1993
- water main
- 2000
Industries that could win this work
- General Contractor
- Site Prep, Grading & Hardscape
- Plumbing
- Utilities (Sub)
- Building & Industrial Supply
Follow this across meetings
Applicants and firms
See the actual businesses behind these numbers
Get the real filings, with addresses and officers, backed by a 14-day money-back guarantee.
Create your account